In BS EN 12845+A2:2026 commissioning is Clause 19 and consists of two subheadings: 19.1 Commissioning tests (TS p.120 / EN p.117) and 19.2 Completion certificate and documents (TS p.121 / EN p.118). This article gives the structure of the clause as it stands, reproduces the test pressures and durations with their source, and summarises the informative Annex J measures that apply where the system is out of service during commissioning.
The structure of Clause 19
| Clause | Heading |
|---|---|
| 19.1 | Commissioning tests |
| 19.1.1 | Pipework |
| 19.1.1.1 | Dry pipework |
| 19.1.1.2 | All pipework |
| 19.1.2 | Equipment |
| 19.1.3 | Water supplies |
| 19.2 | Completion certificate and documents |
There is no 19.3 or 19.4 in Clause 19, and there is no flushing provision. Flushing connections are in Clause 15.6 (TS p.112 / EN p.109), and the standard gives no flushing velocity or flow rate.
19.1.1.1: Pneumatic test of dry pipework
What the standard requires (TS p.120 / EN p.117): dry pipework must pass an air (pneumatic) test at 2.5 bar or more, held for at least 24 h. If leakage makes the pressure drop by more than 0.15 bar over those 24 h, the leak must be repaired.
Where the weather rules out running the 19.1.1.2 hydrostatic test straight after the pneumatic test, the hydrostatic test should follow as soon as conditions allow.
| Quantity | Value |
|---|---|
| Minimum test pressure | 2.5 bar |
| Minimum duration | 24 h |
| Maximum permitted pressure loss | 0.15 bar / 24 h |
19.1.1.2: Hydrostatic test of all pipework
What the standard requires (TS p.120 / EN p.117): the whole of the installation pipework must stay under hydrostatic pressure for at least 2 h; the test pressure is 15 bar or 1.5 times the highest pressure the system will experience, whichever is greater, with both figures referred to the installation control valves.
Faults found during the test, for example permanent distortion, rupture or leakage, must be rectified, after which the test is run again.
Care is also required so that no system component sees a pressure above the level its supplier recommends.
| Quantity | Value |
|---|---|
| Test pressure | 15 bar or 1.5 × maximum system pressure (whichever is the greater) |
| Point of measurement | The installation control valves |
| Minimum duration | 2 h |
The standard gives no separate hydrostatic pressure or duration for underground pipework; 19.1.1.2 applies to "all installation pipework".
For comparison, the informative Annex K (TS p.162 / EN p.159) recommends, for the inspection after 25 years, that the pipework be thoroughly flushed and hydrostatically tested to the maximum static pressure or 12 bar, whichever is the higher. That is a different threshold from the commissioning test.
19.1.2: Equipment
What the standard requires (TS p.120 / EN p.117): the system must be put through the 20.2.2 and 20.3.2 tests once, in other words the checks that will later recur as the weekly and quarterly routines, and every fault found must be corrected.
The two test packages that Clause 19.1.2 effectively calls up are these:
Clause 20.2.2 Weekly routine (TS p.122-123 / EN p.119-120):
- 20.2.2.2: all water and air pressure gauge readings on installations, trunk mains and pressure tanks; all water levels in elevated private reservoirs, rivers, canals, lakes and water storage tanks (including pump priming water tanks and pressure tanks); the correct position of all main stop valves. NOTE: in dry, alternate and pre-action installations the pipework pressure should not drop faster than 1.0 bar per week.
- 20.2.2.3: each water motor alarm shall be sounded for no less than 30 s.
- 20.2.2.4: on automatic pump sets, the fuel and engine lubricating oil levels are checked; the water pressure on the starting device is reduced, simulating the condition of automatic starting; when the pump set starts, the starting pressure is checked and recorded; on diesel pumps, the oil pressure and the flow of cooling water through open circuit cooling systems are checked.
- 20.2.2.5: the engine is run for 20 min (or for the time recommended by the supplier), then stopped and immediately restarted using the manual start test button; the water level in the primary circuit of closed circuit cooling systems is checked. Oil pressure, engine temperatures and coolant flow are monitored throughout the test; the oil hoses are checked and a general inspection is made for leakage of fuel, coolant or exhaust fumes.
- 20.2.2.6: heating systems to prevent freezing in the sprinkler system are checked for correct function.
Clause 20.3.2 Quarterly routine (TS p.123-124 / EN p.120-121): review of the hazard; sprinklers, multiple controls and sprayers; pipework and pipe supports; water supplies and their alarms (each water supply is tested with each control valve set in the system and the supply pressure at the appropriate flow shall be no less than the appropriate value in accordance with Clause 10); electrical supplies; stop valves; flow alarms; spare parts.
19.1.3: Water supplies
What the standard requires (TS p.120 / EN p.117): each water supply must be tested once following 8.6, and diesel engine driven pumps must be tested following 20.2.2.5.
