NFPA 25 covers the inspection, testing and maintenance (ITM) of water-based fire protection systems. This series works through the standard chapter by chapter as checklists you can turn into a site form. The first page is Chapter 8: the fire pump assembly and the pump room. How a pump is installed is the job of NFPA 20 (see the Fire Pumps series); NFPA 25 says what to check on that pump for the rest of its life, how often and against which criterion. Every line below carries its clause number in NFPA 25-2026.
In short: The pump room, pump, electrical and diesel systems get a weekly visual inspection (8.2.2). The no-flow (churn) test is weekly for diesel pumps and weekly or monthly for electric pumps depending on the installation; an electric pump runs for at least 10 minutes, a diesel pump for at least 30 (8.3.1, 8.3.2.3, 8.3.2.4). Once a year a flow test is run: for a constant-speed pump at no flow, rated flow and 150 percent of rated flow (8.3.3.1). Net pressure at every point must be at least 95 percent of the original curve (8.3.7.2.3). The owner receives a written report (8.4.1).
A. General rules: where the frequency comes from
Chapter 8 gives the minimum requirements for routine ITM of pump assemblies installed to NFPA 20 or another approved installation standard (8.1.1.1). The minimum frequency must follow both the manufacturer’s instructions and Table 8.1.1.2 (8.1.1.2), so the more frequent of the two governs.
| Check | Criterion | Clause |
|---|---|---|
| ☐ Common components and valves | Inspected, tested and maintained to Chapter 13 | 8.1.2 |
| ☐ Suspected obstruction | Chapter 14 obstruction investigation | 8.1.3 |
| ☐ Protection out of service | Chapter 15 impairment procedures | 8.1.9 |
| ☐ Suction supply | Provides the required flow at or above the lowest permissible suction pressure to meet system demand | 8.1.5.1 |
| ☐ Installation where NFPA 20 allowed negative suction gauge pressure | Compliant if the pump and water supply can still meet system demand | 8.1.5.2 |
| ☐ Energy source | Supplies the brake horsepower the driver needs for the pump to meet system demand | 8.1.6 |
| ☐ Driver | Does not overload beyond its rating (including service factor allowance) at the required brake horsepower | 8.1.7 |
| ☐ Controller | Automatic and manual controllers suit the type of pump used | 8.1.8 |
| ☐ Preventive maintenance programme | Covers all pump assembly components per the manufacturer’s recommendations or an approved alternative plan; starts immediately after the acceptance tests are passed | 8.5.1, 8.5.3 |
Auxiliary equipment is part of the programme too (8.1.4): the pump shaft coupling, automatic air release valve, pressure gauges and circulation relief valve (not used with a diesel drive that has a heat exchanger); pump test devices; the pump relief valve and piping (where the maximum pump discharge pressure exceeds the rating of system components or the driver is variable speed); alarm sensors and indicators; right-angle gear sets on engine-driven vertical shaft turbine pumps; and the pressure maintenance (jockey) pump with its accessories.
B. Frequency summary: Table 8.1.1.2
The standard’s summary table is below. Rows marked "—" have no separate frequency in the table; the clause says which test the check goes with (relief valves, for example, during every pump test).
