Sprinklers activated. Fire controlled. Fire department left. The building's pumps are still running, water keeps flowing — and if it is left alone, thousands of litres pour onto the floor every minute. Now what? The answer to this critical question is the difference between months of insurance battles and days of downtime. NFPA 25 provides a clear roadmap for sprinkler system restoration — but in practice, most building management cannot execute these steps in sequence. Below is the restoration process as I have lived it on my own projects, step by step.

First Check: When to Shut the Water Off?

Don't close the water until you're sure the fire is completely out. The sprinkler system continues to operate until the fire department says "you can shut water off." No visible smoke doesn't mean the fire is dead — smouldering may continue inside insulation, above suspended ceilings or deep inside storage. After the fire officer approves, I never skip these three checks:

Step 1: Close the Control Valve for the Affected Area

After the fire is out, close the control valve for the affected zone. NFPA 25's approach is partial shutdown — only the fire zone, not the entire system. This keeps the rest of the building protected. The moment you close the valve, the tamper switch triggers a supervisory alarm — this is normal; don't forget to notify the monitoring center.

Step 2: Drainage

Open drain valves to empty water from the affected zone. The volume to drain can be 5-20 m³; a large-diameter hose or a permanent drain line is needed. Where the drain water may be discharged (environment, storm water, sewer) is regulated. Some municipalities require a contamination test of the discharged water, so ask the relevant authority before starting.

Step 3: Replace Operated and Damaged Sprinklers

Activated sprinklers cannot be reused. Each must be replaced. NFPA 25 requires:

Step 4: Pipe and Fitting Inspection

Physically inspect piping in the fire zone:

Step 5: Hydrostatic Test

Repaired or replaced piping is hydrostatically tested. Under NFPA 13-2025 the modified portion is isolated and tested as in 29.2.1: at not less than 200 psi (13.8 bar) for 2 hours, or 50 psi (3.4 bar) above static pressure where static pressure exceeds 150 psi (10.3 bar). Where the modification affects 20 sprinklers or fewer, or cannot be isolated, the test is at system working pressure (30.7.1). This test reveals hidden leak points. I isolate and test the fire-affected area first, then move on to the full system.

Step 6: Open Valve and Restore Supervision

Once hydrostatic test passes, slowly reopen the control valve (sudden opening causes water hammer). Verify the main valve's tamper switch returns to the open position through the monitoring center. Test the flow switch (inspector's test connection). Confirm from the panel that the system has returned to "supervised, ready" status.

Step 7: Documentation

NFPA 25 requires recording each stage of restoration. How many sprinklers activated, which heads were replaced, hydrostatic test results, time system returned to service. These documents are needed for the insurance claim and will come up again at the next annual NFPA 25 inspection. In my experience, anyone who does not file photos and serial numbers the same day ends up trying to remember them months later.

Sprinkler restoration checklist in MEP Calc

MEP Calc's fire category includes hydrostatic test calculations, drainage and a restoration checklist.

View on App Store

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report. One of the few tools that unifies all three major fire protection standards.

Download SprinkCalc on the App Store

Conclusion

Sprinkler activation is the system's success; fast and correct restoration is the operator's job. Botched restoration leaves the building defenseless against fire again, and insurance claims become difficult. Following NFPA 25's steps without shortcuts is the engineer's and building manager's responsibility.

Sources & Further Reading

Core reference: NFPA 25 - ITM of Water-Based Fire Protection Systems. Original NFPA post: NFPA Today - Sprinkler Systems Restoration.