Two independent batteries, six cranking attempts and constant-voltage charging — what the diesel starting clauses mean on site.

Called out to a logistics warehouse acceptance, we found a single battery in the diesel pump enclosure. The plate was new, the cabling neat, the charger lit — but there was only one. The contractor had meant to add the second later and forgotten. When the test button was pressed, the engine failed to catch on the third attempt, because of voltage drop. Had there been two independent batteries as EN 12845 requires, the system would have switched automatically on the second attempt and the engine would very likely have fired. This article covers the standard behind that scene.

The relevant clauses

The diesel starting system is detailed across several sub-clauses:

Two independent batteries — why two?

The standard requires two separate battery power supplies serving no other purpose. The reason is not redundancy alone; combined with the automatic changeover logic, it gives the six cranking attempts their practical meaning. If the first battery is weak or has an open cell, the controller switches to the second on the next attempt and the engine gets a fresh chance.

The connection rule we watch for on site: there must be an isolating relay or diode group preventing one battery from affecting the other. We do not accept designs with a single common busbar permanently paralleling both batteries, because a short on one drains the other.

Battery type selection:

A hydrometer must be kept in the pump room; we do not sign off maintenance without an electrolyte specific gravity measurement.

Six consecutive cranking attempts — the timing table

The automatic sequence parameters:

ParameterValue
Total attempts6
Cranking time per attempt5–10 s
Rest between attempts10–15 s
Battery changeoverAutomatic after each attempt
Additional pinion attempts (within the engine)5
After six attemptsFail-to-start alarm, manual test button active
Nominal voltage≥ 12 V

The site acceptance procedure: close the fuel line, trigger the automatic sequence, and confirm the fail-to-start alarm operates after six unsuccessful cycles. Then restore the fuel and start the engine from the manual test button. The acceptance record should not be signed without that test.

The automatic constant-voltage charger

Each battery gets its own charger: permanently connected, fully automatic and constant potential. One must be able to be removed for repair while the other continues — so they must be independently supplied, without a shared fuse.

Reference values for lead-acid:

For vented Ni-Cd prismatic cells:

Charging current must be adjusted for local climate; the same float value may not suit a tropical or very cold cell. "Constant potential" means a modern voltage-regulated charging circuit, not a simple transformer-and-bridge arrangement.

Battery location and room conditions

Four basic requirements:

  1. On a stand — batteries do not sit directly on the floor; a profile or composite stand provides vibration and moisture isolation.
  2. Away from contamination — oil, fuel leaks, coolant and external moisture must not reach them.
  3. Minimum vibration — mounting directly on the pump baseplate is not acceptable.
  4. Close to the starter motor — cable runs as short as possible, to minimise voltage drop.

The charger may share an enclosure with the batteries; our standard practice is two batteries and two chargers in a common steel cabinet, in separate compartments. The inside of the cabinet door is labelled with each battery's capacity, date of manufacture and last test date.

Tools and spare parts

The spares that must be kept in the pump enclosure:

Alongside these, the engine manufacturer's recommended tool kit, a hydrometer and a battery terminal cleaning brush are kept in a locked cabinet in the room.

Typical field errors

Comparison with NFPA

NFPA 20 (2025) defines the diesel starting system similarly: two separate batteries, automatic changeover, and six cranking attempts of 15 s each with 15 s rest, giving a three-minute cycle. EN 12845 uses shorter cranking (5–10 s) with battery changeover after each, so the total cycle is shorter. On chargers, NFPA 20 calls for a two-rate float charger and EN 12845 for constant potential plus boost; in practice the same device satisfies both. NFPA additionally mandates an automatic weekly no-flow test cycle, where EN 12845 describes the weekly test within its maintenance clauses.

Application in Turkey

BYKHY requires two separate batteries and an automatic charger for a diesel fire pump but gives no detail, leaving EN 12845 or NFPA 20 as the reference standard. Insurance surveyors — particularly on FM-compliant projects — test the changeover logic on site: remove one battery, and the engine must still make six attempts on the other. We ask for the panel manufacturer's changeover relay schematic and a record of successful running on the second battery.

Frequently asked questions

Can I certify to EN 12845 with a single battery?

No. Two separate battery power supplies are a "shall" requirement; a single battery cannot pass acceptance testing.

Can the batteries serve other loads, such as pump room lighting?

No. The starting batteries must be used for no other purpose.

What charger output current is required?

3.5–7.5 % of C10 capacity for lead-acid — 3.5 to 7.5 A for a 100 Ah battery. The manufacturer's data sheet should recommend a value in that range.

Is boost charging automatic or manual?

The standard requires the facility to be provided without mandating automation. Modern chargers activate boost automatically when the float level drops; a manual boost button is also accepted.

How often are batteries replaced?

The standard sets no fixed life. Hydrometer checks are carried out regularly, and where specific gravity is low with a healthy charger, the battery is replaced. In practice lead-acid batteries are renewed every four to five years and Ni-Cd every eight to ten.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 86+ Engineering Calculators

MEP Calc bundles 86+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

BS EN 12845:2015+A1:2019 Fixed firefighting systems — Automatic sprinkler systems. EN 12845-2:2024 (CMSA & ESFR sprinkler systems). NFPA 13 Standard for the Installation of Sprinkler Systems. Turkish Regulation on Fire Protection of Buildings (BYKHY). FM Global Property Loss Prevention Data Sheet 2-0.

FS

Fatih Selvi

Mechanical engineer and software developer with field experience in MEP and fire protection, working actively with NFPA, FM Global and BS EN 12845 on site projects.