| Item | Frequency | Clause |
|---|---|---|
| Inspection | ||
| Alignment | Annually | 8.3.6.4 |
| Cable/wire insulation | Annually | 8.1.1.2.5 |
| Circulation relief valve | — | 8.2.3.3 |
| Diesel engine system | Weekly | 8.2.2(4) |
| Electric system | Weekly | 8.2.2(3) |
| Engine crankcase breather | Quarterly | 8.1.1.2.12 |
| Exhaust system, drain condensate trap and silencers | Annually | 8.1.1.2.13 |
| Flexible hoses and connections | Annually | 8.1.1.2.11 |
| Fuel tank vents and overflow | Annually | 8.1.1.2.10 |
| Main relief valve | — | 8.2.4 |
| Plumbing parts — inside and outside of panels | Annually | 8.1.1.2.6 |
| Printed circuit board (PCB) corrosion | Annually | 8.1.1.2.4 |
| Pump | Weekly | 8.2.2(2) |
| Pump house/room | Weekly | 8.2.2(1) |
| Shaft movement or end play while running | Annually | 8.1.1.2.1 |
| Steam pump system | Weekly | 8.2.2(5) |
| Suction screens | Annually | 8.3.3.16 |
| Test | ||
| Automatic transfer switch and emergency/standby generators | Per NFPA 110 | 8.3.6.2 |
| Diesel-engine-driven fire pump (no flow) | Weekly | 8.3.1.1 |
| Diesel fuel testing | Annually | 8.3.4.1 |
| Electric-motor-driven fire pump (no flow) | Weekly/monthly | 8.3.1.2 |
| Electronic control module (ECM) | Annually | 8.3.3.17 |
| Fire pump alarm signals | Annually | 8.3.3.14 |
| Flow meters | Annually | 8.3.3.5.3 |
| Fuel tank, float switch and interstitial-space supervisory signal | Quarterly | 8.1.1.2.7 |
| Gauges, transducers and other devices used for testing | Annually | 8.3.3.5.2 |
| Main pressure relief valve | Annually | 8.3.3.12, 13.5.6.2.3 |
| Positive displacement pump activation time (flow) | Annually | 8.3.5.8 |
| Pump house/room environmental conditions | — | 8.3.6.3 |
| Pump operation (no flow) | Weekly/monthly | 8.3.2, 8.3.5 |
| Pump performance (flow) | Annually | 8.3.3, 8.3.5 |
| Supervisory signal for high cooling water temperature | Annually | 8.1.1.2.8 |
| Maintenance | ||
| Batteries | Annually | 8.1.1.2.15 |
| Circulating water filter | Annually | 8.1.1.2.22 |
| Control and power wiring connections | Annually | 8.1.1.2.16 |
| Controller and all other pump assembly components | Per manufacturer | 8.5 |
| Diesel active fuel maintenance system | Annually or per manufacturer | 8.3.4.3 |
| Diesel engine system | Per manufacturer | 8.5 |
| Electric motor and power system | Per manufacturer | 8.5 |
| Electrical connections | Annually | 8.1.1.2.2 |
| Engine lubricating oil | 50 operating hours or annually | 8.1.1.2.17 |
| Engine oil filter | 50 operating hours or annually | 8.1.1.2.18 |
| Fuel filter | 50 operating hours or annually | 8.1.1.2.19 |
| Fuel tank — check for water and foreign material | Annually | 8.1.1.2.9 |
| Measure back pressure on engine turbo | Annually | 8.1.1.2.14 |
| Power transmission parts with elastomeric materials (incl. torsional couplings) | 5 years or per manufacturer | 8.1.1.2.24 |
| Pressure gauges and sensors | Annually | 8.1.1.2.23 |
| Pump and motor bearings and coupling | Annually or as required | 8.1.1.2.3 |
| Sacrificial anode | Annually | 8.1.1.2.21 |
C. Weekly inspection: pump room
The weekly inspection confirms that the pump assembly appears to be in operating condition and free from physical damage (8.2.1).