Clause 8.6.1 General (TS p.48 / EN p.45): testing must use the test facility of 8.5.2. Every supply must be tested on its own, with the other supplies isolated. Whether the installation is pre-calculated or fully calculated, the supply must be tested at a flow no lower than the installation's maximum demand flow.
Clause 8.6.2 Storage tank and pressure tank supplies (TS p.48 / EN p.45): the stop valves between the water supply and the installation must be opened fully, and automatic starting of the pump set must be checked by lowering the system pressure. The flow must be verified against Clause 7, and the supply pressure read at the 'C' gauge must be confirmed to be no lower than the relevant Clause 7 value.
Clause 8.6.3 Town main, booster pump, elevated private reservoir and gravity tank supplies (TS p.49 / EN p.46): the stop valves shall be fully opened, automatic pump set starting shall be checked by reducing the system pressure, and the drain and test valve shall be adjusted to give the flow specified in Clause 7. Once the flow is steady, the supply pressure measured at the 'C' gauge shall be verified.
The test facility itself is defined in Clause 8.5 (TS p.47-48 / EN p.44-45): 8.5.1 requires permanently installed devices that measure pressure and flow, so that compliance with 7.3 and Clause 10 can be checked; the pressure readings that build the pressure/flow test curve must be taken only with an accurate test gauge (± 1.6 %), and at least three pressure/flow readings are required to form the curve, plus one pressure reading at zero flow. 8.5.2 requires the flow measuring device to be permanently installed at the pump house where the supply is by automatic pump sets, and 8.5.3 requires it to be permanently available on site (fixed or mobile) at the control valve sets where the supply is not by pumps, with facilities provided for the disposal of the test water.
19.2: Completion certificate and documents
What the standard requires (TS p.121 / EN p.118): the installer must hand the user two things:
- a completion certificate confirming that the system meets every applicable requirement of the standard, or listing any departures from those requirements;
- the full operating instructions and the 'as-built' design documents, in which every valve and instrument used for testing and operation is identified, accompanied by an inspection and checking programme for the user (20.2) and a schedule for service and maintenance (20.3).
The clause also carries a recommendation: where the local jurisdiction imposes no other requirement, every new or modified installation should be inspected by a third party once it is complete, and the resulting completion certificate, together with the relevant design documents, should be sent to the authorities.
Apart from this, Clause 19.2 gives no item by item minimum content list for the certificate.
Its counterpart on the labelling side is Clause 18.2.7 (TS p.120 / EN p.117): all valves and instruments used for testing and operating the system shall be suitably labelled and the corresponding identification shall be included in the documentation.
While the system is out of service: Annex J
During commissioning, alteration and repair the system may not be fully operational. The informative Annex J (TS p.160-161 / EN p.157-158) gives the measures to be taken during that period.
J.1 Minimizing the effects (TS p.160 / EN p.157): when a system is not fully operational, maintenance, alteration and repair work on it should be organized so that both the duration and the extent of the outage are kept as small as possible. While an installation is out of action, the user should take these steps:
- a) The authorities, and any central monitoring station, should be told.
- b) Alterations and repairs to the installation or its water supply should be done within normal working hours, unless Annex F has been applied.
- c) Supervisory staff in the affected areas should be informed, and continuous patrols of the area should be kept up.
- d) Hot work of any kind should require a permit. In the affected areas, smoking and naked lights should be banned for as long as the work continues.
- e) If the installation is still out of action outside working hours, all fire doors and fire shutters should be kept closed.
- f) Fire extinguishing appliances should be ready for use, with trained personnel on hand to operate them.
- g) The largest possible part of the installation should be kept in service by blanking off the pipework that feeds the part or parts under work.
- h) On manufacturing premises, where the alterations or repairs are extensive, where a pipe larger than 40 mm nominal diameter has to be disconnected, or where a main stop valve, alarm valve or non-return valve has to be overhauled or removed, every effort should be made to schedule the work for when the machinery is not running.
- i) A pump set that is out of commission should be isolated using the valves provided for it.
- j) Where possible, parts of the installation should be brought back into service overnight to give some protection, using blinders and blanks inside the pipework; each blinder and blank should carry a visible indicator tag and be numbered and logged so that it is removed in good time.
J.2 Planned shut-down (TS p.160-161 / EN p.157-158): permission to shut down a sprinkler installation or zone for any reason other than an emergency should come from the user alone. Before any whole or partial shut-down, every part of the premises should be checked to make sure there is no sign of fire.
J.3 Unplanned shut-down (TS p.161 / EN p.158): if an installation is put out of action urgently or by accident, the J.1 precautions should be applied, as far as they are relevant, with the least possible delay, and the authorities concerned should also be informed as soon as possible.
