Industrial cooling towers use PVC film fill - high surface area for heat transfer. During maintenance when the tower is dry (no water), welding/grinding sparks ignite the PVC fill. NFPA 214 covers tower protection and FM DS 3-23 sprinkler design plus maintenance precautions. Many major fires since 1980 are on record.

Tower Materials

Fire Scenarios

NFPA 214 Deluge

Mid-size tower 15 x 15 x 10 m, FM DS 3-23:

System Features

Maintenance and Hot Work

Cooling towers with SprinkCalc

SprinkCalc sizes cooling-tower deluge, K=160 nozzle count, 10.2 L/min/m2 flow and NFPA 214 / FM DS 3-23 compliance.

Download SprinkCalc on the App Store
Sources & Further Reading

NFPA 214, NFPA 51B, FM DS 3-23, CTI Bulletin ESG-152, IRI IM 8.1.1. NFPA 214 Cooling Tower standard.