The third article in the NFPA 25 series covers Chapter 13: common components and valves. The fire pump and sprinkler system articles kept saying “see Chapter 13” for valves, gauges, alarm devices and the fire department connection; this is that chapter. Standpipe, private fire service main and water spray systems send their valves here too. Control valves, alarm, dry pipe, preaction and deluge valves, pressure-reducing valves, hose valves, backflow preventers, fire department connections, the main drain test, waterflow and supervisory devices, compressors and the actions required when a component changes are listed in order, each with its NFPA 25-2026 clause number.
In short: Control valves are inspected weekly; locked or supervised valves monthly and electrically supervised valves quarterly are permitted (13.3.2.1). Every control valve is operated through its full range annually (13.3.3.1). A main drain test is run annually at each water supply lead-in, and a 10 percent drop in full flow pressure must be explained (13.2.2). Vane, paddle and pressure-switch waterflow devices are tested semiannually and must alarm within 90 seconds (13.2.3.2). Gauges are replaced or compared with a calibrated gauge every 5 years (13.2.4.2). Dry pipe valves are trip tested annually and every 3 years with the control valve fully open (13.4.5.2). Backflow preventers get an annual forward flow test at system demand (13.7.2.1). FDC piping is hydrostatically tested at 150 psi (10 bar) for 2 hours every 5 years (13.8.5).
A. Scope and general provisions
Chapter 13 gives the minimum requirements for routine inspection, testing and maintenance of common components and valves (13.1.1.1). Minimum frequencies come from Table 13.1.1.2 (13.1.1.2).
| Check | Criterion | Clause |
| ☐ All system valves | Protected from physical damage and accessible | 13.2.1 |
| ☐ Records | Maintained per Section 4.3 | 13.2.6 |
| ☐ Closing a normally open valve | Follow the impairment procedures of Chapter 15 | 13.3.1.2 |
| ☐ Automatic detection equipment that actuates water-based systems | Inspected, tested and maintained per NFPA 72 | 13.9.1 |
B. Frequency summary: Table 13.1.1.2
The standard’s summary table is reproduced below. Rows marked “—” have no frequency in the table; the requirements sit in the chapter shown on the right. Double entries such as “Annually/3 years” cover two separate tasks on the same item (for example partial and full flow trip tests).
| Item | Frequency | Reference |
| Inspection |
| Alarm valves: exterior | Quarterly | 13.4.1.1 |
| Alarm valves: interior | 5 years | 13.4.1.2 |
| Alarm valves: strainers, filters, orifices | 5 years | 13.4.1.2 |
| Backflow prevention assemblies: reduced pressure | Weekly | 13.7.1 |
| Backflow prevention assemblies: reduced-pressure detectors | Weekly | 13.7.1 |
| Backflow prevention assemblies: interior | 5 years | 13.7.1.3 |
| Check valves: interior | 5 years | 13.4.2.1 |
| Control valves: all valves except locked or supervised | Weekly | 13.3.2.1 |
| Control valves: locked or supervised | Monthly | 13.3.2.1.1 |
| Control valves: electrically supervised | Quarterly | 13.3.2.1.2 |
| Dry pipe valves/quick-opening devices: enclosure (during cold weather) | — | Chapter 4 |
| Dry pipe valves: exterior | Monthly | 13.4.5.1.2 |
| Dry pipe valves: interior | Annually | 13.4.5.1.3 |
| Dry pipe valves: strainers, filters, orifices | 5 years | 13.4.5.1.4 |
| Dry pipe valves: low-temperature alarm | Annually | Chapter 4 |
| Deluge valves: enclosure (during cold weather) | Daily/weekly | Chapter 4 |
| Deluge valves: exterior | Monthly | 13.4.4.1.1 |
| Deluge valves: interior | Annually | 13.4.4.1.2 |
| Deluge valves: strainers, filters, orifices | 5 years | 13.4.4.1.3 |
| Fire department connections | Quarterly | 13.8.1 |
| Gauges | Monthly/quarterly | 13.2.4 |
| Hose valves and hose connections | Quarterly | 13.6.1 |
| Preaction valves: enclosure (during cold weather) | — | Chapter 4 |
| Preaction valves: exterior | Monthly | 13.4.3.1.1 |
| Preaction valves: interior | Annually | 13.4.3.1.2 |
| Preaction valves: strainers, filters, orifices | 5 years | 13.4.3.1.3 |
| Pressure-regulating devices: master pressure-reducing valve | Weekly | 13.5.4.1 |
| Pressure-regulating devices: pressure-reducing valve | Quarterly | 13.5.1.1 |
| Pressure-regulating devices: pressure-reducing hose connection | Annually | 13.5.2.1 |
| Pressure-regulating devices: pressure-reducing hose valve with hose rack assembly | Annually | 13.5.3.1 |
| Valve supervisory signal initiating device | Quarterly | 13.3.2.1.3 |
| Supervisory signal devices (except valve supervisory switches) | Quarterly | 13.2.5.1 |
| Air compressors or nitrogen generators | Monthly | 13.10.2 |
| Corrosion inhibitor systems | Per manufacturer | 13.11 |
| Waterflow alarms | Quarterly | 13.2.3 |
| Testing |
| Backflow prevention assemblies | Annually | 13.7.2 |
| Control valves: operation and position | Annually | 13.3.3.1 |
| Control valves: valve status test | After control valve is closed and reopened | 13.3.3.4 |
| Control valves: valve supervisory signal initiating device | Semiannually | 13.3.3.5.1 |
| Deluge valves: solenoid supervisory | Quarterly | 13.4.4.2.14 |
| Deluge valves: trip test | Annually/3 years | 13.4.4.2.3 |
| Dry pipe valves: air leakage | 3 years | 13.4.5.2.9 |
| Dry pipe valves: priming water | Quarterly | 13.4.5.2.1 |
| Dry pipe valves: low and high air pressure alarm | Annually | 13.4.5.2.6 |
