NFPA 25 covers the inspection, testing and maintenance (ITM) of water-based fire protection systems. This series works through the standard chapter by chapter as checklists you can turn into a site form. The first page is Chapter 8: the fire pump assembly and the pump room. How a pump is installed is the job of NFPA 20 (see the Fire Pumps series); NFPA 25 says what to check on that pump for the rest of its life, how often and against which criterion. Every line below carries its clause number in NFPA 25-2026.

In short: The pump room, pump, electrical and diesel systems get a weekly visual inspection (8.2.2). The no-flow (churn) test is weekly for diesel pumps and weekly or monthly for electric pumps depending on the installation; an electric pump runs for at least 10 minutes, a diesel pump for at least 30 (8.3.1, 8.3.2.3, 8.3.2.4). Once a year a flow test is run: for a constant-speed pump at no flow, rated flow and 150 percent of rated flow (8.3.3.1). Net pressure at every point must be at least 95 percent of the original curve (8.3.7.2.3). The owner receives a written report (8.4.1).

A. General rules: where the frequency comes from

Chapter 8 gives the minimum requirements for routine ITM of pump assemblies installed to NFPA 20 or another approved installation standard (8.1.1.1). The minimum frequency must follow both the manufacturer’s instructions and Table 8.1.1.2 (8.1.1.2), so the more frequent of the two governs.

CheckCriterionClause
☐ Common components and valvesInspected, tested and maintained to Chapter 138.1.2
☐ Suspected obstructionChapter 14 obstruction investigation8.1.3
☐ Protection out of serviceChapter 15 impairment procedures8.1.9
☐ Suction supplyProvides the required flow at or above the lowest permissible suction pressure to meet system demand8.1.5.1
☐ Installation where NFPA 20 allowed negative suction gauge pressureCompliant if the pump and water supply can still meet system demand8.1.5.2
☐ Energy sourceSupplies the brake horsepower the driver needs for the pump to meet system demand8.1.6
☐ DriverDoes not overload beyond its rating (including service factor allowance) at the required brake horsepower8.1.7
☐ ControllerAutomatic and manual controllers suit the type of pump used8.1.8
☐ Preventive maintenance programmeCovers all pump assembly components per the manufacturer’s recommendations or an approved alternative plan; starts immediately after the acceptance tests are passed8.5.1, 8.5.3

Auxiliary equipment is part of the programme too (8.1.4): the pump shaft coupling, automatic air release valve, pressure gauges and circulation relief valve (not used with a diesel drive that has a heat exchanger); pump test devices; the pump relief valve and piping (where the maximum pump discharge pressure exceeds the rating of system components or the driver is variable speed); alarm sensors and indicators; right-angle gear sets on engine-driven vertical shaft turbine pumps; and the pressure maintenance (jockey) pump with its accessories.

B. Frequency summary: Table 8.1.1.2

The standard’s summary table is below. Rows marked "—" have no separate frequency in the table; the clause says which test the check goes with (relief valves, for example, during every pump test).