| Check | Criterion | Clause |
|---|---|---|
| ☐ Heat (electric pump, or diesel pump with engine heaters) | Room at least 4 °C (40 °F) | 8.2.2(1)(a) |
| ☐ Heat (diesel pump without engine heaters) | Room at least 21 °C (70 °F) | 8.2.2(1)(b) |
| ☐ Ventilating louvres | Free to operate | 8.2.2(1)(c) |
| ☐ Floor | No excessive water collecting | 8.2.2(1)(d) |
| ☐ Coupling guard | In place | 8.2.2(1)(e) |
D. Weekly inspection: pump system
| Check | Criterion | Clause |
|---|---|---|
| ☐ Suction, discharge and bypass valves | Fully open | 8.2.2(2)(a) |
| ☐ Piping | Free of leaks | 8.2.2(2)(b) |
| ☐ Suction line pressure gauge | Reading within acceptable range | 8.2.2(2)(c) |
| ☐ System line pressure gauge | Reading within acceptable range | 8.2.2(2)(d) |
| ☐ Suction reservoir | At the required water level | 8.2.2(2)(e) |
| ☐ Wet pit suction screens | In place and unobstructed | 8.2.2(2)(f) |
| ☐ Waterflow test valves and hose connection valve | Closed; line to test valves free of water | 8.2.2(2)(g) |
| ☐ Suction pressure regulating valve | Fully open | 8.2.2(2)(h) |
E. Weekly inspection: electrical system
| Check | Criterion | Clause |
|---|---|---|
| ☐ Controller power-on pilot light | Illuminated | 8.2.2(3)(a) |
| ☐ Transfer switch normal pilot light | Illuminated | 8.2.2(3)(b) |
| ☐ Isolating switch — standby (emergency) source | Closed | 8.2.2(3)(c) |
| ☐ Reverse phase alarm pilot light | Off, or normal phase rotation light on | 8.2.2(3)(d) |
| ☐ Oil level in vertical motor sight glass | Within acceptable range | 8.2.2(3)(e) |
| ☐ Pressure maintenance (jockey) pump | Power provided | 8.2.2(3)(f) |
F. Weekly inspection: diesel engine and steam system
| Check | Criterion | Clause |
|---|---|---|
| ☐ Fuel tank | At least two-thirds full | 8.2.2(4)(a) |
| ☐ Controller selector switch | In auto position | 8.2.2(4)(b) |
| ☐ Voltage readings of both batteries | Within acceptable range | 8.2.2(4)(c) |
| ☐ Charging current readings of both batteries | Within acceptable range | 8.2.2(4)(d) |
| ☐ Battery pilot lights | Both battery lights on, or both battery failure lights off | 8.2.2(4)(e) |
| ☐ Alarm pilot lights | All off | 8.2.2(4)(f) |
| ☐ Engine running time meter | Reading | 8.2.2(4)(g) |
| ☐ Right-angle gear drive oil level | Within acceptable range | 8.2.2(4)(h) |
| ☐ Crankcase oil level | Within acceptable range | 8.2.2(4)(i) |
| ☐ Cooling water level | Within acceptable range | 8.2.2(4)(j) |
| ☐ Battery electrolyte level | Within acceptable range | 8.2.2(4)(k) |
| ☐ Battery terminals | Free from corrosion | 8.2.2(4)(l) |
| ☐ Water-jacket heater | Operating | 8.2.2(4)(m) |
| ☐ Steam-driven pump: steam pressure gauge | Reading within acceptable range | 8.2.2(5) |
G. Relief valves
| Check | Criterion | Clause |
|---|---|---|
| ☐ Circulation relief valve (where installed) | Inspected at the no-flow test frequency; water flows through it while the pump runs at shutoff (churn) so the pump does not overheat | 8.2.3.1, 8.2.3.2 |
| ☐ Circulation relief valve, after a test | After every pump test the valve has closed automatically and discharge has stopped at normal supply pressure | 8.2.3.3 |
| ☐ Main pressure relief valve (where installed), every pump test | Valve and trim free of physical damage and not leaking | 8.2.4.1, 8.2.4.2(1) |
| ☐ Main pressure relief valve, discharge pressure | Pressure downstream of the relief valve fittings in the discharge piping does not exceed the rating of system components | 8.2.4.2(2) |
| ☐ Main pressure relief valve, setting | Annually: correctly adjusted to relieve at the correct pressure and close below that setting | 8.2.4.3 |
H. No-flow (churn) test
Frequency
| Pump | Test frequency | Clause |
|---|---|---|
| ☐ Diesel-engine-driven pump | Weekly; another frequency may be set by an approved risk analysis | 8.3.1.1 |
| ☐ Electric pump serving systems in buildings beyond the pumping capacity of the fire department | Weekly | 8.3.1.2.1(1) |
| ☐ Electric pump with a limited service controller | Weekly | 8.3.1.2.1(2) |
| ☐ Electric vertical turbine pump | Weekly | 8.3.1.2.1(3) |