| Dry pipe valves: quick-opening devices | Quarterly | 13.4.5.2.4 |
| Dry pipe valves: trip test | Annually | 13.4.5.2.2 |
| Dry pipe valves: full-flow trip test | 3 years | 13.4.5.2.2.2 |
| Gauges | 5 years | 13.2.4.2 |
| Main drains | Annually/quarterly | 13.2.2 |
| Preaction valves: priming water | Quarterly | 13.4.3.2.1 |
| Preaction valves: low and high air pressure alarms | Quarterly | 13.4.3.2.11 |
| Preaction valves: solenoid supervisory | Quarterly | 13.4.4.2.14* |
| Preaction valves: trip test | Annually/3 years | 13.4.3.2.2 and 13.4.3.2.3 |
| Preaction valves: air leakage | 3 years | 13.4.3.2.6 |
| Preaction valves: low-temperature alarm | Annually | 13.4.3.2.12* |
| Pressure-regulating devices: master pressure-reducing valve | Quarterly/annually | 13.5.4.2 and 13.5.4.3 |
| Pressure-regulating devices: pressure-reducing valve | Annually/5 years | 13.5.1.3 and 13.5.1.2 |
| Pressure-regulating devices: pressure-reducing hose valve | Annually/5 years | 13.5.2.3 and 13.5.2.2 |
| Pressure-regulating devices: pressure-reducing hose valve with rack assembly | Annually/5 years | 13.5.3.3 and 13.5.3.2 |
| Air compressors or nitrogen generators | Annually | 13.10.3 |
| Hose valves | Annually/3 years | 13.6.2 |
| Waterflow alarms | Quarterly/semiannually | 13.2.3 |
| Supervisory signal devices (except valve supervisory switches) | Annually | 13.2.5.2 |
| Maintenance |
| Alarm valves | Per manufacturer | 13.4.1.3 |
| Backflow prevention assemblies | Per manufacturer | 13.7.3 |
| Check valves | Per manufacturer | 13.4.2.2 |
| Control valves (outside screw and yoke) | Annually | 13.3.4 |
| Deluge valves | Annually | 13.4.4.3 |
| Dry pipe valves/quick-opening devices | Annually | 13.4.5.3 |
| Hose valves | As needed | 13.6.3 |
| Preaction valves | Annually | 13.4.3.3 |
| Air compressors or nitrogen generators | Per manufacturer | 13.10.4 |
| Corrosion-inhibiting systems | Per manufacturer | 13.11 |
* For preaction valves the table cites 13.4.4.2.14 on the solenoid supervisory row and 13.4.3.2.12 on the low-temperature alarm row; in the text the matching preaction clauses are 13.4.3.2.12 (solenoid supervisory) and 13.4.3.2.13 (low-temperature alarm). The frequencies are the same in both places.
C. Main drain test
The main drain test is how you tell whether the condition of the water supply has changed (13.2.2).
| Check | Criterion | Clause |
| ☐ Each water supply lead-in to a building water-based system | Main drain test annually | 13.2.2 |
| ☐ Lead-in supplies a header or manifold serving multiple systems | A single main drain test is permitted | 13.2.2.1 |
| ☐ Sole water supply is through a backflow preventer and/or pressure-reducing valves | Main drain test of at least one downstream system quarterly | 13.2.2.2 |
| ☐ 10 percent reduction in full flow pressure versus the acceptance test or previous tests | Cause identified and corrected if necessary | 13.2.2.3 |
D. Waterflow alarm devices
Mechanical alarms (including water motor gongs) and vane, paddle and pressure-switch devices
| Check | Criterion | Clause |
| ☐ Mechanical waterflow alarm devices: physical damage | Inspected quarterly | 13.2.3.1.1 |
| ☐ Mechanical waterflow alarm devices: test | Quarterly | 13.2.3.1.2 |
| ☐ Mechanical alarm response | Audible alarm starts within 5 minutes of flow beginning and continues until flow stops | 13.2.3.1.3 |
| ☐ Vane-, paddle- and pressure-switch-type devices: physical damage | Inspected quarterly | 13.2.3.2.1 |
| ☐ Vane-, paddle- and pressure-switch-type devices: test | Semiannually | 13.2.3.2.2 |
| ☐ Electrical device response | Within 90 seconds of waterflow at the alarm-initiating device, at a flow equal to one sprinkler of the smallest orifice size in the system | 13.2.3.2.3 |
Test method
| Check | Criterion | Clause |
| ☐ Testing on wet pipe systems | Open the inspector’s test connection or use automated test equipment per Section 4.7 | 13.2.3.3 |
| ☐ Freezing weather or other conditions prohibit use of the inspector’s test connection | The bypass connection is permitted | 13.2.3.4 |
| ☐ Vane-type devices on wet pipe systems | Flow equivalent to the smallest single K-factor sprinkler (or smaller) past the flow switch | 13.2.3.5 |
| ☐ Listed vane-type device with integral automated test feature | Permitted where it verifies water at the device location and proper function of device and alarm | 13.2.3.5.1 |
| ☐ Vane-type devices tested semiannually with circulated water or per 13.2.3.5.1 | Tested by opening the inspector’s test connection at least once every 3 years | 13.2.3.5.2 |
| ☐ Testing on dry pipe, preaction or deluge systems | Any of: bypass connection, inspector’s test connection, or automated test equipment per Section 4.7 | 13.2.3.6 |
Device status during testing and maintenance
| Check | Criterion | Clause |
| ☐ Vane-type devices | Remain in service unless impairment procedures per NFPA 72 or an approved fire alarm code are followed | 13.2.3.7.1 |
| ☐ Disabling by preventing movement of the vane or stem | Prohibited | 13.2.3.7.1.1 |
| ☐ Waterflow alarm circuits | Not interrupted or disabled except as permitted by NFPA 72 or an approved fire alarm code | 13.2.3.7.1.2 |
E. Gauges and supervisory signal devices
| Check | Criterion | Clause |
| ☐ All gauges | Monthly: operable and not physically damaged | 13.2.4.1.1 |
| ☐ Gauges monitoring water pressure | Quarterly: normal supply pressure maintained | 13.2.4.1.2 |
