Whether sprinklers are required does not come from a single number. The regulation ties the decision to a combination of four variables: occupancy class, building height, floor area, and the hazard or operational characteristics. So "above how many square metres do I need sprinklers" has no single answer.

The decision runs through four questions

  1. What is the occupancy class? Requirements differ for residential, office, retail, assembly, healthcare, education, hotels, industry, storage and car parks. Whether occupants can evacuate unaided (healthcare and care facilities) is decisive.
  2. Does the building fall into the high-rise class? Requirements tighten markedly for buildings classified as high-rise.
  3. What are the floor and total areas? As area grows, so does the expectation of compartmentation and automatic suppression.
  4. How hazardous is the activity? With flammable liquids, plastics storage, high-bay warehousing or a special process, the area threshold loses meaning and the hazard class takes over.

Thresholds are project-specific. Because the numerical limits in the regulation can change over time, the threshold for a given project must be confirmed from the current text published in the Official Gazette and from the authority's interpretation. This page explains the decision logic; it does not offer numbers to memorise.

Beyond the requirement: why fit sprinklers anyway?

A significant share of projects are designed with sprinklers where they are not mandatory. The reasons are:

What is required where sprinklers are not?

Without sprinklers the protection burden falls on the other layers: fire compartmentation, detection and alarm, smoke control, escape route design, hose reels and hydrants, portable extinguishers. None of these is a full substitute for automatic suppression, but together they can establish an acceptable level of risk.

Can protection be partial?

In some projects only the basement, car park or storage section is sprinklered. That is a workable approach for sections separated by fire compartmentation and assessed separately. The critical point is that the division between sprinklered and unsprinklered sections must be a real fire compartment; otherwise the sprinklered section's design has to account for fire arriving from the adjacent one.

How to justify it in the design report

  1. Occupancy class and occupant profile.
  2. Height status and the reasoning behind the classification.
  3. Floor areas and the compartmentation arrangement.
  4. Description of the activity, the goods stored and the storage height.
  5. The provision the sprinkler requirement rests on; where not mandatory, the reason for fitting them voluntarily.
  6. How the unsprinklered sections are protected.

Frequently Asked Questions

At what floor area do sprinklers become mandatory?

There is no single number. The decision depends on the combination of occupancy class, building height, floor area and the hazard of the activity; thresholds must be confirmed from the current regulation text.

Why fit sprinklers where they are not mandatory?

For insurance cover and premium, business continuity, the room they create for performance-based architectural solutions, and corporate investor standards.

Can protection be partial?

Yes, but the division between sprinklered and unsprinklered sections must be a real fire compartment. Otherwise the sprinklered section must account for fire arriving from next door.

Which layers matter most without sprinklers?

Fire compartmentation, detection and alarm, smoke control, escape route design, hose reels and hydrants, and portable extinguishers.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 86+ Engineering Calculators

MEP Calc bundles 86+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

The Turkish Regulation on Fire Protection of Buildings (BYKHY) · NFPA 13 (2025) · NFPA 20 (2025) · BS EN 12845:2015+A1:2019 · FM Global Data Sheets. For article numbers, thresholds and exemptions, the current regulation text published in the Official Gazette governs.

FS

Fatih Selvi

Mechanical engineer and software developer. 16+ years of MEP and fire protection field experience.