This article in the NFPA 25 series covers Chapter 11. In the 2026 edition the chapter is titled “Foam Systems”; going by the title of its summary table, it covers low-, medium- and high-expansion foam systems together with foam-water sprinkler systems. The fire pump is sent to the fire pump checklist, common components and valves to the valves and common components checklist and the water tank to the water storage tank checklist. For deluge systems without foam see the water spray system article, and for closed-head wet systems the sprinkler system article. This article covers inspection, testing and maintenance only, not design. Every line carries its clause number from NFPA 25-2026.
In short: The location and position of foam-water discharge devices are inspected monthly for spray nozzles and annually for sprinklers (Table 11.1.1.2). A foam concentrate sample goes to the manufacturer or an approved laboratory every year (11.3.1). The proportioner gets an annual operational test; the measured induction rate must be within minus 0 to plus 30 percent of the manufacturer’s listed concentration or plus 1 percentage point, whichever is less (11.3.2.5.7). The complete system gets an annual operational (discharge) test (Table 11.1.1.2, 11.3.10). Bladder and concentrate tanks are hydrostatically tested every 10 years (Table 11.1.1.2), underground foam piping is pressure tested at least every 10 years (11.2.11.8) and pressure vacuum vents are serviced every 5 years (11.4.4.6).
A. Scope and general rules
Chapter 11 gives the minimum requirements for routine inspection, testing and maintenance of foam systems installed to NFPA 11 or another approved installation standard (11.1.1.1). Minimum frequencies come from Table 11.1.1.2 (11.1.1.2, 11.2.1).
| Check | Criterion | Clause |
| ☐ Foam solution during inspection and testing | Conducted without inadvertent discharge of foam solution into the system piping | 11.1.1.3 |
| ☐ Fire pumps, water storage tanks, common components and valves | Per Chapter 8, Chapter 9 and Chapter 13 respectively, and Table 11.1.1.2 | 11.1.2 |
| ☐ Alarm and detection devices | Tested and inspected per NFPA 72 | 11.1.3 |
| ☐ Obstruction investigation needed | Follow the procedures of Chapter 14 | 11.1.4 |
| ☐ Impairment to protection | Follow the procedures of Chapter 15 | 11.1.5.1 |
| ☐ Critical deficiency | Appropriate action is taken | 11.1.5.2 |
| ☐ Noncritical deficiency | Appropriate corrective action is taken | 11.1.5.3 |
| ☐ Hose connections | Inspected, tested and maintained per Chapter 6 and Chapter 13 | 11.1.6 |
| ☐ System altered so foam concentrate and components are not compatible | The system is considered impaired | 11.1.7 |
| ☐ Inspection finds a deficiency | Documented and corrected per 11.1.5 | 11.2.2 |
| ☐ Testing or maintenance finds a deficiency | Documented, corrected and retested per 11.1.5 | 11.3.1, 11.4.1.2 |
B. Frequency summary: Table 11.1.1.2
The standard’s summary table for low-, medium- and high-expansion foam and foam-water sprinkler systems is reproduced in full below. Rows marked "—" have no frequency of their own in the table; the frequency and method come from the chapter or standard in the right-hand column. In the maintenance group, “In-line balanced pressure type”, “Line type” and “Proportioning system(s), standard pressure type” appear in the table as sub-headings.
| System/component | Frequency | Reference |
| Inspection |
| Control valve(s) | — | Chapter 13 |
| Deluge/preaction valve(s) | — | Chapter 13 |
| Discharge device location and position (spray nozzle) | Monthly | 11.2.4.1.1 |
| Discharge device location and position (sprinkler) | Annually | 11.2.4.1.1 |
| Drainage in system area | Quarterly | 11.2.7 |
| Fire pump(s) | — | Chapter 8 |
| Foam concentrate pump(s) | — | Chapter 8 |
| Fittings corrosion | Annually | 11.2.11 |
| Fittings damage | Annually | 11.2.11 |
| Foam concentrate storage | Annually | 11.2.9 |
| Gauges | — | Chapter 13 |
| Hangers/braces/supports | Annually | 11.2.12 |
| Pipe corrosion | Annually | 11.2.11 |
| Pipe damage | Annually | 11.2.11 |
| Proportioning system(s), all | Monthly | 11.2.8 |
| Standard pressure proportioning pickup tube | 10 years | 11.2.8.5.2 |
| Line proportioner pickup tubes | Annually | 11.2.8.6.3 |
| Foam tank inspection | Annually | 11.2.9 |
| Proportioning head | Annually | 11.2.8.5.2 |
| Water-powered foam proportioner pump leakage | Monthly | 11.2.8.6.8 |
| Water-powered foam proportioner pump valve position | Monthly | 11.2.8.6.8 |
| Water-powered foam proportioner pump oil level | Semiannually | 11.2.8.6.8 |
| Water-powered foam proportioner pump shock absorbers | Semiannually | 11.2.8.6.8 |
| Water-powered foam proportioning pump filters | Semiannually | 11.2.8.6.8 |
| Strainer(s), mainline | Annually | Chapter 7 |
| Strainer(s), discharge device | After each use | 11.2.6.1 |
| Foam concentrate strainers | Annually | 11.2.6.4 |
| Water supply piping | — | Chapter 7 |
| Water supply tank(s) | — | Chapter 9 |
| Waterflow devices | — | Chapter 13 |
| Supplementary hoses | — | Chapter 6 |
| Auxiliary drain signage | — | Chapter 13 |
| Supplementary hose stream nozzles | — | Chapter 6 |
| Supplementary hose stream storage | — | Chapter 6 |
| Fixed foam discharge outlet | Annually | 11.2.4.2 |
| Vapor seals | Annually | 11.2.4.2.4 |
| Fire department hose connections | — | Chapter 6 |