| ☐ Gauges monitoring air or nitrogen pressure | Monthly: normal air or nitrogen pressure maintained | 13.2.4.1.3 |
| ☐ Quick-opening device gauge (if provided) | Reads the same as the gauge on the system side of the dry pipe valve | 13.2.4.1.3.1 |
| ☐ Air pressure supervision connected to a constantly attended location | Gauges may be inspected quarterly | 13.2.4.1.3.2 |
| ☐ Dry pipe or preaction systems protecting freezers with gauges on the air line between compressor and valve | Compressor gauge compared monthly with the gauge above the valve | 13.2.4.1.4 |
| ☐ Compressor gauge reads higher than the valve gauge | Take the air line in service out of service and open the alternate air line to equalize | 13.2.4.1.4.1 |
| ☐ Air line taken out of service | Internally inspected, cleared of all ice blockage and reassembled as a future alternate line | 13.2.4.1.4.2 |
| ☐ Gauge replacement or calibration | Replaced every 5 years after installation or tested every 5 years by comparison with a calibrated gauge | 13.2.4.2 |
| ☐ Gauge not accurate to within 3 percent of full scale | Recalibrated or replaced | 13.2.4.3 |
| ☐ Supervisory signal devices (except valve supervisory switches) | Quarterly: free of physical damage | 13.2.5.1 |
| ☐ Supervisory signal devices: test | Annually, per the manufacturer’s instructions | 13.2.5.2 |
F. Control valves
Identification and securing
| Check | Criterion | Clause |
| ☐ Each control valve | Identified, with a sign indicating the system or portion it controls | 13.3.1 |
| ☐ More than one valve must be closed to work on a system | Sign on each affected valve referring to the existence and location of the others | 13.3.1.1 |
| ☐ Normally open valves | Secured by seal or lock, or electrically supervised per the applicable NFPA standards | 13.3.1.3 |
| ☐ Normally closed valves | Secured by seal, or electrically supervised per the applicable NFPA standard | 13.3.1.4 |
| ☐ Hose valves | Sealing or electrical supervision not required | 13.3.1.5 |
Inspection frequency and criteria
| Check | Criterion | Clause |
| ☐ All valves | Inspected weekly | 13.3.2.1 |
| ☐ Valves secured with locks or supervised per applicable NFPA standards | May be inspected monthly | 13.3.2.1.1 |
| ☐ Electrically supervised valves | May be inspected quarterly | 13.3.2.1.2 |
| ☐ Control valve supervisory alarm devices | Quarterly: free of physical damage | 13.3.2.1.3 |
| ☐ After any alterations or repairs | Owner or designated representative verifies the system is in service and all valves are in the normal position and properly sealed, locked or electrically supervised | 13.3.2.1.4 |
| ☐ Position | Normal open or closed position | 13.3.2.2(1) |
| ☐ Security | Sealed, locked or supervised | 13.3.2.2(2) |
| ☐ Access | Accessible | 13.3.2.2(3) |
| ☐ Post indicator valves (PIVs) | Provided with correct wrenches | 13.3.2.2(4) |
| ☐ Leakage | Free from external leaks | 13.3.2.2(5) |
| ☐ Identification | Provided with applicable identification | 13.3.2.2(6) |
Testing and maintenance
| Check | Criterion | Clause |
| ☐ Each control valve | Operated annually through its full range and returned to its normal position | 13.3.3.1 |
| ☐ Post indicator valves | Opened until spring or torsion is felt in the rod, showing the rod has not detached from the valve | 13.3.3.2 |
| ☐ PIV spring/torsion test | Conducted every time the valve is closed | 13.3.3.2.1 |
| ☐ PIVs and OS&Y valves | Backed a one-quarter turn from fully open to prevent jamming | 13.3.3.3 |
| ☐ Control valve closed and reopened at the system riser | Valve status test every time | 13.3.3.4 |
| ☐ Valve supervisory switches | Tested semiannually | 13.3.3.5.1 |
| ☐ Supervisory signal | Distinctive signal within the first two revolutions of the handwheel or when the stem has moved one-fifth of the distance from its normal position | 13.3.3.5.2 |
| ☐ Signal restoration | Not restored at any valve position except the normal position | 13.3.3.5.3 |
| ☐ OS&Y valve operating stems | Lubricated annually | 13.3.4.1 |
| ☐ After lubrication | Valve completely closed and reopened to test operation and distribute the lubricant | 13.3.4.2 |
G. Alarm valves and check valves
Alarm valves and system riser check valves are externally inspected quarterly to verify the following (13.4.1.1):
| Check | Criterion | Clause |
| ☐ Gauges | Indicate normal supply water pressure is maintained | 13.4.1.1(1) |
| ☐ Valves and trim | Free of physical damage | 13.4.1.1(2) |
| ☐ All valves | In the appropriate open or closed position | 13.4.1.1(3) |
| ☐ Retarding chamber or alarm drains | Not leaking | 13.4.1.1(4) |
| ☐ Valve in the connection to pressure-type contacts or water motor–operated alarm devices (where applicable) | Sealed, locked or electrically supervised in the open position | 13.4.1.1(5) |
| ☐ Alarm valves with strainers, filters and restriction orifices | Internal inspection every 5 years unless tests indicate a greater frequency | 13.4.1.2 |
| ☐ Alarm valve internal components | Cleaned/repaired as necessary per the manufacturer’s instructions | 13.4.1.3.1 |
| ☐ Return to service | Per the manufacturer’s instructions | 13.4.1.3.2 |
| ☐ Check valves | Internal inspection every 5 years; all components operate correctly | 13.4.2.1 |
| ☐ Check valve internal components | Cleaned, repaired or replaced as necessary per the manufacturer’s instructions | 13.4.2.2 |
H. Preaction valves
Inspection
| Check | Criterion | Clause |