ItemFrequencyClause
Inspection
AlignmentAnnually8.3.6.4
Cable/wire insulationAnnually8.1.1.2.5
Circulation relief valve—8.2.3.3
Diesel engine systemWeekly8.2.2(4)
Electric systemWeekly8.2.2(3)
Engine crankcase breatherQuarterly8.1.1.2.12
Exhaust system, drain condensate trap and silencersAnnually8.1.1.2.13
Flexible hoses and connectionsAnnually8.1.1.2.11
Fuel tank vents and overflowAnnually8.1.1.2.10
Main relief valve—8.2.4
Plumbing parts — inside and outside of panelsAnnually8.1.1.2.6
Printed circuit board (PCB) corrosionAnnually8.1.1.2.4
PumpWeekly8.2.2(2)
Pump house/roomWeekly8.2.2(1)
Shaft movement or end play while runningAnnually8.1.1.2.1
Steam pump systemWeekly8.2.2(5)
Suction screensAnnually8.3.3.16
Test
Automatic transfer switch and emergency/standby generatorsPer NFPA 1108.3.6.2
Diesel-engine-driven fire pump (no flow)Weekly8.3.1.1
Diesel fuel testingAnnually8.3.4.1
Electric-motor-driven fire pump (no flow)Weekly/monthly8.3.1.2
Electronic control module (ECM)Annually8.3.3.17
Fire pump alarm signalsAnnually8.3.3.14
Flow metersAnnually8.3.3.5.3
Fuel tank, float switch and interstitial-space supervisory signalQuarterly8.1.1.2.7
Gauges, transducers and other devices used for testingAnnually8.3.3.5.2
Main pressure relief valveAnnually8.3.3.12, 13.5.6.2.3
Positive displacement pump activation time (flow)Annually8.3.5.8
Pump house/room environmental conditions—8.3.6.3
Pump operation (no flow)Weekly/monthly8.3.2, 8.3.5
Pump performance (flow)Annually8.3.3, 8.3.5
Supervisory signal for high cooling water temperatureAnnually8.1.1.2.8
Maintenance
BatteriesAnnually8.1.1.2.15
Circulating water filterAnnually8.1.1.2.22
Control and power wiring connectionsAnnually8.1.1.2.16
Controller and all other pump assembly componentsPer manufacturer8.5
Diesel active fuel maintenance systemAnnually or per manufacturer8.3.4.3
Diesel engine systemPer manufacturer8.5
Electric motor and power systemPer manufacturer8.5
Electrical connectionsAnnually8.1.1.2.2
Engine lubricating oil50 operating hours or annually8.1.1.2.17
Engine oil filter50 operating hours or annually8.1.1.2.18
Fuel filter50 operating hours or annually8.1.1.2.19
Fuel tank — check for water and foreign materialAnnually8.1.1.2.9
Measure back pressure on engine turboAnnually8.1.1.2.14
Power transmission parts with elastomeric materials (incl. torsional couplings)5 years or per manufacturer8.1.1.2.24
Pressure gauges and sensorsAnnually8.1.1.2.23
Pump and motor bearings and couplingAnnually or as required8.1.1.2.3
Sacrificial anodeAnnually8.1.1.2.21

C. Weekly inspection: pump room

The weekly inspection confirms that the pump assembly appears to be in operating condition and free from physical damage (8.2.1).

CheckCriterionClause
☐ Heat (electric pump, or diesel pump with engine heaters)Room at least 4 °C (40 °F)8.2.2(1)(a)
☐ Heat (diesel pump without engine heaters)Room at least 21 °C (70 °F)8.2.2(1)(b)
☐ Ventilating louvresFree to operate8.2.2(1)(c)
☐ FloorNo excessive water collecting8.2.2(1)(d)
☐ Coupling guardIn place8.2.2(1)(e)

D. Weekly inspection: pump system

CheckCriterionClause
☐ Suction, discharge and bypass valvesFully open8.2.2(2)(a)
☐ PipingFree of leaks8.2.2(2)(b)
☐ Suction line pressure gaugeReading within acceptable range8.2.2(2)(c)
☐ System line pressure gaugeReading within acceptable range8.2.2(2)(d)
☐ Suction reservoirAt the required water level8.2.2(2)(e)
☐ Wet pit suction screensIn place and unobstructed8.2.2(2)(f)
☐ Waterflow test valves and hose connection valveClosed; line to test valves free of water8.2.2(2)(g)
☐ Suction pressure regulating valveFully open8.2.2(2)(h)

E. Weekly inspection: electrical system

CheckCriterionClause
☐ Controller power-on pilot lightIlluminated8.2.2(3)(a)
☐ Transfer switch normal pilot lightIlluminated8.2.2(3)(b)
☐ Isolating switch — standby (emergency) sourceClosed8.2.2(3)(c)
☐ Reverse phase alarm pilot lightOff, or normal phase rotation light on8.2.2(3)(d)
☐ Oil level in vertical motor sight glassWithin acceptable range8.2.2(3)(e)
☐ Pressure maintenance (jockey) pumpPower provided8.2.2(3)(f)