| Hydraulic design information sign | — | Chapter 4 |
| Foam dam | — | 11.2.15 |
| Pressure foam maker | Annually | 11.2.4.2.5 |
| Rupture disk | Annually | 11.2.4.2.5.5 |
| Alarm devices | — | NFPA 72 |
| Operating instructions and training | Annually | 11.2.17 |
| High pressure cylinders | Annually | 11.2.14 |
| Foam in surrounding space of bladder | Annually | 11.2.9.8 |
| Test |
| Backflow preventer(s) | — | Chapter 13 |
| Complete foam-water sprinkler system(s) (operational test) | Annually | 11.3.10.2 |
| Control valve(s) | — | Chapter 13 |
| Deluge/preaction valve(s) | — | Chapter 13 |
| Detection system | — | NFPA 72 |
| Discharge device location | Annually | 11.3.10.2.7 |
| Discharge device obstruction | Annually | 11.3.10.2.7 |
| Discharge device position | Annually | 11.3.10.2.7 |
| Fixed foam discharge outlet water flow | Annually | 11.3.11 |
| Pressure foam maker water flow | Annually | 11.3.11.6 |
| Fire pump(s) | — | Chapter 8 |
| Foam concentrate pump(s) | — | Chapter 8 |
| Manual actuation device(s) | Annually | 11.3.10.4 |
| Proportioning system(s), all | Annually | 11.3.2 |
| Valve status test | — | Chapter 13 |
| Water supply flow test | — | Chapter 7 |
| Water supply tank(s) | — | Chapter 9 |
| Waterflow alarm devices | — | Chapter 13 |
| Supplementary hose streams | — | Chapter 6 |
| Supplementary hose stream nozzles | — | Chapter 23 of NFPA 1930 |
| Foam concentrate | Annually | 11.3.1.1 |
| Monitors | Annually | 11.3.7 |
| Oscillating monitor’s range of motion | Annually | 11.3.7.2 |
| Oscillating monitor full flow | 5 years | 11.3.7.3 |
| Water-powered foam proportioning pump operation | Quarterly | 11.3.4 |
| Water-powered foam proportioning pump operation at specified rate of flow | Annually | 11.3.4 |
| Water-powered foam proportioning pump screwed connections | Semiannually | 11.3.4 |
| Water-powered foam proportioning pump valves | Semiannually | 11.3.4 |
| Bladder tank hydrostatic test | 10 years | 11.3.5.1 |
| Foam concentrate tank hydrostatic test | 10 years | 11.3.5.1 |
| High pressure cylinder | 5 years/12 years | 11.3.5.4 |
| Underground piping | 10 years | 11.2.11.8 |
| Maintenance |
| Backflow preventer(s) | — | Chapter 13 |
| Bladder sight glass cleaning | 10 years | 11.4.3.2 |
| Check valve(s) | — | Chapter 13 |
| Control valve(s) | — | Chapter 13 |
| Deluge/preaction valves | — | Chapter 13 |
| Detection system | — | NFPA 72 |
| Detector check valve(s) | — | Chapter 13 |
| Fire pump(s) | — | Chapter 8 |
| Foam concentrate strainer(s) | Annually | 11.2.6.4 |
| Metallic atmospheric and pressure vessel storage tanks drain/flush | 10 years | 11.4.3.1 |
| Foam concentrate pump(s) | — | Chapter 8 |
| In-line balanced pressure type | — | — |
| Balancing valve diaphragm | 5 years | 11.4.4.3.3 |
| Line type | — | — |
| Pressure vacuum vents | 5 years | 11.4.4.6 |
| Proportioning system(s), standard pressure type | — | — |
| Ball drip (automatic-type) drain valves | 5 years | 11.4.4.1 |
| Balancing valve diaphragm | 5 years | 11.4.4.2.3 |
| Strainer(s), mainline | — | Chapter 7 |
| Water supply | — | 11.4.2 |
| Water supply tank(s) | — | Chapter 9 |
| Hose valves | — | Chapter 13 |
| Pressure gauges | — | Chapter 13 |
| Fixed foam discharge outlet | Per manufacturer | 11.4.4.8 |
| Pressure foam maker | Per manufacturer | 11.4.4.9 |
| Monitors | — | Chapter 7 |
| Monitor nozzles | — | Chapter 7 |
| Supplementary hoses | — | NFPA 1930 |
| Supplementary hose nozzles | — | NFPA 1930 |
| Rupture disks | Per manufacturer | 11.4.4.9.1 |
| Water-powered foam concentrate proportioning pump shaft lubrication | Semiannually | 11.4.4.5 |
| Water-powered foam concentrate proportioning pump oil change | 5 years | 11.4.4.5 |
| Water-powered foam concentrate proportioning vane replacement | Per manufacturer | 11.4.4.5 |
| Auxiliary drains | — | Chapter 13 |
C. Foam-water discharge devices
| Check | Criterion | Clause |
| ☐ Condition of discharge devices | In place, still aimed in the direction intended by the design, free from external loading and corrosion (visual) | 11.2.4.1.1 |
| ☐ Devices requiring caps or plugs | Caps and plugs confirmed in place visually | 11.2.4.1.2 |
| ☐ Misaligned discharge device | Adjusted (aimed) by visual means | 11.2.4.1.3 |
| ☐ Alignment and coverage of an adjusted device | Observed and verified during the next scheduled flow test | 11.2.4.1.3.1 |
| ☐ Device and concentrate pairing | Verify that unlisted combinations of discharge devices and foam concentrate have not been substituted | 11.2.4.1.4 |
D. Fixed foam discharge outlets and pressure foam makers
| Check | Criterion | Clause |
| ☐ Fixed foam discharge outlets | Inspected annually | 11.2.4.2 |
| ☐ Outlets inaccessible for safety due to process operations or personnel hazards | Inspected during each scheduled shutdown | 11.2.4.2.1 |
| ☐ Outlets on tanks | Visually inspected from ground level or other means | 11.2.4.2.2 |
| ☐ Outlets on external floating roofs | Visually inspected from ground level and from the top of the stairs | 11.2.4.2.3 |
Where a vapor seal is provided, the inspection verifies the seal is present by one of the following means (11.2.4.2.4):
- Visual inspection: approved by the AHJ before the inspection; where an inert gas system is provided, the owner verifies that the makeup gas is sufficient to remove a fixed foam discharge outlet lid (11.2.4.2.4(1)).