| ☐ External inspection | Monthly: valve free from physical damage; all trim valves in the appropriate position; valve seat not leaking; electrical components in service; valve in the connection to pressure-type contacts or water motor–operated alarms (where applicable) sealed, locked or electrically supervised open | 13.4.3.1.1 |
| ☐ Valve interior and condition of detection devices | Annually, when the trip test is conducted | 13.4.3.1.2 |
| ☐ Strainers, filters and restricted orifices | Internal inspection every 5 years unless tests indicate a greater frequency | 13.4.3.1.3 |
| ☐ Preaction systems with auxiliary drains | Sign at the valve showing the number of auxiliary drains and the location of each | 13.4.3.1.4 |
Testing
| Check | Criterion | Clause |
| ☐ Priming water level in supervised systems | Quarterly, for compliance with the manufacturer’s instructions | 13.4.3.2.1 |
| ☐ Trip test with control valve fully open | Every 3 years (except systems protecting freezers) | 13.4.3.2.2 |
| ☐ Years without full flow testing | Trip test with the control valve partially open | 13.4.3.2.3 |
| ☐ Scope of flow tests | Full functionality of the system as a unit, including automatic and manual activation | 13.4.3.2.4 |
| ☐ Valves protecting freezers | Trip tested without introducing moisture into the freezer piping | 13.4.3.2.5 |
| ☐ Air leakage test (every 3 years), method 1 | Pressure test at 40 psi for 2 hours; loss of up to 3 psi (0.2 bar) permitted, more than that and leaks are addressed | 13.4.3.2.6(1) |
| ☐ Air leakage test, method 2 | At normal system pressure, shut off the air source (compressor or shop air) for 4 hours; if the low air pressure alarm operates, leaks are addressed | 13.4.3.2.6(2) |
| ☐ Manual actuation devices | Operated annually | 13.4.3.2.7 |
| ☐ After the annual trip test | System returned to service per the manufacturer’s instructions | 13.4.3.2.8 |
| ☐ Valve seating surfaces | No grease or other sealing materials applied | 13.4.3.2.9 |
| ☐ Trip records | Date last tripped, tripping time, and the individual and organization conducting the test, readily available to the AHJ | 13.4.3.2.10 |
| ☐ Low and high air pressure alarms (if provided) | Quarterly, per the manufacturer’s instructions | 13.4.3.2.11 |
| ☐ Solenoid supervisory signal device monitoring coil position | Quarterly | 13.4.3.2.12 |
| ☐ Low-temperature alarms in valve enclosures (if installed) | Annually, toward the beginning of the heating season before freezing conditions | 13.4.3.2.13 |
| ☐ Automatic air pressure maintenance devices (if provided) | Annually at the time of the annual trip test, per the manufacturer’s instructions | 13.4.3.2.14 |
| ☐ Systems using nitrogen for an increased C value per NFPA 13 | Nitrogen supply tested semiannually; concentration 98 percent or greater | 13.4.3.2.15 |
| ☐ Nitrogen concentration monitored at a constantly attended location | Concentration verified annually | 13.4.3.2.15.1 |
| ☐ Nitrogen concentration below 98 percent | Cause identified and corrected | 13.4.3.2.15.2 |
Maintenance
| Check | Criterion | Clause |
| ☐ Leaks dropping supervisory pressure enough to sound warning alarms, and electrical malfunctions causing alarms | Located and repaired | 13.4.3.3.1 |
| ☐ During the annual trip test | Valve interior cleaned thoroughly; parts replaced or repaired as necessary | 13.4.3.3.2 |
| ☐ Auxiliary drains | Operated after each system operation, toward the beginning of the heating season before freezing (where applicable), and thereafter as needed | 13.4.3.3.3 |
| ☐ Additional maintenance | As required by the manufacturer’s instructions | 13.4.3.3.4 |
I. Deluge valves
Inspection
| Check | Criterion | Clause |
| ☐ External inspection | Monthly: the same five criteria as preaction valves (damage, trim valve position, seat leakage, electrical components, alarm connection valve) | 13.4.4.1.1 |
| ☐ Valve interior and condition of detection devices | Annually, when the trip test is conducted | 13.4.4.1.2 |
| ☐ Strainers, filters, restricted orifices and diaphragm chambers | Internal inspection every 5 years unless tests indicate a greater frequency | 13.4.4.1.3 |
Trip and flow tests
| Check | Criterion | Clause |
| ☐ Scope of flow tests | Full functionality of the system as a unit, including automatic and manual activation | 13.4.4.2.1 |
| ☐ Devices or equipment subject to damage by discharge | Protected during flow tests | 13.4.4.2.2 |
| ☐ Annual full flow trip test | Each deluge valve annually at full flow, in warm weather, per the manufacturer’s instructions | 13.4.4.2.3 |
| ☐ Water cannot be discharged for test purposes | Annual trip test may be done without discharge in the protected area | 13.4.4.2.3.1 |
| ☐ Water cannot be discharged unless protected equipment is shut down (e.g., energized electrical equipment) | Full flow test at the next scheduled shutdown | 13.4.4.2.3.2 |
| ☐ Full flow tests per 13.4.4.2.3.2 | Frequency not to exceed 3 years | 13.4.4.2.3.3 |
| ☐ Open spray nozzles or sprinklers | During the annual full flow test, discharge patterns observed: no plugged nozzles, nozzles correctly positioned, obstructions do not prevent wetting of protected surfaces | 13.4.4.2.4 |
| ☐ Where water cannot be discharged | Nozzles or open sprinklers inspected for correct orientation | 13.4.4.2.4.1 |
| ☐ Where discharge requires equipment shutdown | All nozzles and open sprinklers inspected per 13.4.4.2.4 during the full flow test at the next scheduled shutdown | 13.4.4.2.4.2 |