J.4.1 Action following sprinkler operation (TS p.161 / EN p.158): once an installation has operated and been shut down, the sprinklers that opened should be replaced with heads of the correct type and temperature rating and the water supply should be restored. Unopened sprinklers around the operating area should be inspected for heat or other damage and replaced where needed. Water to an installation or zone that has operated should stay on until the fire is completely out, and only the fire service should decide to shut down an installation or zone that has operated because of a fire. The user should keep any component taken out of the system so that an authority can examine it if required.
Field note
The wording of Clause 19.1.2, "the system shall be tested once as specified in 20.2.2 and 20.3.2", takes the commissioning protocol out of the realm of a separate document: the weekly and quarterly routine forms are filled in for the first time at commissioning and the same forms are repeated throughout operation. This makes the commissioning records comparable with the maintenance records in the same format. (This paragraph is engineering commentary.)
Frequently Asked Questions
How does EN 12845 define the hydrostatic test?
Under BS EN 12845+A2:2026 Clause 19.1.1.2 (TS p.120 / EN p.117), every part of the installation pipework must be hydrostatically tested for at least 2 h. The test pressure is 15 bar or 1.5 times the highest pressure the system will experience, whichever is greater, both measured at the installation control valves. Faults the test reveals (for example permanent distortion, rupture or leakage) must be corrected and the test repeated, and no system component may be exposed to a pressure above the supplier's recommended value.
How is dry pipework tested?
Clause 19.1.1.1 (TS p.120 / EN p.117): dry pipework must be tested with air at 2.5 bar or more for at least 24 h, and any leak that makes the pressure fall by more than 0.15 bar over those 24 h must be repaired. If the weather prevents the 19.1.1.2 hydrostatic test from being done straight after the pneumatic test, it should be done as soon as conditions allow.
Does Clause 19 contain a flushing provision?
No. Clause 19.1 is headed 'Commissioning tests' and consists of three subclauses: 19.1.1 Pipework, 19.1.2 Equipment, 19.1.3 Water supplies. Flushing connections are governed by Clause 15.6 (TS p.112 / EN p.109), and the standard gives no flushing velocity or flow rate.
What does the completion certificate contain?
Clause 19.2 (TS p.121 / EN p.118) requires the installer to give the user a completion certificate confirming that the system meets every applicable requirement of the standard, or listing any departures from them, plus the full operating instructions and 'as-built' design documents identifying every valve and instrument used for testing and operation, an inspection and checking programme for the user (20.2) and a schedule for service and maintenance (20.3).
Can hot work be carried out while the system is out of service?
Annex J.1 d) (informative, TS p.160 / EN p.157) recommends that all hot work be controlled through a permit system and that smoking and naked lights be banned in the affected areas for as long as the work continues. Hot work is therefore not prohibited but made subject to a permit; what is prohibited is smoking and naked lights.
References
- BS EN 12845+A2:2026 Clauses 19.1.1.1, 19.1.1.2, 19.1.2, 19.1.3 (TS p.120 / EN p.117)
- BS EN 12845+A2:2026 Clause 19.2 Completion certificate and documents (TS p.121 / EN p.118)
- BS EN 12845+A2:2026 Clause 18.2.7 Testing and operating devices (TS p.120 / EN p.117)
- BS EN 12845+A2:2026 Clause 8.5.1 Test facility devices (TS p.47-48 / EN p.44-45)
- BS EN 12845+A2:2026 Clauses 8.5.2, 8.5.3, 8.6.1, 8.6.2 (TS p.48 / EN p.45)
- BS EN 12845+A2:2026 Clause 8.6.3 (TS p.49 / EN p.46)
- BS EN 12845+A2:2026 Clause 15.6 Flushing connections (TS p.112 / EN p.109)
- BS EN 12845+A2:2026 Clause 20.2.2 Weekly routine (TS p.122-123 / EN p.119-120)
- BS EN 12845+A2:2026 Clause 20.3.2 Quarterly routine (TS p.123-124 / EN p.120-121)
- BS EN 12845+A2:2026 Annex J (informative), J.1 and J.2 (TS p.160 / EN p.157)
- BS EN 12845+A2:2026 Annex J, continuation of J.2, J.3, J.4.1 (TS p.161 / EN p.158)
- BS EN 12845+A2:2026 Annex K (informative) (TS p.162 / EN p.159)

SprinkCalc — Fire Sprinkler Design Across Three Standards
SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.
Download SprinkCalc on the App Store
MEP Calc — 110+ Engineering Calculators
MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.
Download MEP Calc on the App StoreBS EN 12845+A2:2026 (EN 12845:2015+A2:2026) Fixed firefighting systems — Automatic sprinkler systems — Design, installation and maintenance; BS EN 12845-2:2025 (EN 12845-2:2024) ESFR and CMSA sprinkler systems. Every figure in this article is taken from the published standard text; clause, table and page references are listed under References. General information only, not a substitute for the standard or for a design review.