- Use of an infrared camera (11.2.4.2.4(2)).
- Gas monitoring: around the outlet lid and air inlet where access to the chamber is provided; at the fire department connection on a semi-fixed foam system; at low-point drains of foam solution piping (11.2.4.2.4(3)).
- Other means allowed and approved by the AHJ and the operator (11.2.4.2.4(4)).
Pressure foam makers
| Check | Criterion | Clause |
| ☐ General | Inspection follows the manufacturer’s specifications | 11.2.4.2.5 |
| ☐ Check valves | Inspected per 13.4.2 | 11.2.4.2.5.1(A) |
| ☐ Before inspection | Air monitoring at truck connections and valved test connections | 11.2.4.2.5.1(B) |
| ☐ Personal protective equipment | Proper PPE used | 11.2.4.2.5.2 |
| ☐ Gate valves | Inspected per 13.3.2.1 | 11.2.4.2.5.3 |
| ☐ Auxiliary drains | Inspected per 11.4.4.13 | 11.2.4.2.5.4 |
| ☐ Rupture disks (where provided) | Inspected per the manufacturer’s requirements | 11.2.4.2.5.5 |
| ☐ System operating valves | In the proper positions determined by the system design | 11.2.4.2.5.6 |
| ☐ Water level in the base of the storage tank | Below the bottom of the foam injection line | 11.2.4.2.5.7 |
| ☐ Foam maker | No signs of physical damage | 11.2.4.2.5.8 |
| ☐ Air inlet | Free of paint, debris or other items that could impede the chamber or foam maker; air inlet screen not damaged or missing | 11.2.4.2.5.9 |
| ☐ Strainers (where equipped) | Inspected per 11.2.6 | 11.2.4.2.5.10 |
E. Monitors, hoselines and water supply
| Check | Criterion | Clause |
| ☐ Monitors, including self-educting monitors | Inspected per 7.2.2.6 | 11.2.4.3 |
| ☐ Pickup tubes on self-educting monitors (where provided) | Inspected for cracking and dry rot | 11.2.4.3.1 |
| ☐ Hoselines | Inspected annually per 6.2.6 or, where applicable, the manufacturer’s instructions | 11.2.4.4 |
| ☐ Hose nozzles | Inspected annually per 6.2.7 | 11.2.4.5 |
| ☐ Water supply systems supplying foam systems | Inspected per Chapter 7, Chapter 8 and Chapter 9 | 11.2.5 |
F. Strainers and drainage
| Check | Criterion | Clause |
| ☐ Individual discharge device basket or screen strainers | Inspected for damaged and corroded parts after each system activation, each operational test and each flushing test | 11.2.6.1 |
| ☐ Mainline strainers | Inspected per 7.2.2.3 | 11.2.6.2 |
| ☐ All strainers | Inspected per the manufacturer’s instructions; cleaned after each use and flow test | 11.2.6.3 |
| ☐ Foam concentrate strainers | Visually verify the blowdown valve is closed and plugged | 11.2.6.4 |
| ☐ Foam concentrate strainers on foam concentrate pump skids | Inspected per Chapter 8 | 11.2.6.4.1 |
| ☐ Area beneath and around a foam-water spray system | Drainage facilities not blocked; retention embankments and dikes in good repair | 11.2.7 |
G. Proportioning system inspection
Proportioning system components are inspected at the frequency in Table 11.1.1.2 (11.2.8.1). Valves being inspected may be open or closed depending on their function; their position is verified against the specified operating conditions (11.2.8.2, 11.2.8.3). The additional items for each proportioner type are (11.2.8.4):
| Proportioner | What the inspection covers | Clause |
| Standard pressure proportioner | Pressure removed first to prevent injury; ball drip valves (automatic drains) free and opened; pickup tube verified intact, undamaged and not clogged by removing the proportioning head | 11.2.8.5.1, 11.2.8.5.2 |
| Bladder tank proportioner | Pressure removed first; water control valves to the foam concentrate tank inspected | 11.2.8.6.1, 11.2.8.6.2 |
| Line proportioner | Strainers per 11.2.6.1; pickup pipes inside the tank for corrosion and plugging | 11.2.8.6.3 |
| Standard balanced pressure proportioner | Strainers per 11.2.6.1; gauges in good operating condition; sensing line valves open; power available to the foam concentrate pump | 11.2.8.6.4 |
| In-line balanced pressure proportioner | Strainers per 11.2.6.1; gauges in good working condition; sensing line valves at the pump unit and at each proportioner station open; power available to the foam concentrate pump | 11.2.8.6.5 |
| Orifice plate proportioner | Strainers per 11.2.6.1; gauges in good working condition; power available to the foam concentrate pump | 11.2.8.6.6 |
| Wide-range proportioner | Reference marks between foam inlet nipple and body aligned (factory setting of the internal metering valve); flow direction arrow correct; foam type on the nameplate consistent with the design and the foam in the tank | 11.2.8.6.7 |
| Water-powered foam concentrate proportioner pump | Valves in the proper operational position per the manufacturer; no leakage on the unit or connections; oil at the appropriate mark; shock absorbers at the water motor/pump coupling evaluated for wear | 11.2.8.6.8 |
| Mobile apparatus proportioner | Proportioning system certification reviewed annually; concentrate type and viscosity unchanged from the one used for certification. If changed, it is an impairment until a new certification is received from the manufacturer | 11.2.8.6.9–11.2.8.6.9.2 |
H. Foam concentrate and storage tanks
| Check | Criterion | Clause |
| ☐ Quantity of concentrate in storage | Satisfies the original design | 11.2.9.1, 11.2.13.3 |