| ☐ Misalignment or obstructions | Piping and nozzles adjusted and/or cleaned and the system retested | 13.4.4.2.4.3 |
| ☐ Full flow tests (13.4.4.2.3 and 13.4.4.2.3.2) | Conducted with the deluge system control valve fully open | 13.4.4.2.5 |
| ☐ Trip tests per 13.4.4.2.3.1 | May be conducted with the control valve partially open | 13.4.4.2.6 |
| ☐ Maximum number of systems expected to operate in a fire | Tested simultaneously to inspect the adequacy of the water supply | 13.4.4.2.8 |
| ☐ Manual actuation devices | Operated annually | 13.4.4.2.9 |
| ☐ After the annual trip test | System returned to service per the manufacturer’s instructions | 13.4.4.2.10 |
| ☐ Valve seating surfaces | No grease or other sealing materials applied | 13.4.4.2.11 |
| ☐ Trip records | Date last tripped, tripping time, and the individual and organization conducting the test, readily available to the AHJ | 13.4.4.2.12 |
Pressure readings
| Check | Criterion | Clause |
| ☐ Hydraulically most remote nozzle or sprinkler | Pressure reading recorded | 13.4.4.2.7.1 |
| ☐ Deluge valve | Second pressure reading recorded | 13.4.4.2.7.2 |
| ☐ Evaluation | Readings compared to hydraulic design pressures to confirm the water supply meets the original design requirements | 13.4.4.2.7.3 |
| ☐ Most remote nozzle or sprinkler inaccessible | Except in foam-water sprinkler systems, visual inspection without a remote pressure reading is permitted | 13.4.4.2.7.4 |
| ☐ Riser reading shows the water supply has deteriorated | A gauge is placed on the most remote nozzle or sprinkler and results compared with the required design pressure | 13.4.4.2.7.5 |
Supervisory devices and maintenance
| Check | Criterion | Clause |
| ☐ Low air pressure supervisory devices on the detection system (if provided) | Tested quarterly per the manufacturer’s instructions | 13.4.4.2.13 |
| ☐ Solenoid supervisory signal device monitoring coil position | Tested quarterly | 13.4.4.2.14 |
| ☐ Low-temperature alarms in valve enclosures (if installed) | Annually, toward the beginning of the heating season before freezing conditions | 13.4.4.2.15 |
| ☐ Automatic air pressure maintenance devices on the detection system (if provided) | Annually at the time of the annual trip test | 13.4.4.2.16 |
| ☐ Leaks and electrical malfunctions causing alarms | Located and repaired | 13.4.4.3.1 |
| ☐ During the annual trip test | Valve interior cleaned thoroughly; internal and external trim parts replaced or repaired as necessary | 13.4.4.3.2, 13.4.4.3.2.1 |
| ☐ Valves that can be reset without removing a faceplate | Interior cleaning permitted every 5 years | 13.4.4.3.2.2 |
| ☐ Auxiliary drains | Operated after each system operation, toward the beginning of the heating season before freezing, and thereafter as needed | 13.4.4.3.3 |
| ☐ Additional maintenance | As required by the manufacturer’s instructions | 13.4.4.3.4 |
J. Dry pipe valves and quick-opening devices
Inspection
| Check | Criterion | Clause |
| ☐ Systems with auxiliary drains | Sign at the dry valve showing the number of auxiliary drains and the location of each | 13.4.5.1.1 |
| ☐ Valve | Monthly: free of physical damage | 13.4.5.1.2(1) |
| ☐ Trim valves | Monthly: in the appropriate open or closed position | 13.4.5.1.2(2) |
| ☐ Valve between the riser and the quick-opening device (where applicable) | Sealed, locked or electrically supervised in the open position | 13.4.5.1.2(3) |
| ☐ Intermediate chamber | Not leaking | 13.4.5.1.2(4) |
| ☐ Valve in the connection to pressure-type contactors or water motor–operated alarms (where applicable) | Sealed, locked or electrically supervised in the open position | 13.4.5.1.2(5) |
| ☐ Valve interior | Annually, when the trip test is conducted | 13.4.5.1.3 |
| ☐ Strainers, filters and restricted orifices | Internal inspection every 5 years unless tests indicate a greater frequency | 13.4.5.1.4 |
Testing
| Check | Criterion | Clause |
| ☐ Priming water level | Tested quarterly | 13.4.5.2.1 |
| ☐ Trip test | Each dry pipe valve annually, during warm weather | 13.4.5.2.2 |
| ☐ Valves protecting freezers | Trip tested without introducing moisture into the freezer piping | 13.4.5.2.2.1 |
| ☐ Full flow trip test | Every 3 years and whenever the system is altered; control valve fully open and quick-opening device (if provided) in service | 13.4.5.2.2.2 |
| ☐ Years without full flow testing | Trip test with the control valve partially open | 13.4.5.2.2.3 |
| ☐ Refilling a dry system | Air supply able to restore normal air pressure within 30 minutes | 13.4.5.2.2.4 |
| ☐ Refrigerated spaces maintained below 5 °F (−15 °C) | Normal air pressure may be restored within 60 minutes | 13.4.5.2.2.5 |
| ☐ Valve seating surfaces | No grease or other sealing materials applied | 13.4.5.2.3 |
| ☐ Quick-opening devices (if provided) | Tested quarterly | 13.4.5.2.4 |
| ☐ Tag or card attached to the valve | Date last tripped and the name of the person and organization conducting the test | 13.4.5.2.5 |
| ☐ Separate records kept on the premises | Initial air and water pressure, tripping air pressure and valve operating conditions, for comparison with previous tests | 13.4.5.2.5.1 |
| ☐ Records for full flow trip tests | Valve tripping time and water transit time to the inspector’s test connection | 13.4.5.2.5.2 |
| ☐ Low and high air pressure alarms (if provided) | Annually, per the manufacturer’s instructions | 13.4.5.2.6 |