F. Weekly inspection: diesel engine and steam system

CheckCriterionClause
☐ Fuel tankAt least two-thirds full8.2.2(4)(a)
☐ Controller selector switchIn auto position8.2.2(4)(b)
☐ Voltage readings of both batteriesWithin acceptable range8.2.2(4)(c)
☐ Charging current readings of both batteriesWithin acceptable range8.2.2(4)(d)
☐ Battery pilot lightsBoth battery lights on, or both battery failure lights off8.2.2(4)(e)
☐ Alarm pilot lightsAll off8.2.2(4)(f)
☐ Engine running time meterReading8.2.2(4)(g)
☐ Right-angle gear drive oil levelWithin acceptable range8.2.2(4)(h)
☐ Crankcase oil levelWithin acceptable range8.2.2(4)(i)
☐ Cooling water levelWithin acceptable range8.2.2(4)(j)
☐ Battery electrolyte levelWithin acceptable range8.2.2(4)(k)
☐ Battery terminalsFree from corrosion8.2.2(4)(l)
☐ Water-jacket heaterOperating8.2.2(4)(m)
☐ Steam-driven pump: steam pressure gaugeReading within acceptable range8.2.2(5)

G. Relief valves

CheckCriterionClause
☐ Circulation relief valve (where installed)Inspected at the no-flow test frequency; water flows through it while the pump runs at shutoff (churn) so the pump does not overheat8.2.3.1, 8.2.3.2
☐ Circulation relief valve, after a testAfter every pump test the valve has closed automatically and discharge has stopped at normal supply pressure8.2.3.3
☐ Main pressure relief valve (where installed), every pump testValve and trim free of physical damage and not leaking8.2.4.1, 8.2.4.2(1)
☐ Main pressure relief valve, discharge pressurePressure downstream of the relief valve fittings in the discharge piping does not exceed the rating of system components8.2.4.2(2)
☐ Main pressure relief valve, settingAnnually: correctly adjusted to relieve at the correct pressure and close below that setting8.2.4.3

H. No-flow (churn) test

Frequency

PumpTest frequencyClause
☐ Diesel-engine-driven pumpWeekly; another frequency may be set by an approved risk analysis8.3.1.1
☐ Electric pump serving systems in buildings beyond the pumping capacity of the fire departmentWeekly8.3.1.2.1(1)
☐ Electric pump with a limited service controllerWeekly8.3.1.2.1(2)
☐ Electric vertical turbine pumpWeekly8.3.1.2.1(3)
☐ Electric pump taking suction from ground-level tanks or a source with no material pressure value without the pumpWeekly8.3.1.2.1(4)
☐ Other electric pumpsMonthly8.3.1.2.2
☐ Electric pump systems with a redundant fire pumpMonthly8.3.1.2.3
☐ Electric pump with an approved risk analysisAs set by the risk analysis8.3.1.2.4

Running the test

CheckCriterionClause
☐ StartingThe pump is started automatically8.3.2.2
☐ Run timeElectric pump at least 10 minutes, diesel pump at least 30 minutes8.3.2.3, 8.3.2.4
☐ Automatic timerPermitted; on a pressure-actuated controller a solenoid valve drain on the pressure control line initiates the start and the program shows as a pressure drop on the pressure recorder8.3.2.6–8.3.2.6.3
☐ PersonnelQualified personnel attend whenever the pump runs; the timer does not remove this8.3.2.7, 8.3.2.7.1
☐ Remotely monitored automated testingPermitted per Section 4.7; every checklist item is still covered and abnormalities recorded; diesel controllers need automatic engine shutdown (NFPA 20 12.7.2.7); qualified personnel can reach the pump within 4 hours of an abnormal condition8.3.2.10
☐ Main relief valveMay weep but not discharge a significant quantity of water8.3.2.1.1
☐ Circulation relief valveDischarges a small flow; does not operate when flow through the main relief valve is more than weeping8.3.2.1.1.1, 8.3.2.1.1.2
☐ Valve installed to open as a safety featureMay discharge water8.3.2.5

Where a pump was installed under NFPA 20 1993 or earlier and the design relies on the main relief valve to keep discharge pressure below component ratings, both valves may operate as designed; suction and discharge readings are then recorded, a difference above 95 percent of rated pump pressure is investigated and corrected, and the discharge water temperature is monitored (8.3.2.1.2–8.3.2.1.2.2).