| ☐ Foam concentrate storage tanks | Inspected annually per 9.2.4 for external corrosion and damage | 11.2.9.2 |
| ☐ Expansion domes | Internal inspection annually | 11.2.9.3 |
| ☐ Sediment | Tank inspected for sediment; excessive sediment requires draining and flushing | 11.2.9.4, 11.2.9.4.1 |
| ☐ Tank drained and flushed for maintenance | Internal inspection conducted | 11.2.9.4.2 |
| ☐ Pressure vacuum vent (where provided) | Verified operating freely | 11.2.9.5 |
| ☐ Tank hydrostatic test (where applicable) | Verified as current | 11.2.9.6 |
| ☐ Through-the-wall fittings (where applicable) | Inspected for mechanical damage and leakage | 11.2.9.7 |
| ☐ Bladder tanks | Annual inspection for foam in the water surrounding the bladder | 11.2.9.8 |
| ☐ Concentrate type and viscosity | Unchanged from the concentrate used for system certification and suitable for the current hazard (e.g., alcohol resistant) | 11.2.13.1 |
| ☐ Mixed brands or types | Verify they have not been mixed; if mixed, confirm with the manufacturer(s) that they are compatible and the mix is approved by the AHJ | 11.2.13.1.1, 11.2.13.1.2 |
| ☐ Condition of concentrate | Inspected at least annually for excessive sludging or deterioration | 11.2.13.2 |
| ☐ Tanks and containers | Normally kept full, with space for expansion | 11.2.13.3.1 |
I. Compressed air foam equipment and high-pressure cylinders
| Check | Criterion | Clause |
| ☐ Compressed air foam–generating equipment and accessories | Inspected annually | 11.2.10.1 |
| ☐ CAF discharge devices | Visually inspected annually for mechanical damage | 11.2.10.2 |
| ☐ Cylinder pressure | Per the manufacturer’s specifications for the system | 11.2.14.1.1 |
| ☐ Hydrostatic test date of CAF high-pressure cylinders | Inspected | 11.2.14.1.2 |
| ☐ Cylinder more than 5 years past its last test | Not recharged without hydrostatic test and remarking | 11.2.14.1.2.1 |
| ☐ Cylinder in continuous service without discharging | May stay in service up to 12 years, then discharged and retested before return to service | 11.2.14.1.2.2 |
J. Pipe, fittings, hangers and supports
| Check | Criterion | Clause |
| ☐ Foam system pipe and fittings | Inspected annually | 11.2.11 |
| ☐ Pipe and fittings inaccessible for safety due to process operations | Inspected during each scheduled shutdown | 11.2.11.1 |
| ☐ Condition | Free of mechanical damage, leakage and corrosion; findings documented and corrected per 11.1.5 | 11.2.11.2, 11.2.11.2.1 |
| ☐ External corrosion detrimental to performance, or mechanical damage, on normally dry piping | Pressure test per NFPA 11 | 11.2.11.2.2 |
| ☐ External loads | No materials resting on or hanging from the pipe | 11.2.11.3 |
| ☐ Misalignment and trapped sections | Inspected | 11.2.11.4 |
| ☐ Auxiliary drain signage | Inspected per 13.4.5.1.2 | 11.2.11.5 |
| ☐ Rubber-gasketed fittings | Location and condition inspected | 11.2.11.6 |
| ☐ Aboveground foam piping | Examined for condition and proper drainage | 11.2.11.7 |
| ☐ Underground foam solution and concentrate piping | Hydrostatic test at the installation standard’s system design pressure at least every 10 years; other AHJ-approved frequencies, or other means per Chapter 14, allowed | 11.2.11.8–11.2.11.8.2 |
| ☐ Foam concentrate lines | No galvanized pipe, per 4.7.1.3 of NFPA 11 | 11.2.11.9 |
| ☐ Hangers, braces and supports | Inspected annually from floor level; those inaccessible due to process operations at each scheduled shutdown | 11.2.12, 11.2.12.1 |
| ☐ Damaged, loose or unattached hangers and supports | Replaced or refastened | 11.2.12.2, 11.2.12.3 |
K. Foam dams, deluge valves and operating instructions
| Check | Criterion | Clause |
| ☐ Foam dams | Inspected per this subsection for the applicable tank construction | 11.2.15.1 |
| ☐ Foam dams inaccessible for safety due to process operations | Inspected during each scheduled shutdown | 11.2.15.2 |
| ☐ Foam dam on an external floating roof | At least annually, visually: dam sound and properly attached; drainage slots free and clear of debris; earthing shunts free of corrosion and damage | 11.2.15.3 |
| ☐ Foam dam on an internal floating roof | Inspected when the tank is brought down for inspection and maintenance per industry standards; earthing shunts for corrosion and damage | 11.2.15.4.1, 11.2.15.4.2 |
| ☐ Deluge valves | Inspected per Chapter 13 | 11.2.16 |
| ☐ Operating instructions and training | System operation, deactivation, acceptance/commissioning test results, maintenance instructions and layouts in place at control equipment, with copies on file | 11.2.17 |
L. Testing: foam concentrate sample
| Check | Criterion | Clause |
| ☐ Foam concentrate testing | Annually | 11.3.1.1 |
| ☐ Sample | Sent to the manufacturer or an approved testing laboratory for quality condition testing | 11.3.1.2 |
| ☐ Foam type and brand known | Quality testing confirms the product meets the manufacturer’s specifications | 11.3.1.3 |
M. Proportioner tests
An operational test of the foam proportioner is conducted annually (11.3.2). Where approved by the AHJ, surrogate test liquids may be used in lieu of foam concentrate, with alternative test methods permitted provided system pressures and flows remain as described in the chapter and meet the design requirements (11.3.2.1, 11.3.2.1.1).