| ☐ Low-temperature alarms in valve enclosures (if installed) | Annually, at the beginning of the heating season | 13.4.5.2.7 |
| ☐ Automatic air pressure maintenance devices (if provided) | Annually during the trip test, per the manufacturer’s instructions | 13.4.5.2.8 |
| ☐ Gas leakage test (every 3 years), method 1 | Gas (air or nitrogen) pressure test at 40 psi for 2 hours; loss of up to 3 psi (0.2 bar) permitted, more than that and leaks are addressed | 13.4.5.2.9(1) |
| ☐ Gas leakage test, method 2 | At normal system pressure, shut off the gas source (nitrogen supply, compressor or shop air) for 4 hours; if the low pressure alarm operates, leaks are addressed | 13.4.5.2.9(2) |
| ☐ Systems using nitrogen for an increased C value per NFPA 13 | Nitrogen supply tested semiannually; concentration 98 percent or greater | 13.4.5.2.10 |
| ☐ Nitrogen concentration monitored at a constantly attended location | Concentration verified annually | 13.4.5.2.10.1 |
| ☐ Nitrogen concentration below 98 percent | Cause identified and corrected | 13.4.5.2.10.2 |
Maintenance
| Check | Criterion | Clause |
| ☐ During the annual trip test | Valve interior cleaned thoroughly; internal and external trim parts replaced or repaired as necessary | 13.4.5.3.1, 13.4.5.3.1.1 |
| ☐ Quick-opening devices | Maintained in working order per the manufacturer’s requirements | 13.4.5.3.2 |
| ☐ Auxiliary drains | Drained after each system operation, toward the beginning of the heating season before freezing, and thereafter as needed | 13.4.5.3.3 |
K. Pressure-regulating devices
Pressure-reducing valves
| Check | Criterion | Clause |
| ☐ All pressure-reducing valves | Quarterly: in the open position; not leaking; maintaining downstream pressures per the design criteria; handwheels installed and unbroken | 13.5.1.1 |
| ☐ Each control valve | Operated annually through its full range and returned to its normal position | 13.5.1.2 |
| ☐ Partial flow test | Annually, adequate to move the valve from its seat | 13.5.1.3 |
| ☐ Full flow test | Each valve at 5-year intervals; compared to previous results | 13.5.1.4 |
| ☐ Valve adjustments | Per the manufacturer’s instructions | 13.5.1.4.1 |
Hose connection pressure-regulating devices
| Check | Criterion | Clause |
| ☐ Pressure-reducing hose valves | Annually: handwheel not broken or missing; outlet hose threads undamaged; no leaks; hose adapter and cap not missing | 13.5.2.1 |
| ☐ Each pressure-reducing hose valve | Operated annually through its full range and returned to its normal position | 13.5.2.2 |
| ☐ Flow test at maximum flow rate | Each device at 5-year intervals | 13.5.2.3 |
| ☐ Flow test results | Compared to previous test results | 13.5.2.3.1 |
| ☐ Valve adjustments | Per the manufacturer’s instructions | 13.5.2.3.2 |
| ☐ Tag attached to the valve | Test date, flow in gpm (L/min), static and residual inlet pressures, and residual outlet pressure recorded during the test | 13.5.2.4 |
| ☐ Pressure-reducing hose valve with hose rack assembly: rack | Inspected and tested per NFPA 1930 | 13.5.3.1 |
| ☐ Pressure-reducing hose valve with hose rack assembly: valve | Inspected and tested per 13.5.2 | 13.5.3.2 |
Master pressure-reducing valves
| Check | Criterion | Clause |
| ☐ Weekly inspection | Normal downstream and supply pressures maintained; devices and trim free of physical damage and not leaking | 13.5.4.1 |
| ☐ Partial flow test | Quarterly, adequate to move the valve from its seat | 13.5.4.2 |
| ☐ Flow test | Each valve annually at maximum and minimum anticipated flow rates | 13.5.4.3 |
| ☐ Pressure-reducing valves in series | Downstream valve tested both at the discharge pressure of the upstream valve and with the upstream valve bypass open | 13.5.4.3.1 |
| ☐ Flow test results | Compared to previous test results | 13.5.4.3.2 |
| ☐ Valve adjustments | Per the manufacturer’s instructions | 13.5.4.4 |
| ☐ Damaged or missing components noted during inspections | Repaired or replaced per the manufacturer’s instructions | 13.5.5 |
L. Hose valves and hose connections
Hose valves are inspected quarterly (13.6.1.1). Test frequency depends on the standpipe class; the standpipe system itself is covered in the series’ Chapter 6 article.
| Check | Criterion | Clause |
| ☐ Hose connection thread protection | In place | 13.6.1.1(1) |
| ☐ Hose connection caps not rated for pressure | Have an opening of at least 1/8 in. in diameter | 13.6.1.1(2) |
| ☐ Hose threads | Not damaged | 13.6.1.1(3) |
| ☐ Valve handles | Present and not damaged | 13.6.1.1(4) |
| ☐ Gaskets | Not damaged or showing signs of deterioration | 13.6.1.1(5) |
| ☐ Leaks | None present | 13.6.1.1(6) |
| ☐ Valve | Not obstructed and capable of normal operation | 13.6.1.1(7) |
| ☐ Restricting devices | Present where required | 13.6.1.2 |
| ☐ Removal of existing restricting devices | Permitted where approved by the AHJ, and not recorded as a deficiency | 13.6.1.3 |
| ☐ Class I and Class III standpipe hose valves | Tested annually by fully opening and closing | 13.6.2.1 |
| ☐ Class I and III hose valves difficult to operate or leaking | Repaired or replaced | 13.6.2.1.1 |
| ☐ Hose valves on hose stations attached to sprinkler systems and Class II standpipes | Tested every 3 years by opening and closing | 13.6.2.2 |
| ☐ Those that are difficult to operate or leak | Repaired or replaced | 13.6.2.2.1 |
| ☐ Hose valves that do not operate smoothly or open fully | Lubricated, repaired or replaced | 13.6.3 |
M. Backflow prevention assemblies
| Check | Criterion | Clause |