| ☐ Electric pump taking suction from ground-level tanks or a source with no material pressure value without the pump | Weekly | 8.3.1.2.1(4) |
| ☐ Other electric pumps | Monthly | 8.3.1.2.2 |
| ☐ Electric pump systems with a redundant fire pump | Monthly | 8.3.1.2.3 |
| ☐ Electric pump with an approved risk analysis | As set by the risk analysis | 8.3.1.2.4 |
Running the test
| Check | Criterion | Clause |
|---|---|---|
| ☐ Starting | The pump is started automatically | 8.3.2.2 |
| ☐ Run time | Electric pump at least 10 minutes, diesel pump at least 30 minutes | 8.3.2.3, 8.3.2.4 |
| ☐ Automatic timer | Permitted; on a pressure-actuated controller a solenoid valve drain on the pressure control line initiates the start and the program shows as a pressure drop on the pressure recorder | 8.3.2.6–8.3.2.6.3 |
| ☐ Personnel | Qualified personnel attend whenever the pump runs; the timer does not remove this | 8.3.2.7, 8.3.2.7.1 |
| ☐ Remotely monitored automated testing | Permitted per Section 4.7; every checklist item is still covered and abnormalities recorded; diesel controllers need automatic engine shutdown (NFPA 20 12.7.2.7); qualified personnel can reach the pump within 4 hours of an abnormal condition | 8.3.2.10 |
| ☐ Main relief valve | May weep but not discharge a significant quantity of water | 8.3.2.1.1 |
| ☐ Circulation relief valve | Discharges a small flow; does not operate when flow through the main relief valve is more than weeping | 8.3.2.1.1.1, 8.3.2.1.1.2 |
| ☐ Valve installed to open as a safety feature | May discharge water | 8.3.2.5 |
Where a pump was installed under NFPA 20 1993 or earlier and the design relies on the main relief valve to keep discharge pressure below component ratings, both valves may operate as designed; suction and discharge readings are then recorded, a difference above 95 percent of rated pump pressure is investigated and corrected, and the discharge water temperature is monitored (8.3.2.1.2–8.3.2.1.2.2).
Pump not running
| Check | Criterion | Clause |
|---|---|---|
| ☐ Suction and discharge gauges | Readings recorded | 8.3.2.8(1) |
| ☐ Electronic pressure sensor control | Current, highest and lowest pressure from the controller event log recorded (where available without opening an energized controller) | 8.3.2.8(2) |
| ☐ Pressure outside the expected range | All event log information that helps identify the abnormality recorded | 8.3.2.8(3) |
Pump running
| Check | Criterion | Clause |
|---|---|---|
| ☐ Pump starting pressure | Recorded from the pressure switch or transducer | 8.3.2.9(1)(a) |
| ☐ Suction and discharge gauges | Readings recorded | 8.3.2.9(1)(b) |
| ☐ Packing glands | Slight discharge; gland nuts adjusted if necessary | 8.3.2.9(1)(c), (d) |
| ☐ Noise and vibration | Nothing unusual | 8.3.2.9(1)(e) |
| ☐ Packing boxes, bearings, pump casing | Not overheating | 8.3.2.9(1)(f) |
| ☐ Pressure switch/transducer reading | Recorded and compared with the discharge gauge | 8.3.2.9(1)(g) |
| ☐ Electronic pressure sensor control | Current, highest and lowest pressure from the event log recorded | 8.3.2.9(1)(h) |
| ☐ Electric motor and radiator-cooled diesel pumps | Circulation relief valve checked for discharge | 8.3.2.9(1)(i) |
| ☐ Suction pressure regulating valve | Bled or drained to confirm the sensing line, speed controls and connections are clear and the valve works | 8.3.2.9(1)(j) |
| ☐ Electric motor | Time to full speed observed; time on first step (reduced voltage or current starting) and run time after start (automatic stop controllers) recorded | 8.3.2.9(2)(a)–(c) |
| ☐ Diesel engine | Crank time and time to running speed observed; oil pressure, speed, water and oil temperature indicators watched; abnormalities recorded; heat exchanger checked for cooling water flow | 8.3.2.9(3)(a)–(e) |
| ☐ Steam turbine | Steam gauge reading recorded; time to running speed observed | 8.3.2.9(4)(a), (b) |
I. Annual flow test
Qualified personnel run the annual test, controlling discharge through approved test devices. For measurement and curve comparison in detail, see fire pump performance test.
