Fire design approval is not a single signature but several linked stages. What usually lengthens the process is not a technical error but getting the order of those stages wrong.

The stages

  1. Pre-application meeting. Once the architectural concept is settled, the conceptual approach is discussed with the reviewing authority (the administration authorised to issue building permits and, where it consults them, the fire service): compartmentation, escape strategy, which design standard will be used. Skipping this makes later revisions expensive.
  2. Fire safety / design report. Occupancy class, height status, capacity, fire load, chosen standard and design parameters are written down. The active systems derive from the decisions in this report.
  3. Detailed designs. Sprinkler, hose reel, hydrant, detection, smoke control, emergency lighting and signage designs, with hydraulic calculations and equipment schedules. Under BYKHY Article 6/4, fire detection and suppression designs are prepared separately from the building services designs, and the evacuation designs for floors with a floor area above 2,000 m² are prepared separately from the architectural drawings.
  4. Design approval. The designs are approved by the authority empowered to issue building permits, which checks that the fire suppression, detection and evacuation designs comply with the regulation (Article 6/4, 6/5). Depending on the administration, a fire service opinion may form part of this review. No building permit is issued for a design that does not comply (Article 5/1), and shortfalls are notified in writing. Where design or construction questions are open to interpretation, the written opinion of the Ministry of Environment, Urbanisation and Climate Change is obtained (Article 5/3).
  5. Revision and resubmission. Closing out the shortfalls; submitting a schedule of changes with each revision speeds this up.
  6. Installation and site inspection. Inspection during and at the end of installation; deviations from the approved design are recorded on as-built drawings.
  7. Acceptance and testing. Flow test, alarm test, pump performance test, smoke control functional test, with results captured in test records. At the occupancy permit stage the administration checks whether the installations comply with the regulation (Article 6/5); no occupancy permit or operating licence is issued until the shortfalls are corrected (Article 5/1).

The most common sequencing mistake: drawing the mechanical design before the architecture is fixed. When the ceiling level, a partition position or a rack height changes, the sprinkler layout and hydraulic calculation are redone from scratch. A pre-application meeting plus a design report is the only real protection against that repetition.

Which documents are asked for

DocumentContent
Design reportOccupancy class, hazard class, chosen standard, design parameters
Hydraulic calculationMost remote area calculation, pump duty point, water supply volume
System schematicsRiser diagram, valve arrangement, zone plan
Equipment scheduleSprinkler type and K-factor, pump, valves, detectors, with approval certificates
Layout drawingsFloor-by-floor sprinkler, detector, hose reel and hydrant layouts
Test recordsAt acceptance: flow, alarm, pump and functional tests

Six practices that shorten the process

Where acceptance testing most often stalls

  1. The pump performance curve not verified on site.
  2. Tank volume not meeting the design duration.
  3. Valve tamper switches not wired back to the panel (a monitored isolating valve on every zone or riser: Article 96/7).
  4. Sprinkler layout not meeting the obstruction rules (ducts, beams, lighting).
  5. No spare sprinkler cabinet and special wrenches (at least 6 spare heads: Article 96/8).
  6. Smoke control and fire detection not tested against the design scenarios.

Frequently Asked Questions

When should the fire authority be consulted?

A pre-application meeting once the architectural concept is settled, with detailed designs submitted after the design report. Skipping the pre-application makes later revisions expensive.

Which documents are required for approval?

Design report, hydraulic calculation, system schematics, equipment schedule with approval certificates, and floor-by-floor layouts; test records are added at acceptance.

What shortens the process most?

Stating the standard used from the start, giving a table reference for every design value, clouding revisions, and attaching equipment approval certificates with the first submission.

Where does acceptance testing most often stall?

An unverified pump curve, insufficient tank volume, tamper switches not wired to the panel, and sprinkler layouts breaching the obstruction rules.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 110+ Engineering Calculators

MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

The Turkish Regulation on Fire Protection of Buildings (BYKHY) · NFPA 13 (2025) · NFPA 20 (2025) · TS EN 12845+A2:2026 (EN 12845:2015+A2:2026) · FM Global Data Sheets. For article numbers and numerical limits, the current regulation text published in the Official Gazette governs.