Pump not running

CheckCriterionClause
☐ Suction and discharge gaugesReadings recorded8.3.2.8(1)
☐ Electronic pressure sensor controlCurrent, highest and lowest pressure from the controller event log recorded (where available without opening an energized controller)8.3.2.8(2)
☐ Pressure outside the expected rangeAll event log information that helps identify the abnormality recorded8.3.2.8(3)

Pump running

CheckCriterionClause
☐ Pump starting pressureRecorded from the pressure switch or transducer8.3.2.9(1)(a)
☐ Suction and discharge gaugesReadings recorded8.3.2.9(1)(b)
☐ Packing glandsSlight discharge; gland nuts adjusted if necessary8.3.2.9(1)(c), (d)
☐ Noise and vibrationNothing unusual8.3.2.9(1)(e)
☐ Packing boxes, bearings, pump casingNot overheating8.3.2.9(1)(f)
☐ Pressure switch/transducer readingRecorded and compared with the discharge gauge8.3.2.9(1)(g)
☐ Electronic pressure sensor controlCurrent, highest and lowest pressure from the event log recorded8.3.2.9(1)(h)
☐ Electric motor and radiator-cooled diesel pumpsCirculation relief valve checked for discharge8.3.2.9(1)(i)
☐ Suction pressure regulating valveBled or drained to confirm the sensing line, speed controls and connections are clear and the valve works8.3.2.9(1)(j)
☐ Electric motorTime to full speed observed; time on first step (reduced voltage or current starting) and run time after start (automatic stop controllers) recorded8.3.2.9(2)(a)–(c)
☐ Diesel engineCrank time and time to running speed observed; oil pressure, speed, water and oil temperature indicators watched; abnormalities recorded; heat exchanger checked for cooling water flow8.3.2.9(3)(a)–(e)
☐ Steam turbineSteam gauge reading recorded; time to running speed observed8.3.2.9(4)(a), (b)

I. Annual flow test

Qualified personnel run the annual test, controlling discharge through approved test devices. For measurement and curve comparison in detail, see fire pump performance test.

CheckCriterionClause
☐ Constant-speed pump: test pointsNo flow (churn), rated flow and 150 percent of rated flow8.3.3.1
☐ Variable-speed pump under variable-speed controlNo flow and 25, 50, 75, 100, 125 and 150 percent of rated flow8.3.3.2
☐ Variable-speed pump under constant-speed controlNo flow, 100 and 150 percent8.3.3.3
☐ Suction supply cannot deliver 150 percentTest at 100 percent and at the maximum flow allowed at the lowest permissible suction pressure8.3.3.4
☐ Test arrangementHose streams, or bypass flowmeter to drain or suction reservoir, at least every third year; closed-loop metering back to suction may be used 2 out of every 3 years8.3.3.9
☐ Closed-loop testRecirculating water temperature monitored; results inconsistent with the previous year are repeated with hose streams, or if that is impossible the flowmeter is calibrated and the test repeated8.3.3.9.3.2–8.3.3.9.3.4
☐ Before flowing hose streamsOwner or representative told the location, approximate flow and duration8.3.3.9.1.2
☐ At no flowCirculation relief valve checked for discharge and pressure relief valve (if installed) for proper operation8.3.3.10(1)
☐ At each flow conditionMotor voltage and current on all lines (where the controller has external means), pump speed, and simultaneous suction pressure, discharge pressure and flow recorded8.3.3.10(2)
☐ Before shutdownElectric pump has run at least 10 minutes, diesel pump at least 308.3.3.10(3), (4)
☐ Several pumps needed together to meet demandEach flow condition repeated with all pumps running8.3.3.11
☐ Pressure relief valveAt every flow condition, watch whether discharge pressure exceeds component operating pressure and whether the valve closes at the right pressure; if closed to reach rated characteristics, reset at the end of the test8.3.3.12–8.3.3.12.2
☐ Automatic transfer switch (where installed)Simulate a power failure with the pump at peak load; switch transfers to the alternate source; record voltage, current, rpm, suction and discharge pressure; pump keeps running at peak horsepower load for at least 2 minutes; on removing the failure, it reconnects to normal power after a time delay. Overcurrent devices (fuses or breakers) must not open8.3.3.13
☐ Alarm conditionsSimulated at the sensor locations and confirmed; sensors that cannot be reached without opening an energized controller are tested at an alternative point outside it8.3.3.14, 8.3.3.14.1
☐ Suction screensInspected and cleared after the flowing part of the annual test or a system activation8.3.3.16
☐ Engines with electronic fuel managementBackup ECM and primary and redundant ECM sensors tested annually8.3.3.17
☐ Pump–driver alignmentParallel and angular alignment inspected at the annual test and corrected8.3.6.4
☐ Pump room environmentHeating, ventilation and lighting equipment tested for proper manual or automatic operation8.3.6.3

