How a full-flow pressure-flow curve is produced, which orifice sizes to use, why pitot and gauge readings diverge — and the annual test routine from field experience.

Opening the annual maintenance report on the OH3 sprinkler installation at a logistics centre, static pressure read 8.4 bar and "at full flow" 7.9 bar. The pump nameplate gave 5.2 bar at its rated point, so the site reading appeared to sit above the pump curve. The reason took an hour to find: the team had opened the drain-and-test valve only partly, and while the flow meter read 850 L/min, the pump was assumed to be running at its rated 2100 L/min. The full-load test requirement exists precisely to prevent that kind of self-confirmation.

EN 12845:2015+A1:2019 requires permanent test equipment on every sprinkler installation, and an annual full-flow test using it. This article covers how the test arrangement should be built, how a pressure-flow curve is properly produced, and the "ambiguous pitot reading" error we meet most often.

What the test arrangement must contain

To measure whether the water supply genuinely meets the hazard class, EN 12845 requires permanent test equipment. It is installed in one of two configurations — in the pump room, or at the control valve set:

Three critical limits govern equipment selection, and they are routinely skipped on site:

Test orifices and drain-test line sizes

The drain-and-test valve exists to confirm, by putting flow on the ground, that both the alarm and the pump operate at full load. The lower limits:

Hazard classMin. drain-test line sizeTypical orifice
LH40 mm40–65 mm; about 380 L/min is sufficient
OH1 / OH250 mm50–65 mm; demand 540–720 L/min
OH3 / OH450 mm65 mm typical; demand above 1100 L/min
HHP / HHS50 mm mandatory minimum; 100 mm in practice100 mm orifice or a multi-outlet rosette; 2700–9000 L/min

A working rule from site: where the test discharge is free, orifices are kept at two main sizes, 65 mm and 100 mm. A 65 mm orifice opens the OH classes to full flow, and a 100 mm orifice does the same for HHP and HHS pumps without choking them. It is impossible to drive an 1800 L/min pump to full load through a smaller orifice; pressure never falls, the pump behaves as if against a closed valve, and the curve comes out biased.

Where test water is not discharged to waste — returned to the town main or the fire water tank — a return line of the same size must be provided. The standard requires an arrangement for disposing of test water; it is the item most often omitted.

The full-flow curve: a four-point method

The standard requires at least three pressure-flow points plus a static reading at zero flow. Taking four on site makes the curve readable:

  1. Static point (Q = 0): drain-test valve closed. Record the churn pressure from the gauge. It also serves the maximum pressure check.
  2. Low flow (Q ≈ 0.5 Qrated): valve partly open. The left branch of the curve, before the pump enters overload.
  3. Rated flow (Q = Qrated): the nameplate figure. The pump must deliver at least its nameplate pressure here; deviations like the 7.9 bar in our report are caught at this point.
  4. Overflow (Q ≈ 1.4 Qrated): the EN pump operating condition. The right branch collapses; pressure must not fall below 65 % of the mid-point figure.

Allow at least 30 seconds at each point for the flow to settle. Where the gauge pulses, fit a snubber before reading; otherwise even a ± 1.6 % gauge swings within a ± 0.3 bar band.

When is a pitot tube useful?

EN 12845 does not require a pitot tube for the pressure-flow curve, emphasising that the primary data comes from the gauge and flow meter. A pitot helps only when measuring the jet from an open discharge orifice. But on site, pitot readings come out "ambiguous" for several reasons:

Our working rule: where a pitot is used to corroborate the curve, the gauge at the pump flange is the primary reading and Q = K√P serves only as a check. If the pitot reading diverges from the pump pressure by more than 10 %, stop the test and re-set the orifice and pitot position.

The annual test sequence

The annual routine treats installations with and without a supply pump separately. Both are carried out at full load:

StepWith pumpWithout pump
1Open the test line connected below the pump discharge check valveOpen the test line above the control valve set
2Record static pressure, then bring the flow meter to full flowOpen the drain-test valve fully to reach the required flow
3Compare with the pump nameplate figures and report any deviationCheck whether the gauge meets the minimum design pressure
4Account for pipe and valve friction lossesAccount for losses between the supply and the valve set

The same routine also includes the diesel fail-to-start alarm, the tank float valves and the suction strainers. Those are independent of the curve but done on the same day, and the report template should have a place for each.

Field error: what an ambiguous pitot reading was hiding

Back to the OH3 logistics facility. Because the pitot read 1.2 bar, the team calculated flow through the 65 mm orifice with K = 18.3 as Q = 18.3 × √1.2 ≈ 2005 L/min and declared it satisfactory. But:

With the valve fully open, the flow meter read 2080 L/min and the pump discharge gauge 5.3 bar, meeting the nameplate. The only intervention was cleaning the drain-test valve spindle. Trusting the pitot reading is a very common site error; the primary readings must always be the calibrated gauge at the pump flange and the flow meter.

Comparison with NFPA 25

NFPA 25 also requires three points — churn, rated and peak — in the annual pump test. The differences:

Turkish practice

BYKHY requires sprinkler installations to be inspected at least annually but does not detail the test procedure. As a result, "I read the gauge and signed" reports are common. The EN 12845 test equipment and annual routine clauses provide the most robust framework for defining which instruments, which ranges and which curve points that report should contain — and a report referencing EN 12845 passes insurance assessment without difficulty.

My practical recommendation: always put four headings on the annual maintenance form — static pressure; at least three pressure-flow pairs; the calibration dates of the flow meter and gauge; and confirmation that the drain-test valve was fully open, photographed with the handle visible. With those four items, both the standard and the inspector are satisfied.

Summary

Frequently asked questions

Is full flow mandatory in the annual test?

Yes. Every water supply pump must be tested at least annually under full load, meeting its nameplate figures. Static or partial flow alone is not sufficient.

Why is a gauge preferred over a pitot tube?

Because the standard requires a calibrated test gauge accurate to ± 1.6 % for the test curve. Pitot readings vary significantly with nozzle axis, entrained air and observer, so the primary data comes from the pump flange gauges and the flow meter.

What accuracy must the test flow meter have?

Better than ± 5 % of maximum flow. A portable device must be verified again before use.

Does a pumpless supply need a different test?

Yes. The full-load test is carried out through a test line connected above the control valve set, with a drain-test valve of at least 40 mm for LH and 50 mm for other classes.

How many readings should be taken?

At least three pressure-flow points plus a static reading at zero flow. In practice, four points — static, low, rated and 140 % — produce a far more reliable curve.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 86+ Engineering Calculators

MEP Calc bundles 86+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

BS EN 12845:2015+A1:2019 Fixed firefighting systems — Automatic sprinkler systems. EN 12845-2:2024 (CMSA & ESFR sprinkler systems). NFPA 13 Standard for the Installation of Sprinkler Systems. Turkish Regulation on Fire Protection of Buildings (BYKHY). FM Global Property Loss Prevention Data Sheet 2-0.

FS

Fatih Selvi

Mechanical engineer and software developer with field experience in MEP and fire protection, working actively with NFPA, FM Global and BS EN 12845 on site projects.