Once a sprinkler system is installed, maintenance begins. NFPA 25 (Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems) prescribes exactly which check happens at which frequency. The operator's question is always the same: "What do I check this month?" This post summarizes weekly through 5-year ITM tasks in field language.

Weekly Checks

Monthly Checks

Quarterly Checks

Annual Checks

Three-Year Checks

Five-Year Checks

Common Gaps in Turkey

  1. Weekly round only on paper: Nobody walks the site; checklist is just a signature.
  2. Fire pump run skipped: Diesel battery dies from lack of 30-min runs; real fire, pump doesn't start.
  3. Internal pipe inspection never performed: Even on 15+ year-old systems.
  4. No log book: Without records, insurer or AHJ can't spot anomalies.

Conclusion

ITM is the heart of the sprinkler system. If you want your system to run 20 years, every frequency from weekly to 5-year needs disciplined execution. NFPA 25 Table 5.1 fits on one page — it should be on every facility manager's wall.

ITM schedule in MEP Calc

NFPA 25 frequency-based ITM calendar, reminders, and field log book.

View on App Store
Sources & Further Reading

Core reference: NFPA 25 Table 5.1 - ITM Frequencies. Original NFPA post: NFPA Today - ITM Frequencies.

FS

Fatih Selvi

Mechanical engineer and software developer. 16+ years of MEP and fire protection experience.