The first fill of a fire protection pipe network is one of the most critical commissioning stages, directly affecting the long-term integrity, reliability and life safety performance of the system. This guide explains flushing, slow filling, air venting, priming, hydrostatic testing and the start-stop settings under NFPA 20 (2025) and NFPA 24 (2022) — including what must be done and what must never be done on site.

1. The Basic Philosophy of First Fill

The underlying principle is to prevent destructive water hammer through slow, controlled filling, to expel all air from the network, and to bring the system safely into service without ever running the pump dry. NFPA 20 governs how a fire pump and its accessories are installed, tested and commissioned; NFPA 24 governs the installation, flushing and acceptance of the infrastructure mains carrying water from the source to the pump and into the building systems.

💡 Companion article: for how the pump pressures are set once the system is full, see Setting Fire Pump Pressures at Commissioning — The NFPA 20 Pressure Cascade.

2. Preparation and Flushing

Before the first fill, a full flushing test is mandatory to clear construction debris from underground and above-ground pipework. Foreign objects that enter pipes during construction — stones, gravel, timber blocks, plastic, work gloves and sacking — will, if not flushed out, permanently damage the pump impeller, disturb shaft alignment, or block sprinkler heads, alarm valves and check valves. NFPA 20 (14.1.1) and NFPA 24 (10.10.2.1) therefore require suction and supply mains to be flushed at high velocity before they are connected to the pump.

Flushing Flow Rates and Velocity Requirements

NFPA 24 clause 10.10.2.1.3 requires underground piping to be flushed at a flow that produces at least 10 ft/s (3.0 m/s) in the pipe (for example 880 gpm, 3,350 L/min, for a 6 in. main). Where the piping is connected to a fire pump, 10.10.2.1.3.2 applies the NFPA 20 Table 14.1.1.1 flows below or the hydraulically calculated system demand, whichever is greater; these flows are higher than the 10 ft/s table. Where the water supply cannot deliver the table flow, the flushing flow must be at least 150% of the rated flow of the connected pump (NFPA 20 14.1.1.3); where even that is not available, the greater of 100% of rated pump flow and the maximum system demand is used (14.1.1.3.1). Flushing takes place before the hydrostatic test (14.1.1.2). These provisions are extracted verbatim in NFPA 13-2025 clause 6.11.2.1. Minimum flushing flows for suction piping connected to a fire pump (NFPA 20 Table 14.1.1.1):

Nominal size (in)Nominal size (mm)Min. flow (gpm)Min. flow (L/min)
2"50 mm150 gpm570 L/min
2½"65 mm229 gpm870 L/min
3"75 mm330 gpm1,250 L/min
4"100 mm590 gpm2,240 L/min
5"125 mm920 gpm3,490 L/min
6"150 mm1,360 gpm5,150 L/min
8"200 mm2,350 gpm8,900 L/min
10"250 mm3,670 gpm13,900 L/min
12"300 mm5,290 gpm20,100 L/min

3. What To Do: Filling and Pressurisation

Once cleanliness has been verified by flushing, the first fill and pressurisation are completed step by step:

1 Fill slowly via the mains or bypass

Filling is always slow and controlled. The preferred sources are the municipal water supply pressure, the pump bypass line, or external filling connections. Suction and discharge valves are opened gradually so the water spreads through the pipework in stages, preventing pressure shocks at pipe junctions.

2 Vent the air progressively

Air trapped in the pipework causes water hammer and component damage. During filling, all air cocks and manual vents are held open and are not closed until an uninterrupted flow of water appears. Centrifugal pumps require an approved automatic float-operated air release valve of at least 0.5 in (12.7 mm) on the casing; vertical shaft turbine pumps require an air release valve of at least 1.5 in (38 mm).

3 Prime the fire pump

Centrifugal fire pumps are not self-priming; the casing and suction line must be completely full of water before the pump can operate. Where the water level is above the pump (flooded suction) this happens automatically. Where the source is below the pump (suction lift), EN 12845 clauses 10.6.2.3–10.6.2.4 require a foot valve at the lowest point of the suction pipe and a separate automatic priming tank for each pump, and EN 12845 says the arrangement should be avoided wherever possible (10.6.1). For an installation under NFPA 20, confirm against the edition in force whether suction lift is accepted at all. The pump is never run without water.

4 Check alignment and rotation

After filling, the coupling is disconnected and the driver rotation is verified against the arrow on the pump casing with a momentary start test. Shaft alignment between pump and driver is then checked with a dial indicator. Alignment is repeated after the baseplate is grouted, after the first 10 hours of running and after three months of operation, and the pump and driver are then dowelled to the base plate (NFPA 20 Annex A.6.5).

5 Hydrostatic leakage test

Once full, the pipework is tested for 2 hours at not less than 200 psi (13.8 bar), or 50 psi (3.4 bar) above working pressure, whichever is greater. There must be no pressure drop or visible leakage during that period; on underground mains the test pressure is held within ±5 psi (0.3 bar), and a pressure loss of less than 5 psi (0.3 bar) or no visible leakage is the pass criterion (NFPA 24 10.10.2.2.1–10.10.2.2.2). Makeup water added to hold the test pressure is measured and must not exceed the NFPA 24 allowance L = S × D × √P / 148,000 (L in gal/h, S pipe length tested in ft, D nominal diameter in in., P average test pressure in psi).