| Check | Criterion | Clause |
| ☐ Concentration of the foam solution sample | Verified by one of: digital refractometer; digital electric conductivity, handheld or online with electronic data acquisition; calibrated listed digital flowmeters (total flow and foam concentrate); other means acceptable to the AHJ | 11.3.2.2 |
| ☐ Data to collect | Static water pressure; residual water pressure at the control valve and at the remote reference point; actual discharge rate; consumption rate of foam-producing material; concentration of the foam solution | 11.3.2.3 |
| ☐ Compressed air foam systems, any discharge test | Static water pressure; residual water pressure at the control device; system air pressure; concentration of the foam solution | 11.3.2.4 |
| ☐ Foam solution or premix testing | Arranged with as little loss of foam concentrate as possible | 11.3.2.4.1 |
| ☐ Proportioning equipment for foam-water sprinkler systems | Verified by flow tests; flow through suitable test outlet connections allowed if it meets design flow conditions and is acceptable to the AHJ; the alternative methods of 11.3.2.1 also allowed | 11.3.2.5–11.3.2.5.1.1 |
| ☐ Water pressure at the proportioner inlet | Meets the design condition at the maximum required system flow; maximum supply pressure does not exceed the maximum allowable working pressure of any proportioning component | 11.3.2.5.2, 11.3.2.5.2.1 |
| ☐ Closed-head systems (including wide-range or variable-range proportioners) | Induction rate (percent concentration) verified at the maximum system design flow and at a flow equal to the four most hydraulically located sprinkler heads discharging | 11.3.2.5.3, 11.3.2.5.3.1 |
| ☐ Open-head deluge systems | Induction rate verified at the maximum system design flow | 11.3.2.5.4 |
| ☐ Multiple proportioners designed to operate individually | Each verified by a separate flow test | 11.3.2.5.5 |
| ☐ Multiple proportioners designed to operate simultaneously | Each verified while the required number discharge simultaneously | 11.3.2.5.6 |
| ☐ Acceptance criterion | Induction rate, as a percentage of foam solution flow (water plus concentrate), within minus 0 to plus 30 percent of the manufacturer’s listed concentration or plus 1 percentage point, whichever is less | 11.3.2.5.7 |
N. Mobile apparatus proportioners and water-powered proportioner pumps
| Check | Criterion | Clause |
| ☐ Mobile apparatus proportioner testing | Verify the proportioning system meets 18.11.2 of NFPA 1900 | 11.3.3.1 |
| ☐ Concentrate type or viscosity changed without recertification per 18.10.1 of NFPA 1900 | System type tested and recertified by the proportioning system manufacturer | 11.3.3.2 |
Testing of water-powered foam concentrate proportioner pumps includes these steps (11.3.4):
- Operate the water motor driven pump per the manufacturer’s specification.
- Operate the manual air bleed valve, pressure relief valves and operational valves per the manufacturer’s specification.
- Check filters for contamination per the manufacturer’s specifications.
- Check screwed connections for tightness.
- Operate the pump to the installed specifications for rate of flow and conduct a proportioning test per the manufacturer’s procedures and specifications.
O. Hydrostatic tests, monitors and hoses
| Check | Criterion | Clause |
| ☐ Standard pressure proportioner tanks and bladder tanks | Hydrostatic test per Table 11.1.1.2 (every 10 years) | 11.3.5.1 |
| ☐ Hydrostatic test of a bladder tank | Creates no pressure differential across the bladder | 11.3.5.2 |
| ☐ Exterior of the bladder tank | Inspected for leaks during the hydrostatic test at system working pressure | 11.3.5.3 |
| ☐ High-pressure cylinders after system activation | Hydrostatically tested if more than 5 years since the last test | 11.3.5.4.1 |
| ☐ High-pressure cylinders with no discharge | Hydrostatic test every 12 years | 11.3.5.4.2 |
| ☐ Water supply for foam systems | Tested per Chapter 7, Chapter 8 and Chapter 9 | 11.3.6 |
| ☐ Monitors and monitor nozzles | Tested per 7.3.3 | 11.3.7.1 |
| ☐ Water-powered oscillating monitors | Tested per the manufacturer’s specifications, but not less than annually | 11.3.7.2 |
| ☐ Full-flow test of oscillating monitors | Every 5 years, verifying range of travel and set spray pattern; alternate frequencies where AHJ-approved | 11.3.7.3, 11.3.7.3.1 |
| ☐ Supplementary hoses | Tested per NFPA 1930; hoses made to other standards per the manufacturer’s specifications | 11.3.8.1, 11.3.8.2 |
| ☐ Hose nozzles | Tested per Chapter 23 of NFPA 1930 | 11.3.9 |
P. Discharge device operational test (annual discharge test)
The frequency of discharge device operational tests comes from Table 11.1.1.2 (11.3.10): the complete system and discharge device location, obstruction and position are tested annually.
