In a major earthquake, a logistics warehouse loses its sprinkler system before the shaking even stops: the main breaks where it crosses a building seismic joint with no seismic separation assembly, and water floods the floor for hours. Had there been a fire, the system would have been unable to do anything. FM Global DS 2-8 (Earthquake Protection for Water-Based Fire Protection Systems, October 2017, Interim Revision April 2025) sets out how sprinkler pipework is protected against seismic movement: sway brace locations and sizing, flexible couplings, clearances and seismic joint crossings.

DS 2-8 applies in FM 50-year through 500-year earthquake zones as defined in DS 1-2, Earthquakes (Section 1.0). Its recommendations serve seven goals: bracing, flexibility, clearance, hangers, connections, anchorage and design verification (2.1).

Design Load: the G Factor (2.2.1.2)

Where Braces Go (2.2.1.1)

How Braces Are Built (2.2.1.3)

Flexibility (2.2.1.4)

Clearance and Impact (2.2.1.5–2.2.1.6)

Pumps and Tanks (2.2.5–2.2.6)

A Recurring and Expensive Omission

A pattern seen repeatedly: a sprinkler system is installed to NFPA 13 and EN 12845, but the seismic detailing is left out under schedule or budget pressure. When a significant earthquake occurs, structural movement cracks the main at a large diameter connection, production stops for days or weeks, and the insurer declines the claim on the basis of non-compliance with the applicable seismic provisions. Retrofitting the bracing afterwards costs several times what it would have cost to install during construction, and that is before the business interruption.

Quick Checklist

Frequently Asked Questions

Why does sprinkler pipework need seismic bracing at all?

Because pipework is heavy, suspended and relatively rigid, while the building moves in an earthquake. Without bracing the pipe swings, impacts structure and equipment, and fails at its most rigid points. DS 2-8 aims to keep the fire protection system working after the earthquake and to minimise water damage from leakage (2.1).

Do mains smaller than DN65 need bracing?

Yes. FM DS 2-8 2.2.1.1.4 braces feed and cross mains regardless of size, and risers are braced regardless of size as well. The DN65 threshold applies only to branch lines (2.2.1.1.5.1); smaller dead-end branch lines get a short hanger or lateral restraint within 1.8 m of the end (2.2.1.1.6).

What brace angle is required?

Under DS 2-8 2.2.1.3.5.2, diagonal members on horizontal pipe are at least 30° from vertical and preferably at least 45°. The flatter the angle, the larger the uplift VF = H / tan Θ − ½ Wp on a single diagonal brace; if it is positive, increase the angle or add a vertical member (2.2.1.3.5.6).

What is the difference between a flexible coupling and a seismic separation assembly?

A flexible coupling allows limited angular and axial movement between pipe sections; DS 2-8 calls for them at riser ends, at floor penetrations and on drops (2.2.1.4). A seismic separation assembly or FM Approved flexible pipe loop accommodates large movement in all three directions where piping crosses a building seismic joint or spans between independent structures (2.2.1.4.8).

How is the brace design load calculated?

Under DS 2-8 2.2.1.2, the horizontal design load is H = G · Wp, with Wp the water-filled pipe weight in the brace's zone of influence. G is at least 0.754 · SDS; without a site value, use 1.0 in FM 50-year zones, 0.7 in 100-year zones and 0.4 in 250- and 500-year zones, or a higher value if the local code requires it.

SprinkCalc — Fire Sprinkler Design Across Three Standards

SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.

Download SprinkCalc on the App Store

MEP Calc — 110+ Engineering Calculators

MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.

Download MEP Calc on the App Store
Standards & References

FM Global Property Loss Prevention Data Sheet DS 2-8, Earthquake Protection for Water-Based Fire Protection Systems, October 2017, Interim Revision April 2025 (1.0, 2.1, 2.2.1, 2.2.5, 2.2.6); related data sheets DS 2-0 (October 2021, Interim Revision April 2025) and DS 1-2 (earthquake zones).