⚠️ Critical: filling is always slow. A mass of water travelling quickly down empty pipework generates severe water hammer when it strikes closed ends and fittings.

4. What Must Never Be Done During First Fill

Even a small procedural or sequencing error during first fill and commissioning can render very expensive equipment unusable. The most critical prohibitions:

5. Start-Stop Pressure Settings After Filling

Once the system is completely full, vented and proven leak-tight, the controller start-stop settings are made per the NFPA 20 guidance:

Worked Example

ParameterDerivationValue
Fire pump rating—1000 gpm at 100 psi (churn 115 psi)
Water supply (municipal main)—Min. static 50 psi / max. static 60 psi
Jockey pump stopChurn + min. static115 + 50 = 165 psi (11.38 bar)
Jockey pump startJockey stop − 10 psi165 − 10 = 155 psi (10.69 bar)
Main pump start (2025)Jockey start − 10 psi155 − 10 = 145 psi (10.00 bar)
Main pump start (2022)Jockey start − 5 psi155 − 5 = 150 psi (10.34 bar)
System maximum pressureChurn + max. static115 + 60 = 175 psi (12.07 bar)
⚠️ Operating note: running a fire pump at churn (zero flow) for a long period overheats the water in the casing. Automatic stopping is therefore not preferred and manual shutdown is the norm. Where automatic stop is approved by the authority having jurisdiction, minimum run timers are mandatory: at least 10 minutes for electric and 30 minutes for diesel pumps.

6. Acceptance Testing and Certification

Once filling, flushing and leakage testing are complete, field acceptance tests are witnessed by the authority having jurisdiction, the owner and the contractor. Results are recorded and signed on the formal certificates, which also form the baseline for the periodic inspection regime under NFPA 25:

Frequently Asked Questions

Why must a fire system be flushed before the first fill?

Foreign objects that enter the pipework during construction - stones, gravel, timber, plastic and work gloves - will damage the pump impeller, disturb shaft alignment or block sprinkler heads, alarm valves and check valves if they are not removed. NFPA 20 and NFPA 24 therefore require suction and supply mains to be flushed at high velocity before they are connected to the pump.

What flushing flow rate is required for fire mains?

NFPA 24 clause 10.10.2.1.3 requires a flow that produces at least 10 ft/s (3.0 m/s) in underground piping, which for a 6 inch (150 mm) main is 880 gpm (3,350 L/min). For suction piping connected to a fire pump, the NFPA 20 Table 14.1.1.1 flows or the calculated system demand, whichever is greater, apply: 1,360 gpm (5,150 L/min) for 6 inch and 2,350 gpm (8,900 L/min) for 8 inch. Where the supply cannot deliver that flow, flushing is done at no less than 150% of rated pump flow (NFPA 20 14.1.1.3).

Can an empty sprinkler system be filled with the jockey pump?

No. The jockey pump is sized only to make up acceptable leakage, and its flow is usually less than that of a single sprinkler. Trying to fill an empty system with it runs the pump continuously for hours, overheats it and can burn out the motor. The jockey is only used to pressurise a system that is already full.

Can the main fire pump be run to fill the system?

No, this is strictly prohibited. Pushing water into empty or air-filled pipework with the main pump produces violent water hammer that can tear off elbows, flanges, fire valves and sprinkler branch lines. Filling is always done slowly from the town main, the bypass line or an external filling connection, and the main pump is only placed on standby once the system is full and tested.

Why does a centrifugal fire pump need priming?

Centrifugal pumps are not self-priming; the casing and suction line must be completely full of water before the pump can operate. Where the water level sits above the pump this happens automatically under flooded suction. Where the source is below the pump (suction lift), EN 12845 clauses 10.6.2.3–10.6.2.4 require a foot valve and a separate automatic priming tank for each pump, and the arrangement should be avoided wherever possible. The pump is never run dry.

At what pressure and for how long is the hydrostatic test carried out?

The system is tested for 2 hours at not less than 200 psi (13.8 bar), or 50 psi (3.4 bar) above working pressure, whichever is greater. There must be no pressure drop or visible leakage during that period; on underground mains a pressure loss of less than 5 psi (0.3 bar) or no visible leakage is the pass criterion (NFPA 24 10.10.2.2.2). Makeup water added during the test must not exceed the allowance L = SD√P / 148,000 (gal/h) given in NFPA 24.

Can a butterfly valve be used in the fire pump suction line?

No. The disc of a butterfly valve sits in the flow path and creates turbulence and constriction that lead to cavitation. NFPA 20 requires a full-bore outside-screw-and-yoke (OS&Y) gate valve with visible position indication in the suction line. A butterfly valve may only be located at least 15.3 m (50 ft) upstream of the suction flange.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 110+ Engineering Calculators

MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

NFPA 20, Standard for the Installation of Stationary Pumps for Fire Protection, 2025 Edition. NFPA 24, Standard for the Installation of Private Fire Service Mains and Their Appurtenances, 2022 Edition. Stationary Fire Pumps and Standpipe Systems Handbook, NFPA. NFPA 25, Standard for the Inspection, Testing and Maintenance of Water-Based Fire Protection Systems. NFPA 13-2025 clause 6.11.2 (extracts of the NFPA 24 and NFPA 20 flushing and hydrostatic test provisions). EN 12845:2015+A2:2026 clauses 10.6.1–10.6.2.4 (suction lift and pump priming).