Inspector test connection, alarm test valve, low-point drain, drainage branch. Properly designed drainage is what makes a system genuinely testable; inadequate drainage means years of tests that were never really carried out.

At one logistics facility, opening the zone test connection released about 1500 L of water across the floor, so for four years the team cut the test short to protect the wall finishes. No drainage had been designed — just a cap. An insurer audit established that the quarterly tests had been abbreviated, and the report was reissued as "test could not be performed". The premium rose sharply at renewal. If the drainage branch required by the installation clauses is missing, every test in the maintenance clauses is left hanging.

Drainage provisions

System drainage

Every control valve set has a main drain valve for emptying the system. Sizing:

Inspector test connection

Taken from the most remote or hydraulically most demanding point of the system, with a test orifice matching the smallest K-factor orifice in the system. During the flow simulation:

Low-point drains

Water collects at the low points of horizontal pipework, which is a freezing risk in a dry system in particular. The solution:

Hydraulic sizing of the drainage branch

System sizeDesign flow (L/min)Drain sizeDrain capacity (L/min)
LH small225DN50about 250
OH2 medium540DN50about 250
OH3 large900DN65about 450
HHP31620DN80about 700
HHS33250DN100about 1200
HHS448752 × DN100about 2400

The 25 % figure is the practical floor. Where the insurer or authority requires drainage at full design flow, a separate test loop is designed.

Test loops and water reuse

A test sends a large fraction of the design flow to drain for three to fifteen minutes. The water loss is significant:

Where it does not compromise tank cleanliness, test water can be returned to the pump suction as a closed-loop test. This is the preferred design for water conservation, but flow and pressure measurements must then be taken with a calibrated flow meter.

Field error — the drainage pit overflowed

At a textile warehouse a 0.5 × 0.5 × 0.3 m drainage pit had been built beside the control valve. When the quarterly test started 540 L/min flowing, the pit filled in twenty seconds and water spread across the warehouse floor, soaking 200 m² of raw fabric. No capacity calculation had been done; "a small pit will do" had been the assumption. The drainage clause requires capacity at 25 % of design flow — which means a connection to an open channel or gully, not a pit.

Drainage route design rules

Fire service connection and drainage

A drain valve is provided on the fire service connection so that residual water can be removed after the fire service has finished pumping. In freeze-prone areas the connection pipe is kept dry, with automatic drainage beneath the main check valve. Check it visually daily and functionally each year.

Comparison with NFPA 13 and NFPA 25

NFPA 13 requires a main drain capable of carrying the full flow — at least 2 in, roughly DN50 — which is effectively the same as EN 12845 in practice. NFPA 25 requires the inspector test connection to be at the most remote point with an orifice matching the smallest K-factor, the same approach as EN 12845. Low-point drains appear on the NFPA side as "auxiliary drains", located at each drum drip rather than at a fixed interval. The two standards run parallel on drainage philosophy.

Link to Turkish regulation

BYKHY has no separate drainage clause; it is applied through the EN 12845 and NFPA references. Because of that gap, drainage branches in Turkey are frequently left at the level of "empty it with a bucket". This is one of the most common deviations recorded in insurance audits: if the quarterly test cannot be reported, the periodic inspection is downgraded to conditional. Drainage design has to be verified physically on site, not only on paper.

Quick check list

Frequently Asked Questions

How large must the main drain be?

At least DN50, with a discharge capacity of 25 % of the design flow. Large systems need DN65 to DN100, or twin DN100 runs on the highest-demand storage systems.

Where is the inspector test connection taken from?

From the most remote or hydraulically most demanding point of the system, with a test orifice matching the smallest K-factor orifice installed.

Is a drainage pit acceptable?

Generally not. A pit of a few hundred litres fills in seconds at design flow. The discharge needs a connection to an open channel or gully sized for the drain capacity.

How often are low-point drains needed?

At least one every 90 m of horizontal pipework, DN15–25, in an accessible position, labelled and locked so they are not opened by mistake.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 86+ Engineering Calculators

MEP Calc bundles 86+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

BS EN 12845:2015+A1:2019 Fixed firefighting systems — Automatic sprinkler systems. EN 12845-2:2024 (CMSA & ESFR sprinkler systems). NFPA 13 Standard for the Installation of Sprinkler Systems. Turkish Regulation on Fire Protection of Buildings (BYKHY). FM Global Property Loss Prevention Data Sheet 2-0.

FS

Fatih Selvi

Mechanical engineer and software developer with field experience in MEP and fire protection, working actively with NFPA, FM Global and BS EN 12845 on site projects.