| Check | Criterion | Clause |
|---|---|---|
| ☐ Constant-speed pump: test points | No flow (churn), rated flow and 150 percent of rated flow | 8.3.3.1 |
| ☐ Variable-speed pump under variable-speed control | No flow and 25, 50, 75, 100, 125 and 150 percent of rated flow | 8.3.3.2 |
| ☐ Variable-speed pump under constant-speed control | No flow, 100 and 150 percent | 8.3.3.3 |
| ☐ Suction supply cannot deliver 150 percent | Test at 100 percent and at the maximum flow allowed at the lowest permissible suction pressure | 8.3.3.4 |
| ☐ Test arrangement | Hose streams, or bypass flowmeter to drain or suction reservoir, at least every third year; closed-loop metering back to suction may be used 2 out of every 3 years | 8.3.3.9 |
| ☐ Closed-loop test | Recirculating water temperature monitored; results inconsistent with the previous year are repeated with hose streams, or if that is impossible the flowmeter is calibrated and the test repeated | 8.3.3.9.3.2–8.3.3.9.3.4 |
| ☐ Before flowing hose streams | Owner or representative told the location, approximate flow and duration | 8.3.3.9.1.2 |
| ☐ At no flow | Circulation relief valve checked for discharge and pressure relief valve (if installed) for proper operation | 8.3.3.10(1) |
| ☐ At each flow condition | Motor voltage and current on all lines (where the controller has external means), pump speed, and simultaneous suction pressure, discharge pressure and flow recorded | 8.3.3.10(2) |
| ☐ Before shutdown | Electric pump has run at least 10 minutes, diesel pump at least 30 | 8.3.3.10(3), (4) |
| ☐ Several pumps needed together to meet demand | Each flow condition repeated with all pumps running | 8.3.3.11 |
| ☐ Pressure relief valve | At every flow condition, watch whether discharge pressure exceeds component operating pressure and whether the valve closes at the right pressure; if closed to reach rated characteristics, reset at the end of the test | 8.3.3.12–8.3.3.12.2 |
| ☐ Automatic transfer switch (where installed) | Simulate a power failure with the pump at peak load; switch transfers to the alternate source; record voltage, current, rpm, suction and discharge pressure; pump keeps running at peak horsepower load for at least 2 minutes; on removing the failure, it reconnects to normal power after a time delay. Overcurrent devices (fuses or breakers) must not open | 8.3.3.13 |
| ☐ Alarm conditions | Simulated at the sensor locations and confirmed; sensors that cannot be reached without opening an energized controller are tested at an alternative point outside it | 8.3.3.14, 8.3.3.14.1 |
| ☐ Suction screens | Inspected and cleared after the flowing part of the annual test or a system activation | 8.3.3.16 |
| ☐ Engines with electronic fuel management | Backup ECM and primary and redundant ECM sensors tested annually | 8.3.3.17 |
| ☐ Pump–driver alignment | Parallel and angular alignment inspected at the annual test and corrected | 8.3.6.4 |
| ☐ Pump room environment | Heating, ventilation and lighting equipment tested for proper manual or automatic operation | 8.3.6.3 |
J. Test equipment and calibration
| Check | Criterion | Clause |
|---|---|---|
| ☐ Test equipment | Calibrated equipment to determine net pump pressure, flow through the pump and speed | 8.3.3.5 |
| ☐ Label | Gauges, transducers and other measuring devices labelled with the latest calibration date | 8.3.3.5.1 |
| ☐ Gauges and transducers (other than flow meters) | Calibrated at least annually to ±1 percent | 8.3.3.5.2 |
| ☐ Flow meters | Calibrated annually to ±3 percent | 8.3.3.5.3 |
| ☐ Discharge and sensing orifices | Those visible without disassembly free of damage and obstruction | 8.3.3.6 |