J. Test equipment and calibration

CheckCriterionClause
☐ Test equipmentCalibrated equipment to determine net pump pressure, flow through the pump and speed8.3.3.5
☐ LabelGauges, transducers and other measuring devices labelled with the latest calibration date8.3.3.5.1
☐ Gauges and transducers (other than flow meters)Calibrated at least annually to ±1 percent8.3.3.5.2
☐ Flow metersCalibrated annually to ±3 percent8.3.3.5.3
☐ Discharge and sensing orificesThose visible without disassembly free of damage and obstruction8.3.3.6
☐ Discharge orificesListed, or built to a recognised standard with a known discharge coefficient8.3.3.8

K. Evaluating the results

CheckCriterionClause
☐ Acceptance 1Pump meets the flow and pressure of the most demanding system(s) it supplies, from owner-provided design information8.3.7.2.3(1)
☐ Acceptance 2Pump supplies 100 percent of rated flow8.3.7.2.3(2)
☐ Acceptance 3Net pressure at each flow point at least 95 percent of the original manufacturer’s curve, the original unadjusted field test curve or a curve generated from the nameplate8.3.7.2.3(3)
☐ Acceptance 48.1.5 (suction supply) met8.3.7.2.3(4)
☐ Suction supply cannot test beyond 100 percentAcceptable if all other requirements are met8.3.7.2.3.1
☐ Raising speedIncreasing engine speed beyond rated pump speed to meet rated performance is not permitted8.3.7.2.2
☐ Constant-speed electric pump currentAt each flow point and phase, not above service factor × full-load amperage; otherwise find and correct the cause8.3.7.2.5, 8.3.7.2.6
☐ Electric pump at varying voltageTest voltage × current not above voltage × full-load current × service factor; otherwise find and correct the cause8.3.7.2.7, 8.3.7.2.8
☐ Motor voltageWithin 5 percent below to 10 percent above nameplate voltage is acceptable8.3.7.2.9
☐ Who evaluatesQualified personnel; net flow performance is compared with the manufacturer’s original performance, gross performance with the demand of connected systems8.3.7.1.1, 8.3.7.1.1.1, 8.3.7.1.2

If the criteria are not met

  • The owner is notified in writing and the cause is investigated (8.3.7.2.4(1), (2)).
  • Failure to provide the maximum system demand is an impairment (8.3.7.2.4(3)).
  • Excessive vibration or excessively worn or loose components are a deficiency; degraded performance that still meets demand is a noncritical deficiency (8.3.7.2.4(4), (5)).
  • Corrections are reported to the owner in writing, and the owner keeps a record of the investigation and corrective action (8.3.7.2.4(6), 8.3.7.2.10).