| Check | Criterion | Clause |
| ☐ Test preparation | Precautions taken to prevent damage to property | 11.3.10.1 |
| ☐ Discharge would be hazardous or conflict with local requirements | Approved alternate method to achieve full-flow conditions allowed | 11.3.10.1.1 |
| ☐ System response | Foam-water sprinkler system responds as designed, automatically and manually; procedures simulate anticipated emergency events | 11.3.10.2.1, 11.3.10.2.2 |
| ☐ Full-flow test of foam-water deluge systems | May use water only in lieu of foam | 11.3.10.2.3 |
| ☐ Plugs or caps on discharge devices | Full-flow test verifies they release as intended | 11.3.10.2.4 |
| ☐ Automatic fire detection | Operates within NFPA 72 requirements for the detector type when exposed to a test source; response time recorded | 11.3.10.2.5, 11.3.10.2.5.1 |
| ☐ Open discharge devices | Time lapse between detection operation and water delivery to the protected area recorded | 11.3.10.2.6 |
| ☐ Discharge patterns | From all open devices, observed to be unimpeded by debris, correctly positioned and giving adequate coverage; devices may differ in orifice size and type | 11.3.10.2.7.1, 11.3.10.2.7.2 |
| ☐ Pressure readings | Recorded at the most hydraulically demanding discharge device and at the main control valve; compared with the original hydraulic design pressures | 11.3.10.2.8.1–11.3.10.2.8.3 |
| ☐ Multiple systems | Maximum number of systems expected to operate in a fire tested simultaneously to check the water supply and foam concentrate pump | 11.3.10.3 |
| ☐ Manual actuation devices | Tested annually | 11.3.10.4 |
| ☐ Return to service | After the full-flow test, system returned to service and the concentrate tank replenished to design level | 11.3.10.5 |
Q. Waterflow tests of fixed foam discharge outlets
| Check | Criterion | Clause |
| ☐ Annual waterflow test | Water discharged through each fixed foam discharge outlet at least annually to confirm outlets and foam solution feed lines are not obstructed; alternative methods and frequencies identified in the standard or approved by the AHJ allowed | 11.3.11.1, 11.3.11.1.1 |
| ☐ During flow | Residual pressure of the most remote device recorded and compared with the original hydraulic calculations; air inlet observed for water backflow | 11.3.11.1.2, 11.3.11.1.3 |
Cone roof tanks
| Check | Criterion | Clause |
| ☐ Outlets inaccessible for safety due to process operations | Tested during each scheduled shutdown | 11.3.11.2.1 |
| ☐ Test plan | AHJ reviews and approves the plans for a waterflow test through the outlet | 11.3.11.2.2 |
| ☐ Means to isolate the outlet provided | Waterflow tests through test connections on the foam solution risers at the tank shell allowed with AHJ approval | 11.3.11.2.2.1 |
| ☐ Waterflow test not possible | Supply piping may be visually inspected per Chapter 14 | 11.3.11.2.2.2 |
| ☐ Makeup gas | Where possible, the AHJ verifies it is sufficient to remove the outlet lid for the duration of the flow test | 11.3.11.2.2.3 |
| ☐ Personnel accessing outlets on in-service product tanks | Proper PPE provided | 11.3.11.2.2.4 |
| ☐ Waterflow testing possible | Water not allowed to enter the storage tank | 11.3.11.2.2.5 |
| ☐ Tanks operating at elevated temperatures | Consideration given to conducting flow tests | 11.3.11.2.2.6 |
Internal floating roofs or geodesic dome roofs
| Check | Criterion | Clause |
| ☐ Outlets inaccessible for safety due to process operations | Tested during each scheduled shutdown | 11.3.11.3(1) |
| ☐ Personnel on in-service product tanks | Proper PPE | 11.3.11.3(2) |
| ☐ Waterflow testing possible | Water not allowed to enter the tank except as permitted in 11.3.11.3.1 | 11.3.11.3(3) |
| ☐ Frequency of waterflow testing onto the roof | Aligned with tank outages and industry inspection frequencies: short outages where product is not removed and the roof is not accessible require no test; test when the outage permits observation of water discharge and foam dam operation; foam dam tested per 11.3.11.5 | 11.3.11.3(4) |
| ☐ Means to isolate the outlet provided | Waterflow tests through test connections on the risers at the tank shell allowed as approved by the AHJ | 11.3.11.3.1 |
External floating roofs
External floating roofs have rim seal protection by either above-the-seal or below-the-seal foam application (11.3.11.4).
