In NFPA 13 the first design decision is not the sprinkler type or the pipe size but the hazard classification. Density, area of operation, sprinkler spacing, hose allowance, water supply duration, and therefore the pump and tank size, all flow from that one decision. A space that is classified wrongly is unprotected, however carefully the calculation is done.
This guide covers NFPA 13's non-storage classification end to end: the logic of the five classes, typical examples, the densities and areas of Table 19.2.3.1.1, hose allowance and duration, how to handle mixed occupancies and when a space crosses into the storage rules. For a quick first pass you can use the NFPA 13 hazard classification tool, but the final call is always a reasoned engineering judgement.
The logic behind classification: three questions
NFPA 13 classifies a space by looking not at the building itself but at the combustible contents and the activity inside it. Three questions are asked of every area:
- Quantity: How much combustible material is there? Furniture and paper, or production raw material, work in progress and packaging stockpiles?
- Combustibility and heat release: Does the material burn slowly (timber furniture, paper) or quickly with a high heat release (foamed plastics, solvents, hydraulic oil)?
- Stockpile height and liquids: How high is material stacked? Are there flammable or combustible liquids, dust or lint present?
The answers lead to one of five classes: Light Hazard (LH), Ordinary Hazard Group 1 (OH1), Ordinary Hazard Group 2 (OH2), Extra Hazard Group 1 (EH1) and Extra Hazard Group 2 (EH2). These classes apply only to non-storage occupancies; rack and pile storage are handled through a separate commodity classification.
The five classes and typical examples
| Class | Essence of the definition | Typical examples |
|---|---|---|
| LH | Low quantity and combustibility of contents, low expected heat release. | Offices (including data processing), dwellings, hotels and dormitories, classrooms, hospitals and nursing homes, places of worship, museums, libraries other than large stack rooms, restaurant seating areas, theatres and auditoriums excluding stages. |
| OH1 | Low combustibility, moderate quantity; stockpiles not above 2.4 m (8 ft); moderate heat release. | Automobile showrooms, bakeries, beverage and dairy production, canneries, electric fire pump rooms, electronics assembly, glass manufacturing, laundries, restaurant service and kitchen areas, mechanical rooms. |
| OH2 | Moderate to high quantity and combustibility; stockpiles of moderate heat release up to 3.7 m (12 ft), high heat release up to 2.4 m. | Automobile parking garages, shops and retail sales floors, machine shops and metalworking, printing and publishing, textile and leather goods manufacture, woodworking and wood product assembly, dry cleaners, cereal and feed mills, repair garages, stages, large library stack areas, exterior loading docks. |
| EH1 | Very high quantity and combustibility; dust, lint or similar material can cause rapid fire spread; little or no flammable or combustible liquid. | Plywood and particleboard manufacture, sawmills, rubber processing and vulcanising, areas using combustible hydraulic fluids, die casting and metal extrusion, upholstering with plastic foams, textile opening and blending. |
| EH2 | Moderate to substantial amounts of flammable or combustible liquids, or extensive shielding of combustibles. | Flammable liquid spraying, dip painting and varnishing, solvent cleaning, plastics manufacture, open oil quenching, asphalt saturating, assembly lines for modular buildings with finished combustible interiors. |
These example lists are not a binding catalogue; the standard itself places them in an explanatory annex. Two facilities with the same name can fall into different classes because of different materials and stockpile heights. Rather than saying "a print works is OH2", ask "does this print works use low flash point inks, and how high are the paper reels stored?" Printing with low flash point inks, for instance, moves up to EH1.
Density and design area: Table 19.2.3.1.1
Earlier editions of NFPA 13 gave each class a density/area curve. According to the standard's origin and development notes, the 2022 edition moved away from the curves to single-point design criteria for new systems; the curves may still be used for existing systems. NFPA 13-2025 has no density/area curves. For a new system the density and design area are taken from Table 19.2.3.1.1 (19.2.3.1.1). The table has two columns for each class: the normal case, and the case where 19.2.3.1.5 requires a 3000 ft² (280 m²) design area because the building has an unsprinklered combustible concealed space. The second column is not a free choice, and there are no intermediate values.
| Class | Normal case | Where a 3000 ft² design area is required (19.2.3.1.5) |
|---|---|---|
| LH | 4.1 mm/min @ 140 m² (0.10 gpm/ft² @ 1500 ft²) | 2.9 mm/min @ 280 m² (0.07 gpm/ft² @ 3000 ft²) |
| OH1 | 6.1 mm/min @ 140 m² (0.15 @ 1500) | 4.9 mm/min @ 280 m² (0.12 @ 3000) |
| OH2 | 8.1 mm/min @ 140 m² (0.20 @ 1500) | 6.9 mm/min @ 280 m² (0.17 @ 3000) |
| EH1 | 12.2 mm/min @ 230 m² (0.30 @ 2500) | 11.4 mm/min @ 280 m² (0.28 @ 3000) |
| EH2 | 16.3 mm/min @ 230 m² (0.40 @ 2500) | 15.5 mm/min @ 280 m² (0.38 @ 3000) |
The design area changes only through the standard's adjustment clauses (below). Where the area of sprinkler operation is smaller than 1500 ft² (140 m²) for LH and OH or 2500 ft² (230 m²) for EH, for example in a small room, the density for those areas is still used (19.2.3.1.4). The table row selected and the adjustments applied should be stated plainly in the calculation report.