| ☐ Reduced-pressure (RP) and reduced-pressure detector (RPDA) assemblies | Weekly: differential-sensing valve relief port not continuously discharging | 13.7.1.1 |
| ☐ After any testing or repair | Owner or designated representative verifies the system is in service and all isolation valves are normally open and properly locked or electrically supervised | 13.7.1.2 |
| ☐ Internal inspection | Every 5 years; all components operate correctly, move freely and are in good condition | 13.7.1.3 |
| ☐ Forward flow test | All backflow preventers in fire protection piping exercised annually at a minimum flow rate of the system demand | 13.7.2.1 |
| ☐ Water rationing during shortages lasting more than 1 year | Internal inspection verifying the check valves will fully open is permitted in lieu of the annual forward flow test | 13.7.2.1.1 |
| ☐ Annual fire pump testing flows the system flow rate through the backflow preventer | Separate forward flow test not required | 13.7.2.1.2 |
| ☐ Hydrants or inside hose stations downstream | Forward flow test includes hose stream demand | 13.7.2.2 |
| ☐ Connections do not permit verification at system demand | Test at the maximum flow rate possible | 13.7.2.3 |
| ☐ Maintenance | By qualified personnel per the manufacturer’s instructions and the AHJ’s procedures and policies | 13.7.3 |
N. Fire department connections
Fire department connections are inspected quarterly to verify the following (13.8.1):
| Check | Criterion | Clause |
| ☐ Visibility and access | Connection visible and accessible | 13.8.1(1) |
| ☐ Couplings or swivels | Not damaged and rotate smoothly | 13.8.1(2) |
| ☐ Plugs or caps | In place and undamaged | 13.8.1(3) |
| ☐ Gaskets | In place | 13.8.1(4) |
| ☐ Identification signs | In place | 13.8.1(5) |
| ☐ Check valve | Not leaking | 13.8.1(6) |
| ☐ Automatic drain valve | In place and operating properly | 13.8.1(7) |
| ☐ FDC clapper(s) | In place and operating properly | 13.8.1(8) |
| ☐ Interior of the connection | Inspected for obstructions | 13.8.1(9) |
| ☐ Visible piping supplying the FDC | Undamaged | 13.8.1(10) |
| ☐ Connections with approved locking caps or plugs | Interior inspection annually | 13.8.2 |
| ☐ Components | Repaired or replaced as necessary per the manufacturer’s instructions | 13.8.3 |
| ☐ Obstructions found | Removed | 13.8.4 |
| ☐ Piping from the FDC to the fire department check valve | Hydrostatic test at 150 psi (10 bar) for 2 hours at least once every 5 years | 13.8.5 |
| ☐ Acceptable result | Pressure loss less than 5 psi (0.3 bar) and no visual signs of leakage | 13.8.5.1 |
| ☐ Piping 10 ft (3.0 m) or less that can be visually inspected internally and externally | 5-year hydrostatic test not required | 13.8.5.2 |
| ☐ Check valves | Internally inspected per 13.4.2.1 | 13.8.6 |
O. Detection, compressors, corrosion inhibition and air vents
| Check | Criterion | Clause |
| ☐ Automatic detection equipment not covered by NFPA 72 | Detectors in place, securely fastened and protected from corrosion, weather and mechanical damage; communication wiring, control panels or pneumatic tubing functional | 13.9.2 |
| ☐ Air compressors and nitrogen generators dedicated to water-based systems | Inspected, tested and maintained per 13.10.2, 13.10.3 and 13.10.4 | 13.10.1.1 |
| ☐ Air compressors not dedicated to water-based systems | Inspected, tested and maintained per the manufacturer’s instructions | 13.10.1.2 |
| ☐ Monthly inspection: unit | Compressor or nitrogen generator free of physical damage | 13.10.2(1) |
| ☐ Monthly inspection: power wiring | Power wiring to the compressor intact and free of physical damage | 13.10.2(2) |
| ☐ Monthly inspection: piping | Piping from the unit to the fire protection system intact and free of physical damage | 13.10.2(3) |
| ☐ Monthly inspection: anchoring | Anchoring to the structure or system piping secure, tight and free of damage | 13.10.2(4) |
| ☐ Monthly inspection: oil | Compressors requiring oil have the required amount in the reservoir | 13.10.2(5) |
| ☐ Monthly inspection: corrosion-inhibiting equipment | Intact and free of physical damage | 13.10.2(6) |
| ☐ Annual test | Unit operates on the proper drop of system air pressure; restores normal supervisory pressure in the required time frame; compressor does not overheat while running | 13.10.3 |
| ☐ Maintenance | Per the manufacturer’s instructions | 13.10.4.1 |
| ☐ Compressors requiring oil | Oil replaced annually unless the manufacturer requires more frequent replacement | 13.10.4.2 |
| ☐ Corrosion-inhibiting equipment | Inspection: intact and undamaged; testing: per the manufacturer’s instructions; maintenance: where required for corrosion mitigation, per the manufacturer’s instructions | 13.11.1–13.11.3 |
| ☐ Automatic air vents | Annually from the floor level: free of physical damage, no signs of leakage | 13.12 |
| ☐ Air vent strainers, filters and screens | Removed and inspected every 5 years for damaged or corroded parts; when removed, flushed until clear or replaced | 13.12.1, 13.12.2 |
P. When a component is adjusted, repaired or replaced: Table 13.13.1
Whenever a valve, valve component and/or valve trim is adjusted, repaired, reconditioned or replaced, the action in Table 13.13.1 is performed (13.13.1). Where the original installation standard differs from the cited one, the appropriate installing standard may be used (13.13.2). These actions do not require a design review (13.13.3).