| Check | Criterion | Clause |
| ☐ Below-the-seal: inaccessible outlets | Tested during each scheduled shutdown | 11.3.11.4.1(1) |
| ☐ Below-the-seal: personnel on in-service tank | Proper PPE | 11.3.11.4.1(2) |
| ☐ Below-the-seal: in-service tank | Waterflow injection between the seal not permitted | 11.3.11.4.1(3) |
| ☐ Below-the-seal: proper isolation and flow test means provided | Waterflow tests conducted with water discharge on the roof | 11.3.11.4.1(4) |
| ☐ Below-the-seal: roof drains | Open and monitored per 11.3.11.5 | 11.3.11.4.1(5) |
| ☐ Below-the-seal: test frequency | Aligned with tank outages and industry inspection frequencies; the test plan is AHJ-approved and considers outlet operating pressure, potential seal damage from waterflow or impingement, and drainage; short outages without product removal or roof access require no test | 11.3.11.4.1(6) |
| ☐ Above-the-seal | Waterflow tests annually with discharge onto the roof; roof drains open before testing; foam dam tested per 11.3.11.5 | 11.3.11.4.2 |
| ☐ Foam dams | Observed for proper retention of water during the waterflow test; roof drains verified functioning properly | 11.3.11.5.1, 11.3.11.5.2 |
Pressure foam makers
| Check | Criterion | Clause |
| ☐ General | Testing follows the manufacturer’s recommendations | 11.3.11.6 |
| ☐ Gate valves | Tested per 13.3.3.1; the AHJ approves operation of the gate valve downstream of the rupture disk or check valve | 11.3.11.6.1, 11.3.11.6.1.1 |
| ☐ Annual water flow | Water discharged through each fixed foam discharge outlet at least annually; alternative methods and frequencies per the standard or AHJ approval allowed | 11.3.11.6.2, 11.3.11.6.2.1 |
| ☐ Before the flow test | Rupture discs removed; gate valves downstream of the check valve verified closed | 11.3.11.6.2.2, 11.3.11.6.2.3 |
| ☐ During the flow test | Inlet and outlet pressure at the foam maker noted and confirmed within the acceptable range per the design and manufacturer; air inlet observed for water backflow | 11.3.11.6.2.4, 11.3.11.6.2.5 |
R. Maintenance: tanks, proportioners and concentrate pumps
Foam systems are maintained per the chapters covering the specific component parts (11.4.1.1); the water supply is maintained per Chapter 7, Chapter 8 and Chapter 9 (11.4.2).
| Check | Criterion | Clause |
| ☐ Metallic atmospheric and pressure vessel tanks: excessive sediment | Tank drained and flushed | 11.4.3.1.1 |
| ☐ Foam concentrate storage tank | Drained and flushed (Table 11.1.1.2: every 10 years) | 11.4.3.1.2 |
| ☐ Drained concentrate | May be salvaged and reused | 11.4.3.1.3 |
| ☐ Bladder tank sight glass (where provided) | Removed and cleaned | 11.4.3.2 |
| ☐ Standard pressure proportioners | Ball drip (automatic-type) drain valves disassembled, cleaned and reassembled | 11.4.4.1 |
| ☐ Standard and in-line balanced pressure proportioners: pump | Concentrate pump operated; concentrate circulated back to the tank | 11.4.4.2.1, 11.4.4.3.1 |
| ☐ Foam pumps, drive trains and drivers | Serviced per the manufacturer’s instructions and frequency, but at intervals not exceeding 5 years | 11.4.4.2.2, 11.4.4.3.2 |
| ☐ Diaphragm balancing valve | Flushed through the diaphragm section with water or concentrate until fluid appears clear or new | 11.4.4.2.3, 11.4.4.3.3 |
| ☐ Mobile apparatus proportioning systems | Maintained per 18.9.4.2 of NFPA 1900 | 11.4.4.4 |
| ☐ Water-powered proportioner pumps | Lubricate the proportioning pump shaft per the manufacturer; change oil in the water-driven pump; change vanes when appropriate per the manufacturer | 11.4.4.5 |
S. Pressure vacuum vent maintenance (every 5 years)
These steps are performed on pressure vacuum vents every 5 years (11.4.4.6):
- Remove the vent from the expansion dome (11.4.4.6.1).
- Inspect that the opening is not blocked and dirt or foreign objects do not enter the tank (11.4.4.6.2).
- Remove the vent bonnet (11.4.4.6.3).
- Lift out the vacuum valve and pressure valve (11.4.4.6.4).
- Flush the vent body internally and wash the vacuum and pressure valves thoroughly (11.4.4.6.5).
- Check that the screen is not clogged; avoid hard, pointed objects to clear it (11.4.4.6.6, 11.4.4.6.6.1).
- If the liquid has become excessively gummy or solidified, soak the body and parts in hot soapy water (11.4.4.6.7).
- Turn the body upside down and drain thoroughly (11.4.4.6.8).
- Dry the parts in a warm, dry area or with an air hose (11.4.4.6.9).
- Spray the parts with a light PTFE coating and reassemble; no oil of any type for lubrication (11.4.4.6.10, 11.4.4.6.11).
- Replace the bonnet and turn the vent upside down slowly a few times to check freedom of the moving parts (11.4.4.6.12).
- Attach the vent to the tank expansion dome (11.4.4.6.13).
T. Maintenance of other components
| Check | Criterion | Clause |
| ☐ Monitors and monitor nozzles | Maintained per 7.4.3 | 11.4.4.7 |
| ☐ Fixed foam discharge outlets: foam chambers and foam makers | Maintained per the manufacturer’s specifications | 11.4.4.8 |
| ☐ Vapor seals | Maintained per the manufacturer’s specifications | 11.4.4.8.1 |
| ☐ Pressure foam makers | Maintained per the manufacturer’s specifications | 11.4.4.9 |
| ☐ Rupture disks | Maintained and replaced per the disk manufacturer’s specifications | 11.4.4.9.1 |
| ☐ Strainers | Maintained per Chapter 7 | 11.4.4.10 |
| ☐ Supplementary hoses | Maintained per NFPA 1930 or the manufacturer’s instructions | 11.4.4.11 |
| ☐ Supplementary hose stream nozzles | Maintained per NFPA 1930 | 11.4.4.12 |
| ☐ Auxiliary drains | Maintained per 13.4.5.3.2 to 13.4.5.3.3 | 11.4.4.13 |
U. When a component is adjusted, repaired or replaced: Table 11.4.4.14.1
Whenever a foam system component is adjusted, repaired, reconditioned or replaced, the action in Table 11.4.4.14.1 is performed (11.4.4.14.1). Where the original installation standard differs from the cited one, the appropriate installing standard may be used (11.4.4.14.2). These actions do not require a design review (11.4.4.14.3). Rows without an “X” simply refer to the chapter shown on the right.