Adjustments that change the area of operation
- Dry pipe and double-interlock pre-action systems: because water arrives late, the area of operation is increased by 30% without changing the density (19.2.3.2.6).
- Sloped ceilings: where the pitch exceeds 2 in 12 (about 16.7%), hot gases travel up the slope and the area is increased by 30%; no increase is needed where a horizontal false ceiling is installed, or where a slope not exceeding 4 in 12 with purlins meets specified conditions (19.2.3.2.4).
- Quick-response (QR) sprinklers: in wet-pipe LH and OH areas with a ceiling below a set height (6.1 m / 20 ft), the area may be reduced by a percentage that depends on ceiling height (up to 40%); the design area must still contain at least five sprinklers (19.2.3.2.3).
- High-temperature or large-K sprinklers in EH: in extra hazard areas with ceilings not above 9.1 m, the area may be reduced by 25% without changing the density when high-temperature rated or K11.2 (K160) and larger sprinklers are used, but not below 185 m² (2000 ft²), and the reduction may be applied only once (19.2.3.2.7).
- Unsprinklered combustible concealed spaces: where the building has an unsprinklered combustible concealed space of the kind described in 9.2.1 and 9.2.2, the system adjacent to it (above, below or beside) needs a design area of at least 3000 ft² (280 m²), with the density from the second column of Table 19.2.3.1.1. The rule does not apply where a barrier with a fire resistance rating at least equal to the water supply duration completely separates the concealed space from the sprinklered area (19.2.3.1.5.1); exempt concealed spaces are listed in 19.2.3.1.5.2.
When several adjustments apply at once they are not added; they are compounded on the originally selected area, and the unsprinklered concealed space rule is applied after all other modifications (19.2.3.2.8). Confirm these percentages and limits against the current edition of NFPA 13; clause numbers and some thresholds have moved between editions.
Sprinkler spacing depends on the class too
The hazard class sets not only how much water is delivered but how densely sprinklers are placed. Typical limits for standard spray pendent and upright sprinklers:
| Class | Maximum coverage per sprinkler (hydraulically calculated) | Maximum spacing between sprinklers |
|---|---|---|
| LH | 20.9 m² (225 ft²) — may be lower depending on ceiling type | 4.6 m (15 ft) |
| OH1 / OH2 | 12.1 m² (130 ft²) | 4.6 m (15 ft) |
| EH1 / EH2 | 9.3 m² (100 ft²) where density ≥ 10.2 mm/min; 12.1 m² (130 ft²) where density < 10.2 mm/min; 8.4 m² (90 ft²) for pipe schedule systems (Table 10.2.4.2.1(c)) | 3.7 m (12 ft); 4.6 m (15 ft) where density < 10.2 mm/min |
For extended coverage sprinklers these values follow the listing. To check a layout, try the sprinkler spacing and layout calculator.
Hose allowance and water supply duration
Density × area gives only the sprinkler demand. The water supply must also deliver a hose allowance for fire service and internal hose use, for the same duration.
| Class | Inside + outside hose allowance (total) | Water supply duration |
|---|---|---|
| LH | 380 L/min (100 gpm) | 30 min |
| OH1 / OH2 | 950 L/min (250 gpm) | 60 or 90 min |
| EH1 / EH2 | 1900 L/min (500 gpm) | 90 or 120 min |
The shorter duration in Table 19.2.3.1.2 is permitted where the sprinkler system waterflow alarm and supervisory devices are electrically supervised and that supervision is monitored at an approved, constantly attended location (19.2.3.1.3); otherwise the longer duration is used. The inside hose allowance forms part of the total, and where hose stations are fed from the sprinkler system the calculation should show where that flow is drawn from. Duration and total flow set the tank volume directly; the fire water tank sizing calculator handles that step.
Quick example (OH2): 8.1 mm/min × 140 m² ≈ 1134 L/min theoretical sprinkler flow. Hydraulic imbalance and minimum pressures push the real figure above the theoretical value; the example assumes ~1300 L/min. Adding the hose allowance gives 1300 + 950 = 2250 L/min. Over 90 minutes the effective tank volume is ≈ 203 m³. Had the same area been wrongly taken as OH1 (6.1 mm/min, 60 min), the answer would have been about 120 m³ — a tank some 40% too small.
How to classify mixed occupancies
Real buildings are rarely one class. A factory may have an office floor (LH), a production hall (OH2), a spray booth (EH2) and a dispatch area (OH2 or storage) side by side. The approach:
- Classify each area on its own contents. Giving the whole building a single class is either needlessly expensive or unsafe.
- Check for physical separation. Where a partition capable of delaying heat from a fire in one area from fusing the sprinklers in the next, or a draft curtain or barrier above an aisle with at least 600 mm (2 ft) horizontal separation from the adjacent hazard on each side, divides the areas (19.1.2), each zone can be designed to its own criteria.