L. Diesel fuel

CheckCriterionClause
☐ Fuel degradation testAt least annually; at minimum fuel quality testing to ASTM D975 or ASTM D6751, depending on fuel type, as approved by the engine manufacturer8.3.4.1, 8.3.4.1.1
☐ Fuel found deficientRecondition or replace the fuel, clean the tank internally and change the engine fuel filter(s)8.3.4.2
☐ After restorationRetest every 6 months until experience shows the fuel keeps at least 1 year without degradation8.3.4.2.1
☐ Active fuel maintenance system (where provided)Listed for fire pump service; maintained per the manufacturer, at least annually for parts with no stated frequency; additives per the manufacturer8.3.4.3–8.3.4.3.3
☐ Fuel tank, float switch and interstitial-space supervisory signalTested quarterly for liquid intrusion8.1.1.2.7
☐ Fuel tankTested annually for water and foreign material8.1.1.2.9
☐ Fuel tank vents and overflow pipingInspected annually for obstruction8.1.1.2.10

M. Annual and periodic inspection and maintenance items

Energized controller rule: Electrical connections, PCB corrosion, cable insulation, plumbing leaks in panels, control and power wiring, and gauge/sensor accuracy are checked to the extent the work can be done without opening an energized electric fire pump controller. The isolating switch in a compartment separate from the other controller components may be used for these checks (8.1.1.2.2.1, 8.1.1.2.2.2 and the related clauses). Section 4.11 applies when working near electric-motor-driven fire pumps (8.3.3.15.1).

ItemFrequency and criterionClause
☐ Shaft movement / end playAnnually, with the pump running8.1.1.2.1
☐ Electrical connectionsInspected annually, repaired as needed8.1.1.2.2.1
☐ Pump and motor bearings, couplingsGreased annually or as required8.1.1.2.3
☐ Printed circuit boardsInspected annually for corrosion8.1.1.2.4.1
☐ Cable/wire insulationInspected annually for cracking8.1.1.2.5.1
☐ Plumbing parts inside and outside panelsInspected annually for leaks8.1.1.2.6.1
☐ High cooling water temperature supervisory circuitTested annually8.1.1.2.8
☐ Flexible hoses and connectionsInspected annually for cracks and leaks8.1.1.2.11
☐ Engine crankcase breatherInspected quarterly8.1.1.2.12
☐ Exhaust system, drain condensate traps, silencersInspected annually8.1.1.2.13
☐ Turbo back pressureMeasured annually8.1.1.2.14
☐ BatteriesAnnually: test specific gravity, state of charge and charger rates; clean terminals; cranking voltage above 9 V on a 12 V system or 18 V on a 24 V system; distilled water only8.1.1.2.15
☐ Control and power wiring connectionsInspected annually, repaired as needed8.1.1.2.16.1
☐ Engine oil and oil filterChanged every 50 operating hours or annually8.1.1.2.17, 8.1.1.2.18
☐ Fuel filtersChanged annually (the table gives 50 operating hours or annually); more often if the manufacturer recommends8.1.1.2.19, 8.1.1.2.20
☐ Sacrificial anodesCondition inspected annually, replaced as needed8.1.1.2.21
☐ Circulating water filtersReplaced annually8.1.1.2.22
☐ Gauge and sensor accuracyAnnually; replaced or recalibrated when more than 5 percent out of calibration, with PPE per NFPA 70E or an approved equivalent8.1.1.2.23, 8.1.1.2.23.2
☐ Power transmission parts with elastomeric materials (torsional couplings)Replaced every 5 years or as the component manufacturer requires8.1.1.2.24

N. Generators, transfer switches and other tests

CheckCriterionClause
☐ Engine generator sets supplying emergency/standby power to the pumpTested routinely per NFPA 1108.3.6.1
☐ Automatic transfer switchesTested and exercised routinely per NFPA 1108.3.6.2

