Above suspended ceilings, beneath raised floors, in roof voids and intermediate landings — invisible spaces become the silent route for fire spread. Clause 7.7 keeps its exemption criteria tight, and a single millimetre outside the limit means sprinklers.

In one shopping centre fire, flame spread not through the retail units but through the 1.1 m ceiling void carrying services between the shops and the plant level above. The design had applied the "below 0.8 m, no sprinklers required" exemption; the dimension existed on paper, but on site the void reached 1.1 m. The shopfronts held, while the concealed space above turned into a flame machine. The Clause 7.7 exemption criteria cannot be accepted without being verified once more on site.

Clause 7.7 — concealed space exemption criteria

A concealed space may be left without sprinklers only if it satisfies all of the following:

All three at once — no "approximately" version of any of them is acceptable. If the height exceeds 0.80 m at any point, that area needs sprinklers; "an average of 0.75 m" is not a valid defence.

Typical concealed space types

Void typeTypical heightFire riskSprinklers required?
Suspended ceiling (office)0.4–0.9 mLow (PVC cable)Yes if above 0.8 m
Suspended ceiling (retail/restaurant)0.6–1.5 mModerate (ductwork, cable)Usually yes
Raised floor (data centre)0.3–0.9 mHigh (cable, airflow)Yes where combustible load exists
Roof void (timber)0.5–3.0 mHigh (timber)Always
Roof void (concrete)0.1–0.4 mLowUsually exempt
Intermediate landing1.0–2.5 mVariableYes, depending on use

Choosing the sprinkler type for a void

Pipework design detail in voids

Field error — the cabling under a raised floor was overlooked

A bank data centre's first-phase design had a 0.55 m raised floor void, densely cabled. It was accepted as exempt because it was below 0.8 m. But the cable insulation was PVC rather than halogen-free, so the combustible load criterion was breached. Six months later an insurance audit recorded the deviation and the system was retrofitted — 240 sprinklers, a new alarm valve and connections, and two and a half months of additional project work. Skipping criterion (b) means criterion (a) alone is not enough.

Testing and drainage in voids

Void sprinklers are included in normal system testing through the zone test connection, but physical access is limited:

Ductwork and obstructions

A void is usually full of ductwork, cable ladders and mechanical services. The obstruction rules apply:

Comparison with NFPA 13

NFPA 13 sets its concealed space exemption on similar criteria: under 6 in (about 0.15 m) with non-combustible construction, or under 32 in (about 0.81 m) with no combustible load. The numbers are close. NFPA is stricter on combustible construction — a timber-joisted roof void almost always requires sprinklers. The structural fire resistance criterion in Clause 7.7(c) is interpreted more tightly on the NFPA side, and the European-American difference in interpretation should be stated in the design documents.

Link to Turkish regulation

BYKHY refers to EN 12845 and NFPA 13 and has no separate clause on concealed spaces. However, its compartmentation provisions require voids not to defeat fire spread barriers, so a concealed space left without sprinklers must maintain compartment continuity through REI 60/90 dampers and firestopping at service penetrations. Sprinkler exemption and firestopping are considered together; without one, the other is incomplete.

Quick check list

Frequently Asked Questions

When can a concealed space be left without sprinklers?

Only when all three criteria are met at once: the void is under 0.80 m high, contains no meaningful combustible material, and is enclosed in fire-resisting construction.

Does cable insulation count as combustible load?

Yes. PVC cable insulation is enough to breach the combustible content criterion, which is why densely cabled raised floors usually require sprinklers even below 0.8 m.

What sprinkler type suits a ceiling void?

Pendent or upright heads at K80 to K115, typically 68 °C, with fast-response bulbs where airflow is high and a higher temperature rating in hot voids.

How is a void system inspected?

Through access hatches every 9 m. Corrosion risk is high because of condensation, so galvanised or internally coated pipe is recommended and voids are sampled at the three-yearly internal inspection.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 86+ Engineering Calculators

MEP Calc bundles 86+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

BS EN 12845:2015+A1:2019 Fixed firefighting systems — Automatic sprinkler systems. EN 12845-2:2024 (CMSA & ESFR sprinkler systems). NFPA 13 Standard for the Installation of Sprinkler Systems. Turkish Regulation on Fire Protection of Buildings (BYKHY). FM Global Property Loss Prevention Data Sheet 2-0.

FS

Fatih Selvi

Mechanical engineer and software developer with field experience in MEP and fire protection, working actively with NFPA, FM Global and BS EN 12845 on site projects.