- Without separation, carry the higher hazard over. In open-plan transitions the higher hazard design criteria are extended a set distance beyond the boundary (of the order of 4.6 m / 15 ft in NFPA 13). Confirm the distance in the current edition.
- Run a separate hydraulic calculation for each class. The water supply is governed by the area that produces the highest total demand (sprinklers plus hose, over the correct duration). That is not always the highest density area: a remote, elevated OH2 zone can be harder to satisfy than a small EH1 zone next to the pump.
- Do not miss small high-hazard pockets. An archive room, kitchen or server room within a large LH office floor is protected to its own class.
When does a space become "storage"?
This boundary needs particular care in classification. The OH1 and OH2 definitions already include stockpiles up to a certain height, so not every stack counts as storage. The road map, broadly:
- Where stockpiles exceed 3.7 m (12 ft) the area is designed to the storage chapters: commodity class (Class I–IV, Group A/B/C plastics), storage arrangement (solid pile, palletised, shelf, rack) and ceiling height are assessed together.
- Storage below 3.7 m is either "miscellaneous storage" or "low-piled storage". Miscellaneous storage is incidental to another occupancy, limited to a small share of the building area and capped in area per pile; where those conditions are met it can be protected to the surrounding class (usually OH2).
- Some commodities trigger stricter rules at lower heights. Group A plastics, tyres, roll paper and rack storage have lower thresholds. Where such materials are present, calling the area OH2 because "we are under 12 ft" is a mistake.
For the storage side see NFPA 13 commodity classification and the warehouse fire protection guide. For high-bay warehouses the ESFR sprinkler design guide offers a separate decision path.
Rough correspondence with EN 12845 and FM Global
Projects may need to move between standards. The classes do not map one to one; the table is a rough orientation only:
| NFPA 13 | EN 12845 (approx.) | FM Global DS 3-26 (approx.) |
|---|---|---|
| LH | LH (compartment size limited) or OH1 | HC-1 |
| OH1 | OH1–OH2 | HC-2 |
| OH2 | OH2–OH3 (some processes OH4) | HC-2 |
| EH1 / EH2 | OH4 or HHP1–HHP4 | HC-3 |
Because EN 12845 ties LH to compartment size and fire resistance, an office that is LH under NFPA may become OH1 under EN. Do not "translate" classes between standards; reclassify using the chosen standard's own table. See the NFPA 13 vs EN 12845 vs FM Global comparison and, for the EN side, the EN 12845 hazard class finder.
Checklist for the classification report
- Has the activity and material content of every area been defined in writing?
- Are stockpile heights based on the real and planned maximum on site?
- Are areas with flammable or combustible liquids, dust or lint marked separately?
- Where there is no separation, have the higher hazard criteria been carried beyond the boundary?
- Have the dry system, sloped ceiling, QR and concealed space adjustments been applied?
- Has a separate hydraulic calculation been run for each class and the governing demand identified?
- Are hose allowance and duration correct for the class?
- Has the owner been told in writing that future changes of use may alter the class?
The last point looks minor but is the source of the costliest problems: when plastic packaging is stacked 5 m high years later in a production hall designed as OH2, the system is compliant on paper and inadequate in reality. Reassessment after a change of use in an existing building should be part of the general workflow in the fire sprinkler system design guide.
Frequently Asked Questions
What NFPA 13 hazard class is an office building?
Usually Light Hazard (LH): 4.1 mm/min density over 140 m², a 380 L/min hose allowance and 30 minutes. Archive rooms, kitchens or stores within it are classified separately on their own contents.
Can I pick a point on a density/area curve in NFPA 13-2025?
No. NFPA 13-2025 has no curves; for a new system the density and area come from Table 19.2.3.1.1 (e.g. 8.1 mm/min over 140 m² for OH2). The table's 280 m² column applies only where the building has an unsprinklered combustible concealed space (19.2.3.1.5). The area changes through adjustment clauses such as those for dry systems or sloped ceilings; the curves of earlier editions may still be used only for existing systems.
Does the density increase on a dry pipe system?
No. Under NFPA 13, dry pipe and double-interlock pre-action systems keep the same density and increase the area of operation by 30%.
Can any stockpile below 3.7 m be protected as OH2?
No. It must meet the miscellaneous storage conditions (incidental use, share of building area and per-pile area limits). Group A plastics, tyres, roll paper and rack storage have lower thresholds.
Can I convert an NFPA 13 class directly to EN 12845?
No. The classes correspond only roughly. Reassess the space with the chosen standard's own classification table; an office that is LH under NFPA, for example, may be OH1 under EN 12845.

SprinkCalc — Fire Sprinkler Design Across Three Standards
SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.
Download SprinkCalc on the App Store
MEP Calc — 110+ Engineering Calculators
MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.
Download MEP Calc on the App StoreNFPA 13, Standard for the Installation of Sprinkler Systems (2022/2025) · BS EN 12845+A2:2026 (EN 12845:2015+A2:2026) · FM Global DS 3-26. This guide is a general road map; percentages, thresholds and clause numbers vary between editions, and the binding text is the current standard and the authority having jurisdiction.