O. Positive displacement pumps

CheckCriterionClause
☐ GeneralTested to 8.3.1–8.3.3 except where 8.3.5 differs8.3.5.1
☐ Flow testUsing a flowmeter or orifice plate in a test loop (to the supply tank, the pump inlet or drain); reading matches the manufacturer’s performance data; flow as specified at system design pressure8.3.5.3, 8.3.5.4, 8.3.5.6
☐ If orifice plates are usedOrifice size and upstream pressure to maintain are given to the AHJ8.3.5.5
☐ Pumps for liquids other than waterMay be tested with water; manufacturer’s calculation of the viscosity difference provided8.3.5.8, 8.3.5.9
☐ Water mist PD pumping unit activation testAnnually and after every modification; with an arrangement simulating the smallest nozzle, system design pressure reached within the listed time and not more than 60 seconds8.3.5.10.1, 8.3.5.10.2

P. Report and records

A complete written report of the pump test results is prepared for and kept by the owner (8.4.1). At minimum it contains (8.4.1.1):

  • All raw data for a full evaluation: suction and discharge pressure, voltage and current (as far as possible without opening an energized controller) and pump speed at each flow tested
  • The fire protection system demand as furnished by the owner
  • Whether pump performance is satisfactory or unsatisfactory
  • Deficiencies found in testing and analysis, with recommendations
  • The manufacturer’s performance data, actual performance and the pump discharge curves the standard requires
  • Time delays for starting, stopping and energy source transfer
  • Comparison with previous results where applicable

Records are kept of all work on the pump, driver, controller and auxiliary equipment (8.5.2).

Q. Adjusting, repairing and replacing components

When a pump component is adjusted, repaired, rebuilt or replaced, the tests needed to return the system to service follow Table 8.6.1 (8.6.1). Depending on the component and the action, the table calls for anything from an NFPA 20 acceptance test to an 8.3.2 no-flow test; NFPA 20 is consulted for design, installation and acceptance testing (8.6.2). Replacement parts keep the listing of the pump component assembly wherever possible; if the original manufacturer no longer supplies the part, an approved like part may be used (8.6.3, 8.6.3.1).

Frequently Asked Questions

How often must a fire pump be run under NFPA 25?

A diesel-engine-driven pump gets a weekly no-flow (churn) test and runs for at least 30 minutes (8.3.1.1, 8.3.2.4). An electric pump is run weekly where it serves buildings beyond fire department pumping capacity, has a limited service controller, is a vertical turbine or takes suction from a ground-level tank; otherwise, and in systems with a redundant pump, monthly; it runs for at least 10 minutes (8.3.1.2, 8.3.2.3). An approved risk analysis may set a different frequency.

What is the minimum pump room temperature?

At least 4 °C (40 °F) with an electric pump or a diesel pump with engine heaters, and at least 21 °C (70 °F) with a diesel pump without engine heaters (8.2.2(1)(a), (b)). It is checked at the weekly inspection.

At which flows is the pump tested annually?

A constant-speed pump at no flow, rated flow and 150 percent of rated flow (8.3.3.1). A variable-speed pump under variable-speed control at no flow and 25 to 150 percent in 25 percent steps; under constant-speed control at no flow, 100 and 150 percent (8.3.3.2, 8.3.3.3).

When is the annual test acceptable?

When the pump meets the most demanding system demand and 100 percent of rated flow, net pressure at every flow point is at least 95 percent of the original manufacturer’s curve, the original field test curve or the nameplate curve, and the suction supply requirement of 8.1.5 is met (8.3.7.2.3).

Can a closed-loop flowmeter be used for the annual test every year?

No. Hose streams or a bypass flowmeter to drain or the suction reservoir are used at least every third year; closed-loop metering is allowed 2 out of every 3 years (8.3.3.9). If closed-loop results are inconsistent with the previous year, the test is repeated with hose streams (8.3.3.9.3.3).

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 110+ Engineering Calculators

MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

NFPA 25-2026, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems: Chapter 8 (8.1–8.6), Table 8.1.1.2 and Table 8.6.1. The content of NFPA 20, NFPA 70E, NFPA 110 and ASTM D975/D6751 referenced by Chapter 8 is not reproduced here.