| ☐ Discharge orifices | Listed, or built to a recognised standard with a known discharge coefficient | 8.3.3.8 |
K. Evaluating the results
| Check | Criterion | Clause |
|---|---|---|
| ☐ Acceptance 1 | Pump meets the flow and pressure of the most demanding system(s) it supplies, from owner-provided design information | 8.3.7.2.3(1) |
| ☐ Acceptance 2 | Pump supplies 100 percent of rated flow | 8.3.7.2.3(2) |
| ☐ Acceptance 3 | Net pressure at each flow point at least 95 percent of the original manufacturer’s curve, the original unadjusted field test curve or a curve generated from the nameplate | 8.3.7.2.3(3) |
| ☐ Acceptance 4 | 8.1.5 (suction supply) met | 8.3.7.2.3(4) |
| ☐ Suction supply cannot test beyond 100 percent | Acceptable if all other requirements are met | 8.3.7.2.3.1 |
| ☐ Raising speed | Increasing engine speed beyond rated pump speed to meet rated performance is not permitted | 8.3.7.2.2 |
| ☐ Constant-speed electric pump current | At each flow point and phase, not above service factor × full-load amperage; otherwise find and correct the cause | 8.3.7.2.5, 8.3.7.2.6 |
| ☐ Electric pump at varying voltage | Test voltage × current not above voltage × full-load current × service factor; otherwise find and correct the cause | 8.3.7.2.7, 8.3.7.2.8 |
| ☐ Motor voltage | Within 5 percent below to 10 percent above nameplate voltage is acceptable | 8.3.7.2.9 |
| ☐ Who evaluates | Qualified personnel; net flow performance is compared with the manufacturer’s original performance, gross performance with the demand of connected systems | 8.3.7.1.1, 8.3.7.1.1.1, 8.3.7.1.2 |
If the criteria are not met
- The owner is notified in writing and the cause is investigated (8.3.7.2.4(1), (2)).
- Failure to provide the maximum system demand is an impairment (8.3.7.2.4(3)).
- Excessive vibration or excessively worn or loose components are a deficiency; degraded performance that still meets demand is a noncritical deficiency (8.3.7.2.4(4), (5)).
- Corrections are reported to the owner in writing, and the owner keeps a record of the investigation and corrective action (8.3.7.2.4(6), 8.3.7.2.10).
L. Diesel fuel
| Check | Criterion | Clause |
|---|---|---|
| ☐ Fuel degradation test | At least annually; at minimum fuel quality testing to ASTM D975 or ASTM D6751, depending on fuel type, as approved by the engine manufacturer | 8.3.4.1, 8.3.4.1.1 |
| ☐ Fuel found deficient | Recondition or replace the fuel, clean the tank internally and change the engine fuel filter(s) | 8.3.4.2 |
| ☐ After restoration | Retest every 6 months until experience shows the fuel keeps at least 1 year without degradation | 8.3.4.2.1 |
| ☐ Active fuel maintenance system (where provided) | Listed for fire pump service; maintained per the manufacturer, at least annually for parts with no stated frequency; additives per the manufacturer | 8.3.4.3–8.3.4.3.3 |
| ☐ Fuel tank, float switch and interstitial-space supervisory signal | Tested quarterly for liquid intrusion | 8.1.1.2.7 |
| ☐ Fuel tank | Tested annually for water and foreign material | 8.1.1.2.9 |
| ☐ Fuel tank vents and overflow piping | Inspected annually for obstruction | 8.1.1.2.10 |
M. Annual and periodic inspection and maintenance items
Energized controller rule: Electrical connections, PCB corrosion, cable insulation, plumbing leaks in panels, control and power wiring, and gauge/sensor accuracy are checked to the extent the work can be done without opening an energized electric fire pump controller. The isolating switch in a compartment separate from the other controller components may be used for these checks (8.1.1.2.2.1, 8.1.1.2.2.2 and the related clauses). Section 4.11 applies when working near electric-motor-driven fire pumps (8.3.3.15.1).
