On a European-owned logistics warehouse project, the third-party insurance survey arrives with an unexpected finding: the pump room sits inside the main building, separated only by one-hour construction, and is not even sprinkler protected. The project had been approved against BYKHY Article 93 and TS EN 12845, and the mechanical team had also laid out the pump room to NFPA 20. The surveyor cited FM Global DS 3-7 Section 2.2.1.2: the pump should be in a detached noncombustible building at least 15 m from the protected buildings; where that is not feasible it should be separated from the rest of the building by two-hour fire-rated construction, reduced to one hour only when the pump room and adjacent areas are sprinkler protected. The design was revised at significant cost. This article summarises DS 3-7 (April 2012, Interim Revision April 2025) in practical terms — the rules that make sure a fire pump is in the right place, with the right connections and the right control logic.

Pump Room Location and Construction

FM Global's strictest requirement concerns pump room separation, given at three levels:

The pump room may not be located within or attached to an unprotected building (2.2.1.2 D). Sprinklers are provided over engine-driven pumps (2.2.1.5). The pump room may not be used for storage — the most frequently violated clause on site, where material stacked in a corner produces an immediate non-conformance at survey.

Alarm Requirements

DS 3-7 requires the alarm set to report to a constantly attended location. For an electric pump, four alarms as a minimum:

For a diesel pump the four alarms reporting to the constantly attended location are: diesel driver running, loss of power (AC and/or DC), controller off/in manual/in test position, and failure to start. In addition, four visual or audible notifications are provided (2.2.1.12.1): overspeed, low oil pressure, high coolant temperature and engine failure. These four need not be monitored at a central location and may be combined into a single general pump trouble alarm. Alarm operation is verified at least annually, for example during the annual flow test (2.2.1.12.2).

Suction Piping — The Red Lines

Suction piping is the section most often rejected at survey. The key rules:

Discharge Piping and Relief Valves

Pump Sizing and Selection

The governing DS 3-7 rule is that the pump must deliver at least 65% of rated pressure at 150% of rated flow (Section 2.4). So a pump rated 5,000 L/min at 10 bar must still produce at least 6.5 bar at 7,500 L/min. The 140% limit on churn pressure is not in DS 3-7; it comes from BYKHY Article 93 (see below). DS 3-7 sizes the pump to Qmax: one 100% Qmax pump or three 50% Qmax pumps, with up to 140% of rated flow usable with a single pump and up to 110% with multiple pumps (2.4.6).

Mechanical seals (2.4.5) are used only on pumps specifically FM Approved for mechanical shaft seals, and only where all of the following apply: the suction water is clean and no water source is an open body of water (retention pond, lake or river); suction pressure is positive at all flows; a spare split seal set is kept on site; and the pump is tested weekly.

Controllers, Sequence Starting and Weekly Testing

An FM Approved fire pump controller is mandatory. The key control rules:

Practical Differences From NFPA 20

A Recurring Surprise at Survey

A common pattern on industrial sites: a diesel fire pump is installed to a design accepted by the local authority under BYKHY and also checked against NFPA 20. Months later a customer supplier audit or an insurer survey reports that the installation does not comply with DS 3-7, typically for three reasons:

The remedy is straightforward but disruptive: sprinklers added over the pump room, the backflow preventer relocated, and the alarm panel connected to the building management system. Taking DS 3-7 as the baseline at design stage would have covered all three at a fraction of the cost.

When FM Compliance Is Required in Practice

The Turkish fire regulation (BYKHY) sets fire pump performance rules itself in Article 93: churn (zero-flow) head at most 140% of rated head, head at 150% of rated flow not below 65% of rated head, use for system demands up to 130% of rated flow, and a standby pump of equal capacity where a single pump is used. Under Article 96(5) the pump arrangement feeding the sprinklers is also part of the TS EN 12845 design. The regulation does not reference NFPA 20 or FM data sheets; these apply as an added layer that must still meet its minimum requirements. FM compliance becomes binding through other routes:

The practical advice is to ask the question explicitly at design stage: will FM compliance be required? Even if the insurer has not been selected, the owner may move the portfolio within a few years, and designing FM compliant from the start avoids a costly retrofit later.

Quick Checklist

Frequently Asked Questions

Why does FM require a detached pump room or two-hour separation?

Because the pump must survive the fire it is there to fight. A pump room inside the protected building, separated by one hour and unsprinklered, can be lost early in an incident, taking the water supply with it. A detached building at 15 m, or two-hour separation (one hour where the pump room and adjacent areas are sprinklered), keeps the pump available for the duration.

Why is a backflow preventer prohibited on the pump suction?

Anything on the suction side that can restrict flow threatens the pump's ability to start and run at full demand, and a backflow preventer adds significant friction loss exactly where NPSH margin is scarce. Where one is required for water authority reasons, it goes on the discharge side instead.

Why an eccentric rather than a concentric reducer at the suction?

A concentric reducer creates a high point at the top of the pipe where air collects, and that air pocket is drawn into the pump when it starts, causing loss of prime. DS 3-7 therefore requires an eccentric tapered reducer arranged so that no air pocket forms (2.3.2.3); in practice this means the flat side up.

Why must the fire pump be stopped manually?

So that someone confirms the emergency is genuinely over before the water supply is removed. An automatic stop at churn pressure can shut the pump down while the fire is still developing, and it also causes repeated short-cycle running that wears the pump. DS 3-7 therefore arranges the controller for manual stopping and has any run-period timer defeated (2.4.7.3, 2.4.10.1).

What does the 150% at 65% rule actually mean?

It defines the required shape of the pump curve. DS 3-7 Section 2.4 requires at least 65% of rated pressure at 150% of rated flow; the limit of 140% at churn comes from BYKHY Article 93, not from DS 3-7. This guarantees the pump still delivers useful pressure if actual fire demand exceeds the design figure, rather than collapsing off the end of its curve.

How does FM DS 3-7 differ most from NFPA 20 in practice?

Equipment approval and pump room separation. FM accepts only FM Approved pumps, drivers, controllers and relief valves, where NFPA accepts listed components. And FM requires a detached building or two-hour separation (one hour if the pump room and adjacent areas are sprinklered), where NFPA 20 (2025) accepts one hour only when the pump room and the exposing building are fully sprinklered (Table 4.14.1.1.2). Those two differences account for most of the findings raised at survey.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 110+ Engineering Calculators

MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

FM Global Property Loss Prevention Data Sheet DS 3-7, Fire Protection Pumps, April 2012, Interim Revision April 2025 (Sections 2.1-2.4.16); related data sheets DS 3-11 (flow and pressure regulating devices) and DS 2-81 (inspection, testing and maintenance, April 2019, Interim Revision April 2026, Table 2.9.1.1 and Appendix C Table C-1); BYKHY Articles 93 and 96(5); NFPA 20 (2025) and NFPA 25 for comparison (NFPA 25 not verified against the source text).