| Component | Adjust | Repair/recondition | Replace | Inspection, test and maintenance procedure |
| Water delivery components |
| Post indicator and wall indicator valves | X | X | X | (1) Inspect for leaks at system pressure; (2) Full operational test conforming to 13.3.3.1; (3) Spring torsion inspection conforming to 13.3.3.2; (4) Verify target visibility at shut and full open position; (5) Test supervisory device; (6) Valve status test |
| Control valves other than post indicator and wall indicator valves | X | X | X | (1) Inspect for leaks at system pressure; (2) Full operational test conforming to 13.3.3.1; (3) Back one-quarter turn from fully open to prevent jamming per 13.3.3.3; (4) Verify supervisory device; (5) Valve status test |
| Alarm check valve | X | X | X | (1) Inspect for leaks at system pressure per 13.4.1; (2) Test all alarms and supervisory signals affected by the alarm valve; (3) Valve status test |
| Dry pipe valve | X | X | X | (1) Inspect for leaks at system pressure; (2) Trip test per 13.4.5.2; (3) Inspect condition of valve seat; (4) Test all dry pipe system alarms and supervisory signals; (5) Valve status test |
| Deluge/preaction valve | X | X | X | (1) Inspect for leaks at system pressure per 13.4.4/13.4.3; (2) Trip test; (3) Inspect condition of valve seat; (4) Test all deluge/preaction system alarms and supervisory signals; (5) Valve status test |
| Quick-opening device | X | X | X | (1) Inspect for leaks at system pressure per 13.4.5.2.9; (2) Trip test; (3) Valve status test |
| Pressure-regulating device: hose valves | X | X | X | (1) Inspect for leaks at system pressure per 13.5.2; (2) Full flow test; (3) Valve status test |
| Pressure-regulating devices: other than hose valves | X | X | X | (1) Inspect for leaks at system pressure per Section 13.5; (2) Test pressure setting with full flow and without flow; (3) Test supervisory device and alarm; (4) Valve status test |
| Hose valve | X | X | X | (1) Inspect for leaks at system pressure per Section 13.6; (2) Valve status test |
| Backflow prevention device | X | X | X | (1) Inspect for leaks at system pressure per Section 13.7; (2) Forward flow test per 13.7.2.1; (3) Test supervisory device and alarm; (4) Valve status test |
| Check valves | X | X | X | (1) Inspect for leaks at system pressure per 13.4.2; (2) Inspect for leaking through check valve; (3) Valve status test |
| Fire department connection | X | X | — | (1) Inspect for leaks at system pressure per Section 13.8; (2) Valve status test |
| Fire department connection: sprinkler system(s) | — | — | X | (1) Isolate and hydrostatic test for 2 hours at 150 psi (10 bar); (2) Valve status test |
| Fire department connection: other than sprinkler system(s) | — | — | X | (1) Isolate and hydrostatic test for 2 hours at 50 psi (3.5 bar) above the normal working pressure [200 psi (14 bar) minimum]; (2) Valve status test |
| Strainers | X | X | X | Inspect and clean in accordance with manufacturer’s instructions |
| Main drain valves | X | X | X | Main drain test per 13.2.2 |
| Gauges | — | — | X | Calibrate per 13.2.4 |
| Alarm and supervisory components |
| Alarm device | X | X | X | Test for conformance with NFPA 13 and/or NFPA 72 |
| Supervisory device | X | X | X | Test for conformance with NFPA 13 and/or NFPA 72 |
| System protection components |
| Pressure relief valve: fire pump installation | X | X | X | See 8.3.3.11 and 13.5.6 |
| Pressure relief valve: other than fire pump installation | — | — | X | Verify relief valve is listed or approved for the application and set to the correct pressure |
| Informational components |
| Identification signs | X | X | X | Inspect for compliance with NFPA 13 and 13.3.1 |
Note: for the fire pump relief valve the table cites 8.3.3.11 together with 13.5.6; the Chapter 13 text of NFPA 25-2026 ends at 13.5.5. Fire pump relief valve tasks are covered in the series’ Chapter 8 article.
Frequently Asked Questions
How often are control valves inspected under NFPA 25?
All valves are inspected weekly; valves locked or supervised per the applicable NFPA standards may be inspected monthly and electrically supervised valves quarterly (13.3.2.1). Every control valve is also operated through its full range annually (13.3.3.1), and valve supervisory switches are tested semiannually (13.3.3.5.1).
When is the main drain test done and how is it judged?
Annually at each water supply lead-in to a building water-based system (13.2.2). Where the sole supply passes through a backflow preventer and/or pressure-reducing valves, at least one downstream system is tested quarterly (13.2.2.2). A 10 percent reduction in full flow pressure versus the acceptance test or previous tests must be explained and corrected if necessary (13.2.2.3).
How are waterflow alarm devices tested?
Mechanical alarms (including water motor gongs) are tested quarterly and must sound within 5 minutes (13.2.3.1). Vane, paddle and pressure-switch devices are tested semiannually and must activate within 90 seconds at the flow of one smallest-orifice sprinkler (13.2.3.2). On wet systems the test uses the inspector’s test connection or automated test equipment; blocking the vane or stem to disable a device is prohibited (13.2.3.3, 13.2.3.7.1.1).
How often is a dry pipe valve trip tested?
Every year in warm weather (13.4.5.2.2). Every 3 years and whenever the system is altered the test is done with the control valve fully open and the quick-opening device in service; in other years with the control valve partially open (13.4.5.2.2.2, 13.4.5.2.2.3). On refill the air supply must restore normal pressure within 30 minutes, or 60 minutes in refrigerated spaces below 5 °F (−15 °C) (13.4.5.2.2.4, 13.4.5.2.2.5).
What inspections and tests apply to a fire department connection?
A quarterly ten-point inspection: visibility and access, couplings, caps, gaskets, signs, check valve, automatic drain, clapper, interior obstructions and visible piping (13.8.1). Piping from the connection to the fire department check valve is hydrostatically tested at 150 psi (10 bar) for 2 hours at least every 5 years, with a loss under 5 psi (0.3 bar) (13.8.5, 13.8.5.1). The test is not required where that piping is 10 ft (3.0 m) or less and can be visually inspected inside and out (13.8.5.2).
SprinkCalc — Fire Sprinkler Design Across Three Standards
SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.
Download SprinkCalc on the App Store
MEP Calc — 110+ Engineering Calculators
MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.
Download MEP Calc on the App Store
Standards & References
NFPA 25-2026, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems: Chapter 13 (13.1–13.13), Table 13.1.1.2 and Table 13.13.1. The content of Chapters 4, 8 and 15 and of NFPA 13, NFPA 72 and NFPA 1930 referenced by Chapter 13 is not reproduced here.