| Item | Frequency and criterion | Clause |
|---|---|---|
| ☐ Shaft movement / end play | Annually, with the pump running | 8.1.1.2.1 |
| ☐ Electrical connections | Inspected annually, repaired as needed | 8.1.1.2.2.1 |
| ☐ Pump and motor bearings, couplings | Greased annually or as required | 8.1.1.2.3 |
| ☐ Printed circuit boards | Inspected annually for corrosion | 8.1.1.2.4.1 |
| ☐ Cable/wire insulation | Inspected annually for cracking | 8.1.1.2.5.1 |
| ☐ Plumbing parts inside and outside panels | Inspected annually for leaks | 8.1.1.2.6.1 |
| ☐ High cooling water temperature supervisory circuit | Tested annually | 8.1.1.2.8 |
| ☐ Flexible hoses and connections | Inspected annually for cracks and leaks | 8.1.1.2.11 |
| ☐ Engine crankcase breather | Inspected quarterly | 8.1.1.2.12 |
| ☐ Exhaust system, drain condensate traps, silencers | Inspected annually | 8.1.1.2.13 |
| ☐ Turbo back pressure | Measured annually | 8.1.1.2.14 |
| ☐ Batteries | Annually: test specific gravity, state of charge and charger rates; clean terminals; cranking voltage above 9 V on a 12 V system or 18 V on a 24 V system; distilled water only | 8.1.1.2.15 |
| ☐ Control and power wiring connections | Inspected annually, repaired as needed | 8.1.1.2.16.1 |
| ☐ Engine oil and oil filter | Changed every 50 operating hours or annually | 8.1.1.2.17, 8.1.1.2.18 |
| ☐ Fuel filters | Changed annually (the table gives 50 operating hours or annually); more often if the manufacturer recommends | 8.1.1.2.19, 8.1.1.2.20 |
| ☐ Sacrificial anodes | Condition inspected annually, replaced as needed | 8.1.1.2.21 |
| ☐ Circulating water filters | Replaced annually | 8.1.1.2.22 |
| ☐ Gauge and sensor accuracy | Annually; replaced or recalibrated when more than 5 percent out of calibration, with PPE per NFPA 70E or an approved equivalent | 8.1.1.2.23, 8.1.1.2.23.2 |
| ☐ Power transmission parts with elastomeric materials (torsional couplings) | Replaced every 5 years or as the component manufacturer requires | 8.1.1.2.24 |
N. Generators, transfer switches and other tests
| Check | Criterion | Clause |
|---|---|---|
| ☐ Engine generator sets supplying emergency/standby power to the pump | Tested routinely per NFPA 110 | 8.3.6.1 |
| ☐ Automatic transfer switches | Tested and exercised routinely per NFPA 110 | 8.3.6.2 |
O. Positive displacement pumps
| Check | Criterion | Clause |
|---|---|---|
| ☐ General | Tested to 8.3.1–8.3.3 except where 8.3.5 differs | 8.3.5.1 |
| ☐ Flow test | Using a flowmeter or orifice plate in a test loop (to the supply tank, the pump inlet or drain); reading matches the manufacturer’s performance data; flow as specified at system design pressure | 8.3.5.3, 8.3.5.4, 8.3.5.6 |
| ☐ If orifice plates are used | Orifice size and upstream pressure to maintain are given to the AHJ | 8.3.5.5 |
| ☐ Pumps for liquids other than water | May be tested with water; manufacturer’s calculation of the viscosity difference provided | 8.3.5.8, 8.3.5.9 |
| ☐ Water mist PD pumping unit activation test | Annually and after every modification; with an arrangement simulating the smallest nozzle, system design pressure reached within the listed time and not more than 60 seconds | 8.3.5.10.1, 8.3.5.10.2 |
P. Report and records
A complete written report of the pump test results is prepared for and kept by the owner (8.4.1). At minimum it contains (8.4.1.1):
- All raw data for a full evaluation: suction and discharge pressure, voltage and current (as far as possible without opening an energized controller) and pump speed at each flow tested
- The fire protection system demand as furnished by the owner
- Whether pump performance is satisfactory or unsatisfactory
- Deficiencies found in testing and analysis, with recommendations
- The manufacturer’s performance data, actual performance and the pump discharge curves the standard requires
- Time delays for starting, stopping and energy source transfer
- Comparison with previous results where applicable
Records are kept of all work on the pump, driver, controller and auxiliary equipment (8.5.2).