| Component | Adjust | Repair/recondition | Replace | Required action |
| Water delivery components |
| Discharge devices | X | — | X | Inspect for leaks at system working pressure; inspect for impairments at orifice |
| Fire department connections | X | X | X | See Chapter 13 |
| Manual release | X | X | X | Operational test; inspect for leaks at system working pressure; test all alarms |
| Pipe and fittings on systems with automatic foam-water sprinklers | X | X | X | Hydrostatic test in conformance with NFPA 13 |
| Pipe and fittings on systems with fixed foam discharge outlets | X | X | X | Operational flow test |
| Foam components |
| Ball drip (automatic-type) drain valves | — | — | — | See Chapter 13 |
| Foam concentrate | X | — | X | Submit a sample for laboratory analysis for conformance with manufacturer’s specifications |
| Foam concentrate pump | — | — | — | See Chapter 8 |
| Foam concentrate strainer(s) | — | — | — | See Chapter 13 |
| Atmospheric foam concentrate tank | X | X | X | Inspect condition and repair as appropriate |
| Foam concentrate bladder tank | X | X | X | Inspect water jacket for presence of foam concentrate |
| Proportioning system(s) | X | X | X | Conduct flow test and inspect proportioning with an approved test device |
| Water supply tank(s) | — | — | — | See Chapter 9 |
| Alarm and supervisory components |
| Detection system | X | X | X | Operational test for conformance with NFPA 13 and/or NFPA 72 |
| Pressure-switch-type waterflow | X | X | X | Operational test using inspector’s test connection |
| Valve supervisory device | — | — | X | Test for conformance with NFPA 13 and/or NFPA 72 |
| Vane-type waterflow | X | X | X | Operational test using inspector’s test connections |
| Water motor gong | — | — | X | Operational test using inspector’s test connection |
| Status-indicating components |
| Gauges | X | — | X | Verify at 0 psi (0 bar) and system working pressure; see Chapter 13 regarding calibration |
| Testing and maintenance components |
| Auxiliary drains | X | X | X | Inspect for leaks at system working pressure |
| Inspector’s test connection | X | X | X | Inspect for leaks at system working pressure |
| Main drain | X | X | X | Full-flow main drain test |
| Structural components |
| Hanger/seismic bracing | X | X | X | Inspect for conformance with NFPA 13 |
| Pipe stands | X | X | X | Inspect for conformance with NFPA 13 |
| Informational components |
| General information | X | X | X | Inspect for conformance with NFPA 11 and NFPA 13 |
| Hydraulic information sign | X | X | X | Inspect for conformance with NFPA 11 and NFPA 13 |
| Valve signs | X | X | X | Inspect for conformance with NFPA 11 and NFPA 13 |
Frequently Asked Questions
How often is foam concentrate tested under NFPA 25?
Annually. A sample is sent to the manufacturer or an approved testing laboratory for quality condition testing; where the foam type and brand are known, the test confirms the product meets the manufacturer’s specifications (11.3.1.1–11.3.1.3). Concentrate is also inspected at least annually for excessive sludging or deterioration (11.2.13.2).
What is the acceptance criterion for a proportioner test?
The induction rate, as a percentage of foam solution flow, must be within minus 0 to plus 30 percent of the manufacturer’s listed concentration or plus 1 percentage point, whichever is less (11.3.2.5.7). Concentration is measured with a digital refractometer, digital conductivity, calibrated listed digital flowmeters or other means acceptable to the AHJ (11.3.2.2).
At which flows is proportioning verified on a closed-head foam-water system?
At the maximum system design flow and at a flow equal to the four most hydraulically located sprinkler heads discharging; the same two points apply to wide-range or variable-range proportioners (11.3.2.5.3, 11.3.2.5.3.1). Open-head deluge systems are verified at the maximum design flow only (11.3.2.5.4).
Can the annual discharge test use water instead of foam?
Yes. Full-flow discharge from foam-water deluge systems may be tested with water only in lieu of foam (11.3.10.2.3). Where discharge would be hazardous or conflict with local requirements, an approved alternate full-flow method is allowed (11.3.10.1.1). After the test the concentrate tank is replenished to design level (11.3.10.5).
Which periodic tests apply to foam tanks and piping?
Standard pressure proportioner tanks and bladder tanks are hydrostatically tested every 10 years (11.3.5.1, Table 11.1.1.2). Underground foam solution and concentrate piping is hydrostatically tested at system design pressure at least every 10 years (11.2.11.8). Metallic concentrate tanks are drained and flushed every 10 years (Table 11.1.1.2, 11.4.3.1), and pressure vacuum vents are serviced every 5 years (11.4.4.6).
SprinkCalc — Fire Sprinkler Design Across Three Standards
SprinkCalc covers hazard classification, design density and area, K-factor selection, water demand and hydraulic calculations for NFPA 13, FM Global and BS EN 12845 in a single iOS app, and exports a professional PDF report.
Download SprinkCalc on the App Store
MEP Calc — 110+ Engineering Calculators
MEP Calc bundles 110+ engineering modules in one iOS app: 21 fire calculations plus heating, cooling, HVAC, plumbing, steam and natural gas.
Download MEP Calc on the App Store
Standards & References
NFPA 25-2026, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems: Chapter 11 (11.1–11.4), Table 11.1.1.2 and Table 11.4.4.14.1. The content of Chapters 4, 6, 7, 8, 9, 13, 14 and 15 and of NFPA 11, NFPA 13, NFPA 72, NFPA 1900 and NFPA 1930 referenced by Chapter 11 is not reproduced here.