Q. Adjusting, repairing and replacing components
When a pump component is adjusted, repaired, rebuilt or replaced, the tests needed to return the system to service follow Table 8.6.1 (8.6.1). Depending on the component and the action, the table calls for anything from an NFPA 20 acceptance test to an 8.3.2 no-flow test; NFPA 20 is consulted for design, installation and acceptance testing (8.6.2). Replacement parts keep the listing of the pump component assembly wherever possible; if the original manufacturer no longer supplies the part, an approved like part may be used (8.6.3, 8.6.3.1).
Frequently Asked Questions
How often must a fire pump be run under NFPA 25?
A diesel-engine-driven pump gets a weekly no-flow (churn) test and runs for at least 30 minutes (8.3.1.1, 8.3.2.4). An electric pump is run weekly where it serves buildings beyond fire department pumping capacity, has a limited service controller, is a vertical turbine or takes suction from a ground-level tank; otherwise, and in systems with a redundant pump, monthly; it runs for at least 10 minutes (8.3.1.2, 8.3.2.3). An approved risk analysis may set a different frequency.
What is the minimum pump room temperature?
At least 4 °C (40 °F) with an electric pump or a diesel pump with engine heaters, and at least 21 °C (70 °F) with a diesel pump without engine heaters (8.2.2(1)(a), (b)). It is checked at the weekly inspection.
At which flows is the pump tested annually?
A constant-speed pump at no flow, rated flow and 150 percent of rated flow (8.3.3.1). A variable-speed pump under variable-speed control at no flow and 25 to 150 percent in 25 percent steps; under constant-speed control at no flow, 100 and 150 percent (8.3.3.2, 8.3.3.3).
When is the annual test acceptable?
When the pump meets the most demanding system demand and 100 percent of rated flow, net pressure at every flow point is at least 95 percent of the original manufacturer’s curve, the original field test curve or the nameplate curve, and the suction supply requirement of 8.1.5 is met (8.3.7.2.3).
Can a closed-loop flowmeter be used for the annual test every year?
No. Hose streams or a bypass flowmeter to drain or the suction reservoir are used at least every third year; closed-loop metering is allowed 2 out of every 3 years (8.3.3.9). If closed-loop results are inconsistent with the previous year, the test is repeated with hose streams (8.3.3.9.3.3).

SprinkCalc — Fire Sprinkler Design Across Three Standards
SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.
Download SprinkCalc on the App Store
MEP Calc — 110+ Engineering Calculators
MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.
Download MEP Calc on the App StoreNFPA 25-2026, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems: Chapter 8 (8.1–8.6), Table 8.1.1.2 and Table 8.6.1. The content of NFPA 20, NFPA 70E, NFPA 110 and ASTM D975/D6751 referenced by Chapter 8 is not reproduced here.